Electrical Permit in Memphis, Tennessee
Permit required
Yes, a permit is required
Before any residential electrical installation, alteration, repair, removal, conversion or replacement
By Mario Bailey, verified against official sources
Quick answer
Electrical permits in Memphis come from the local joint building department, not from the state. This is the opposite of the arrangement in unincorporated Williamson County, where electrical permits are issued by the Tennessee Department of Commerce and Insurance through the CORE system; Memphis and Shelby County adopted their own 2020 Memphis and Shelby County Electrical Code, based on the 2020 National Electrical Code with local amendments, and the Office of Construction Code Enforcement issues and inspects the permits itself. A permit is required for essentially all residential electrical work, with only three narrow exemptions. Permits are issued to licensed or registered contractors, with a homeowner exception that requires proof the house is the applicant's principal residence and a score of at least 70 percent on an examination approved by the Electrical Code Board.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before any residential electrical installation, alteration, repair, removal, conversion or replacement
What an electrical permit costs in Memphis
How Memphis compares in Tennessee
No Tennessee jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Memphisthis page | Permit required | E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00, E-6.2... |
| Nashville | Permit required | Flat minimum of $75 per permit with itemized add-on charges for circuits... |
| Williamson County | Permit required | State-issued via the TN CORE system: a $5 issuing fee plus ampere-based... |
How to apply in Memphis
In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) sets the exact checklist for Memphis.
Where to apply in Memphis:
Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)
- 6465 Mullins Station Road, Memphis, TN 38134
- Phone: 901-222-8300
- Email: develop901@memphistn.gov
Inspections and closing out your permit
Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Memphis permit portal or by phone at 901-222-8300.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Memphis
- Confirm the requirement. Yes, a permit is required. Usually needed: Before any residential electrical installation, alteration, repair, removal, conversion or replacement.
- Budget the fee. E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00, E-6.2 EXISTING RESIDENTIAL 1&2 FAMILY OCCUPANCIES $30.00 for 1 to 5 circuits and $45.00 for over 5 circuits providing 2 inspections, E6.3 service, feeder, or panel replacement $50.00, E6.4 in ground residential swimming pool $100.00, E6.5 residential low voltage $30.00, per the 2022 Fee Schedule, Electrical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule. Official fee schedule.
- Apply. In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Memphis permit portal.
- Keep the office details handy. Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Phone: 901-222-8300. Address: 6465 Mullins Station Road, Memphis, TN 38134.
- Plan for inspections. Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an electrical permit in Memphis?
- Electrical permits in Memphis come from the local joint building department, not from the state. This is the opposite of the arrangement in unincorporated Williamson County, where electrical permits are issued by the Tennessee Department of Commerce and Insurance through the CORE system; Memphis and Shelby County adopted their own 2020 Memphis and Shelby County Electrical Code, based on the 2020 National Electrical Code with local amendments, and the Office of Construction Code Enforcement issues and inspects the permits itself. A permit is required for essentially all residential electrical work, with only three narrow exemptions. Permits are issued to licensed or registered contractors, with a homeowner exception that requires proof the house is the applicant's principal residence and a score of at least 70 percent on an examination approved by the Electrical Code Board. Always confirm with the Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) before starting.
- How much does an electrical permit cost in Memphis?
- E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00, E-6.2 EXISTING RESIDENTIAL 1&2 FAMILY OCCUPANCIES $30.00 for 1 to 5 circuits and $45.00 for over 5 circuits providing 2 inspections, E6.3 service, feeder, or panel replacement $50.00, E6.4 in ground residential swimming pool $100.00, E6.5 residential low voltage $30.00, per the 2022 Fee Schedule, Electrical Permit and Inspection Fees Schedule. Work commencing before permit issuance is charged double fee. All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule. See the official fee schedule for current amounts.
- Where do you apply for an electrical permit in Memphis?
- You can apply through the Memphis permit portal or contact the Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in Memphis?
- Under Tennessee law (T.C.A. 62-6-103; Tenn. Comp. R. & Regs. 0780-02-23-.01(1)(i), -.05(3), -.05(4)(b)2.; Tenn. Comp. R. & Regs. 0780-02-01-.05(2)(a)): Tennessee lets a homeowner act as their own builder. Under T.C.A. 62-6-103, as the State Fire Marshal's Office explains it, an owner may construct a single residence once every two years for personal use without a contractor's license, so long as the home is not for resale, lease, or rent, and anyone the homeowner hires whose portion of the work is $25,000 or more must be a licensed contractor. In state permit areas the owner pulls a property owner's permit, limited by rule to one per 24 month period, and the work is subject to the same inspections and fees as a contractor's job; proof of licensure is waived at permit purchase only when the owner personally performs the work. For electrical work, a homeowner may wire their own residence only after obtaining a residential property owner's electrical permit, which covers only the applicant and immediate family, does not authorize help from anyone unlicensed, and is limited to one per 12 month period unless the owner lost the home to fire or windstorm. Confirm how Memphis applies this before you apply.
From the Library
What else needs a permit in Memphis
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | 200 square feet of deck area, taken with a 30 inch height above grade at any point, no attachment to the dwelling and no service to the exit door required by Section R311.4 | CONSTRUCTION/REPAIR/ALTERATION TO DECKS, SPAS AND SIMILAR STRUCTURES $50.00, plus the APP. |
| Fence Permit | Permit required | Not specified | RESIDENTIAL FENCE PERMIT 400 LINEAR FT OR LESS $25.00 and RESIDENTIAL FENCE PERMIT 401... |
| HVAC Permit | Permit required | Not specified | M-0 fee issuance cost per permit $20.00, M-3.1 fee for the first $1,000 valuation $15.00... |
| Plumbing Permit | It depends | whether the work only stops a leak or clears a stoppage without replacing, rearranging or removing pipe, valve or fixture components | Permit issuance $20.00, plus $4.00 for issuing each permit (data processing) and a $1.00... |
| Pool Permit | It depends | prefabricated swimming pools, measured by the depth of the pool | POOL OR RETAINING WALL $5.00/1,000 (NO MAX) with a $70.00 minimum, per the 2022 Fee... |
| Roof Replacement Permit | It depends | whether decking, structural members or equipment supports are modified | No residential roofing line item. |
| Shed Permit | Permit required | Not specified | DETATCHED ACCESSORY BUILDINGS 400 SQ. |
| Solar Permit | Permit required | Not specified | No solar line item. |
Electrical Permit in other Tennessee localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Memphis documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Electrical Permit requirements across Tennessee localities
Permit office
Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)