Deck Permit in Birmingham, Alabama
Permit required
Yes, a permit is required
Before building, enlarging or repairing a deck.
Issued byCity of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
By Mario Bailey, verified against official sources
Quick answer
Birmingham requires a building permit to erect, construct, enlarge, alter or repair any structure, and its exemption list has no deck exemption of any size or height. The City deleted the IRC's own Chapter 1, so the model code's exemption for small, low decks does not apply in Birmingham.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
If a contractor builds your deck, they usually handle the permit as part of the job. Compare a few bids before you commit.
Compare deck contractor quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before building, enlarging or repairing a deck.
What a deck permit costs in Birmingham
How to apply in Birmingham
In Birmingham, a residential deck permit application is a set of construction documents that show what will be built and prove it meets the IRC deck provisions. In practice that means a scaled site plan locating the deck and its setbacks, plus deck plans and structural details covering the footings, posts, beams, joists, ledger, guards, and stairs.
What most deck permit applications include:
- For Birmingham, a permit application identifying the work, the deck's size (square footage), and whether electrical work such as lights or receptacles is included, submitted for plan review before construction begins (IRC R106).
- For Birmingham, a scaled site plan (for example 1/4 inch to 1 foot) showing the new deck's location relative to the house, its overall length and width, and dimensioned distances from the deck to all property lines and other structures so required setbacks can be verified (IRC R106.1.1).
- For Birmingham, a deck plan drawn to scale showing overall dimensions and the framing layout: joist size, spacing, span, and species; beam size and span; post size and height; and footing or pier size and depth (IRC R507.4 posts, R507.5 beams, R507.6 joists, R507.3 footings).
- For Birmingham, a section or side elevation with connection details showing the ledger attachment to the house band joist with flashing, the fastener or bolt schedule, joist hangers, post-to-beam and post-to-footing connections, and the required lateral load connection (IRC R507.9 ledger connection, R507.9.2 lateral connection, R507.2.4 flashing).
- Footing sizing derived from tributary area, the soil bearing value, and design loads per IRC Table R507.3.1, with footings shown bearing on undisturbed soil at the frost depth required by the jurisdiction (IRC R507.3).
- Details for the guards required where the walking surface is more than 30 inches above grade, and for the stairs and handrails, showing guard height and opening limits, stair riser and tread dimensions, and handrail location (IRC R312 guards, R311.7 stairs and handrails).
- For designs that fall outside the prescriptive R507 tables (for example multi-story or stacked decks, or a ledger attached to a cantilever), engineered and stamped structural plans are submitted in place of the prescriptive details (IRC R507.1 and R301).
General submittal guidance from IRC R106.1.1 (construction documents) and IRC R507 (exterior decks), 2021 IRC. Source. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division sets the exact checklist for Birmingham.
Where to apply in Birmingham:
City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division
- City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203
- Phone: (205) 254-2904
- Email: OnlinePermitCenter@birminghamal.gov
Inspections and closing out your permit
In Birmingham, deck work is inspected in sequence as it is built: the footings before concrete is placed, the framing before the decking boards go down, and a final inspection once the deck is complete. Each stage checks the items that would be hidden or unsafe if missed.
- Footing or pier inspection in Birmingham: after the holes are dug and any forms or reinforcing are set but before concrete is placed, the inspector checks footing depth and diameter, a flat undisturbed bearing surface, and that the holes are free of water (IRC R109.1.1 foundation inspection; R507.3 footings).
- Framing inspection in Birmingham: after the deck is framed but before the decking conceals it, the inspector verifies the ledger attachment and its flashing, the fastener and bolt schedule, joist hangers and metal connectors, post-to-beam and post-to-footing connections, and the lateral load connection; call it before decking is installed (IRC R109.1.4 frame inspection; R507.9 ledger and flashing).
- Final inspection in Birmingham: after the deck is complete and before it is used, the inspector confirms guard height and opening limits (a 4 inch sphere must not pass, 4 3/8 inch at stairs), stair riser and tread dimensions, handrail height and graspability where there are 4 or more risers, stair landings, and required stair lighting (IRC R109.1.6 final inspection; R312 guards, R311.7 stairs and handrails).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Birmingham permit portal or by phone at (205) 254-2904.
