Electrical Permit in Birmingham, Alabama
Permit required
Yes, a permit is required
Before installing, altering, repairing or replacing any electrical wiring or equipment.
Issued byCity of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
By Mario Bailey, verified against official sources
Quick answer
Birmingham requires an electrical permit from PEP to erect, install, enlarge, alter, repair, remove, convert or replace any electrical system, under the 2020 National Electrical Code as adopted by the City's Technical Code. Low voltage wiring (telecommunication, data, alarm, lawn sprinkler controls and similar) needs a separate low voltage permit instead.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing, altering, repairing or replacing any electrical wiring or equipment.
What an electrical permit costs in Birmingham
How to apply in Birmingham
In Birmingham, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- For Birmingham, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- For Birmingham, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division sets the exact checklist for Birmingham.
Where to apply in Birmingham:
City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
- City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203
- Phone: (205) 254-2904
- Email: OnlinePermitCenter@birminghamal.gov
Inspections and closing out your permit
In Birmingham, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- In Birmingham: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- In Birmingham: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- In Birmingham: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- In Birmingham: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- In Birmingham: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- In Birmingham: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- In Birmingham: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Birmingham permit portal or by phone at (205) 254-2904.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Birmingham
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing, altering, repairing or replacing any electrical wiring or equipment.
- Budget the fee. Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). Low voltage work is a separate Low Voltage permit: minimum $125.00, "$9.50 per $1000 worth of installation cost" (105.8.3.2). Official fee schedule.
- Apply. In Birmingham, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Birmingham permit portal.
- Keep the office details handy. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Phone: (205) 254-2904. Address: City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203.
- Plan for inspections. In Birmingham, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Birmingham?
- Birmingham requires an electrical permit from PEP to erect, install, enlarge, alter, repair, remove, convert or replace any electrical system, under the 2020 National Electrical Code as adopted by the City's Technical Code. Low voltage wiring (telecommunication, data, alarm, lawn sprinkler controls and similar) needs a separate low voltage permit instead. Always confirm with the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division before starting.
- How much does an electrical permit cost in Birmingham?
- Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "ELECTRICAL PERMIT FEES ... $9.50 per $1000.00 valuation for alterations", "Minimum permit fee ... $125.00". Article V also sets the general rule that "the minimum charge for any permit will be no less than one-hundred-twenty-five dollars ($125.00)". Work begun before the permit pays a doubled fee (section 104.2). Low voltage work is a separate Low Voltage permit: minimum $125.00, "$9.50 per $1000 worth of installation cost" (105.8.3.2). See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Birmingham?
- You can apply through the Birmingham permit portal or contact the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Birmingham?
- Under Alabama law (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)): Yes. The home builder licensing law does not apply to owners acting as their own contractor and providing all material supervision themselves when building or improving a one- or two-family home on their own property for their own occupancy or use and not offered for sale (34-14A-6(5)a). The exemption cannot be transferred, including through a power of attorney, and selling or offering the home for sale within one year after completion is presumptive evidence it was built for sale (34-14A-6(5)b). Owners may also do their own electrical work on their premises (34-36-13(a)(5)) and their own plumbing in a building they own or occupy (34-37-15), though plumbing work stays subject to inspection under state law and local ordinances. Whether an owner may pull a local building permit is set by the city or county. Confirm how Birmingham applies this before you apply.
From the Library
What else needs a permit in Birmingham
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before any bathroom work beyond painting, papering, flooring, cabinets, countertops and... | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Deck Permit | Permit required | Any size | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| EV Charger Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Fence Permit | Permit required | Any size | ...1, Chapter 9, Article VIII, Section 3 (Miscellaneous Fees): "Fence Permit"... |
| HVAC Permit | It depends | Before installing, replacing, enlarging or relocating a heating, cooling or ventilation... | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Plumbing Permit | It depends | length of water service repaired or replaced, and no more than 50% of the service | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Pool Permit | Permit required | Any size | Electrical and plumbing permits: $9.50 per $1,000.00 valuation, minimum $125.00 each... |
| Roof Replacement Permit | It depends | Before reroofing a home in a historic or design review district, and before any reroof... | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Shed Permit | It depends | floor area of an accessory structure for a one- or two-family dwelling; the exemption applies only when the Planning Division approves it | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Solar Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Water Heater Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Birmingham documents; the office above sets the local rules.
How this electrical permit page for Birmingham was verified. 2 official sources: birminghamal.gov, s3.us-east-2.amazonaws.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Alabama localities