HVAC Permit in Memphis, Tennessee
Permit required
Yes, a permit is required
Before installing, altering, repairing or replacing heating, air conditioning, ventilating or exhaust equipment
By Mario Bailey, verified against official sources
Quick answer
A mechanical permit is required for residential HVAC work in Memphis, with no published size or tonnage floor. The joint Memphis and Shelby County administrative code requires a permit to erect, install, alter, refurbish or repair air conditioning, heating, mechanical ventilating, blower or exhaust systems, and the joint amendments to the 2021 International Residential Code delete the model code's mechanical exempt work list outright, so a one or two family dwelling has no residential carve out to fall back on. Fees for a single family house are computed from the contract price using a floor of $1,000.00 per ton. Apply through the Develop 901 Citizen Portal under Residential Mechanical Permit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing, altering, repairing or replacing heating, air conditioning, ventilating or exhaust equipment
What an HVAC permit costs in Memphis
How Memphis compares in Tennessee
No Tennessee jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Memphisthis page | Permit required | M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000... |
| Nashville | Permit required | Flat minimum of $75 per gas/mechanical permit plus $32 per 100,000 Btuh or... |
| Williamson County | Permit required | Mechanical Permit Fee Schedule: $10.00 permit fee plus $10.00 for the first... |
How to apply in Memphis
A residential HVAC (mechanical) permit application must identify the covered equipment and scope of work, since installing, altering, or replacing a heating or cooling system is regulated work that cannot start until the application is submitted and the permit issued. The equipment itself must be picked by a real sizing calculation rather than a rule of thumb.
What most HVAC permit applications include:
- A mechanical permit is required before anyone may install, alter, repair, remove, convert, or replace a heating, ventilating, or air conditioning system regulated by the code, and the work may not begin until the application is submitted and the permit is issued (IRC R105.1).
- The application identifies the specific equipment being installed, such as a furnace, heat pump, or air conditioner, since the unit must be installed according to its listing and the manufacturer's installation instructions (IRC M1401.1).
- The proposed equipment location must leave the clearances needed to clean coils and replace filters, blowers, motors, and controls after installation (IRC M1401.2).
- The application carries the equipment sizing basis: ACCA Manual J building loads and Manual S equipment selection, or another approved sizing method, not a rule of thumb (IRC M1401.3).
- For a split system, the work covered by the permit includes refrigerant suction line insulation, since the piping is inspected against that standard once installed (IRC M1411.6).
General submittal guidance from International Residential Code (IRC), 2021 edition, Chapter 1 (Permits) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) sets the exact checklist for Memphis.
Where to apply in Memphis:
Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)
- 6465 Mullins Station Road, Memphis, TN 38134
- Phone: 901-222-8300
- Email: develop901@memphistn.gov
Inspections and closing out your permit
Mechanical work gets a rough in inspection after the ductwork, refrigerant lines, and gas piping are in but before they are covered or concealed, followed by a final inspection that confirms the equipment operates correctly and its clearances, combustion air, and condensate disposal are in place. A straight equipment changeout with no new ductwork commonly gets a single final inspection instead of a separate rough in trip.
- Rough inspection of the mechanical and gas systems must be made before the work is covered or concealed, before fixtures or appliances are set or installed, and before the framing inspection (IRC R109.1.2).
- Where a cooling coil is added to an existing warm air furnace, the rough in confirms the coil is not installed upstream of the heat exchanger unless the furnace is listed for it, and that the blower can handle the added static pressure (IRC M1411.2).
- The rough in and final both confirm the appliance access opening and working space are large enough to service the unit (IRC M1305.1).
- At final inspection, the inspector verifies the equipment has adequate combustion air, with openings kept clear for the distance the code requires (IRC M1402.3).
- Final inspection also checks that the condensate line drains to an approved point of disposal with the required slope and does not create a nuisance (IRC M1411.3).
- For a straight equipment changeout with no new ductwork, many permit offices require only a single final inspection, while a new installation still gets a rough in inspection before the final (common local inspection practice).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Memphis permit portal or by phone at 901-222-8300.
Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Required Inspections) and Chapter 14 (Heating and Cooling Equipment and Appliances). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your HVAC Permit checklist for Memphis
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing, altering, repairing or replacing heating, air conditioning, ventilating or exhaust equipment.
- Budget the fee. M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000 valuation $15.00 then $8.00 for each additional $1,000 under $1,000,000, M-4 minimum permit fee $15.00, and M-3.2.1 SINGLE FAMILY RESIDENTS ONLY, mechanical permit fees shall be based on total valuation (contract price) based on a minimum $1,000.00 per ton, per the 2022 Fee Schedule, Mechanical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule. Official fee schedule.