Inspection sequence from IRC R109 (inspections: R109.1.1 footing before concrete, R109.1.4 frame, R109.1.6 final), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Deck Permit checklist for Birmingham
- Confirm the requirement. Yes, a permit is required. Usually needed: Before building, enlarging or repairing a deck.
- Budget the fee. Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50 per $1000 valuation", with a minimum charge for any permit of $125.00. Work begun before the permit pays a doubled fee (section 104.2). Official fee schedule.
- Apply. In Birmingham, a residential deck permit application is a set of construction documents that show what will be built and prove it meets the IRC deck provisions. In practice that means a scaled site plan locating the deck and its setbacks, plus deck plans and structural details covering the footings, posts, beams, joists, ledger, guards, and stairs. Start at the Birmingham permit portal.
- Keep the office details handy. City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Phone: (205) 254-2904. Address: City Hall, Room 210, 710 20th Street North, Birmingham, AL 35203.
- Plan for inspections. In Birmingham, deck work is inspected in sequence as it is built: the footings before concrete is placed, the framing before the decking boards go down, and a final inspection once the deck is complete. Each stage checks the items that would be hidden or unsafe if missed.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a deck permit in Birmingham?
- Birmingham requires a building permit to erect, construct, enlarge, alter or repair any structure, and its exemption list has no deck exemption of any size or height. The City deleted the IRC's own Chapter 1, so the model code's exemption for small, low decks does not apply in Birmingham. Always confirm with the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division before starting.
- How much does a deck permit cost in Birmingham?
- Technical Code of the City of Birmingham, 2024 (effective 10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50 per $1000 valuation", with a minimum charge for any permit of $125.00. Work begun before the permit pays a doubled fee (section 104.2). See the official fee schedule for current amounts.
- Where do you apply for a deck permit in Birmingham?
- You can apply through the Birmingham permit portal or contact the City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a deck permit themselves in Birmingham?
- Under Alabama law (Ala. Code 34-14A-6(5); 34-36-13(a)(5); 34-37-15(a)(5), (b)): Yes. The home builder licensing law does not apply to owners acting as their own contractor and providing all material supervision themselves when building or improving a one- or two-family home on their own property for their own occupancy or use and not offered for sale (34-14A-6(5)a). The exemption cannot be transferred, including through a power of attorney, and selling or offering the home for sale within one year after completion is presumptive evidence it was built for sale (34-14A-6(5)b). Owners may also do their own electrical work on their premises (34-36-13(a)(5)) and their own plumbing in a building they own or occupy (34-37-15), though plumbing work stays subject to inspection under state law and local ordinances. Whether an owner may pull a local building permit is set by the city or county. Confirm how Birmingham applies this before you apply.
From the Library
What else needs a permit in Birmingham
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before any bathroom work beyond painting, papering, flooring, cabinets, countertops and... | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Electrical Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| EV Charger Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Fence Permit | Permit required | Any size | ...1, Chapter 9, Article VIII, Section 3 (Miscellaneous Fees): "Fence Permit"... |
| HVAC Permit | It depends | Before installing, replacing, enlarging or relocating a heating, cooling or ventilation... | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Plumbing Permit | It depends | length of water service repaired or replaced, and no more than 50% of the service | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Pool Permit | Permit required | Any size | Electrical and plumbing permits: $9.50 per $1,000.00 valuation, minimum $125.00 each... |
| Roof Replacement Permit | It depends | Before reroofing a home in a historic or design review district, and before any reroof... | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Shed Permit | It depends | floor area of an accessory structure for a one- or two-family dwelling; the exemption applies only when the Planning Division approves it | ...10/1/2024), Article V: "Building permit fees shall be determined at a rate of $9.50... |
| Solar Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
| Water Heater Permit | Permit required | Any size | $9.50 per $1000.00 valuation for alterations", "Minimum permit fee .. |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Birmingham documents; the office above sets the local rules.
How this deck permit page for Birmingham was verified. 2 official sources: birminghamal.gov, s3.us-east-2.amazonaws.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Birmingham Department of Planning, Engineering & Permits (PEP), Permitting & Inspection Division. Rules change; confirm before you build. How we verify.