- Apply. A residential HVAC (mechanical) permit application must identify the covered equipment and scope of work, since installing, altering, or replacing a heating or cooling system is regulated work that cannot start until the application is submitted and the permit issued. The equipment itself must be picked by a real sizing calculation rather than a rule of thumb. Start at the Memphis permit portal.
- Keep the office details handy. Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Phone: 901-222-8300. Address: 6465 Mullins Station Road, Memphis, TN 38134.
- Plan for inspections. Mechanical work gets a rough in inspection after the ductwork, refrigerant lines, and gas piping are in but before they are covered or concealed, followed by a final inspection that confirms the equipment operates correctly and its clearances, combustion air, and condensate disposal are in place. A straight equipment changeout with no new ductwork commonly gets a single final inspection instead of a separate rough in trip.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an HVAC permit in Memphis?
- A mechanical permit is required for residential HVAC work in Memphis, with no published size or tonnage floor. The joint Memphis and Shelby County administrative code requires a permit to erect, install, alter, refurbish or repair air conditioning, heating, mechanical ventilating, blower or exhaust systems, and the joint amendments to the 2021 International Residential Code delete the model code's mechanical exempt work list outright, so a one or two family dwelling has no residential carve out to fall back on. Fees for a single family house are computed from the contract price using a floor of $1,000.00 per ton. Apply through the Develop 901 Citizen Portal under Residential Mechanical Permit. Always confirm with the Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) before starting.
- How much does an HVAC permit cost in Memphis?
- M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000 valuation $15.00 then $8.00 for each additional $1,000 under $1,000,000, M-4 minimum permit fee $15.00, and M-3.2.1 SINGLE FAMILY RESIDENTS ONLY, mechanical permit fees shall be based on total valuation (contract price) based on a minimum $1,000.00 per ton, per the 2022 Fee Schedule, Mechanical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule. See the official fee schedule for current amounts.
- Where do you apply for an HVAC permit in Memphis?
- You can apply through the Memphis permit portal or contact the Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) directly. The links are listed on this page.
- Can a homeowner pull an HVAC permit themselves in Memphis?
- Under Tennessee law (T.C.A. 62-6-103; Tenn. Comp. R. & Regs. 0780-02-23-.01(1)(i), -.05(3), -.05(4)(b)2.; Tenn. Comp. R. & Regs. 0780-02-01-.05(2)(a)): Tennessee lets a homeowner act as their own builder. Under T.C.A. 62-6-103, as the State Fire Marshal's Office explains it, an owner may construct a single residence once every two years for personal use without a contractor's license, so long as the home is not for resale, lease, or rent, and anyone the homeowner hires whose portion of the work is $25,000 or more must be a licensed contractor. In state permit areas the owner pulls a property owner's permit, limited by rule to one per 24 month period, and the work is subject to the same inspections and fees as a contractor's job; proof of licensure is waived at permit purchase only when the owner personally performs the work. For electrical work, a homeowner may wire their own residence only after obtaining a residential property owner's electrical permit, which covers only the applicant and immediate family, does not authorize help from anyone unlicensed, and is limited to one per 12 month period unless the owner lost the home to fire or windstorm. Confirm how Memphis applies this before you apply.
From the Library
What else needs a permit in Memphis
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | 200 square feet of deck area, taken with a 30 inch height above grade at any point, no attachment to the dwelling and no service to the exit door required by Section R311.4 | CONSTRUCTION/REPAIR/ALTERATION TO DECKS, SPAS AND SIMILAR STRUCTURES $50.00, plus the APP. |
| Electrical Permit | Permit required | Not specified | E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00, E-6.2 EXISTING... |
| Fence Permit | Permit required | Not specified | RESIDENTIAL FENCE PERMIT 400 LINEAR FT OR LESS $25.00 and RESIDENTIAL FENCE PERMIT 401... |
| Plumbing Permit | It depends | whether the work only stops a leak or clears a stoppage without replacing, rearranging or removing pipe, valve or fixture components | Permit issuance $20.00, plus $4.00 for issuing each permit (data processing) and a $1.00... |
| Pool Permit | It depends | prefabricated swimming pools, measured by the depth of the pool | POOL OR RETAINING WALL $5.00/1,000 (NO MAX) with a $70.00 minimum, per the 2022 Fee... |
| Roof Replacement Permit | It depends | whether decking, structural members or equipment supports are modified | No residential roofing line item. |
| Shed Permit | Permit required | Not specified | DETATCHED ACCESSORY BUILDINGS 400 SQ. |
| Solar Permit | Permit required | Not specified | No solar line item. |
HVAC Permit in other Tennessee localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Memphis documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare HVAC Permit requirements across Tennessee localities
Permit office
Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)
901-222-8300Permit portalTennessee rule changes
- Metro Nashville posts a current codes fee schedule, replacing the 2010 sheet
BL2022-1215 (Metro Fee Schedule Legislation) ·
Compare
HVAC Permit across Tennessee