Solar Permit in Memphis, Tennessee
Permit required
Yes, a permit is required
Before installing, altering or replacing a rooftop or ground mounted photovoltaic system
Quick answer
Memphis and Shelby County publish no solar specific permit type, checklist or fee line, but rooftop photovoltaic work is not exempt. The 2020 Memphis and Shelby County Electrical Code, the joint local adoption of the National Electrical Code, requires a permit before anyone erects, installs, enlarges, alters, repairs, removes, converts or replaces any electrical system or equipment regulated by that code, and its short exempt list covers only decorative lighting, receptacle reinstallation and laboratory wiring. The locally amended residential code exempt list does not mention solar either, and the reroofing exemption does not help because racking modifies equipment supports. Zoning is separate: the Unified Development Code makes building mounted photovoltaic systems an accessory use permitted in all zoning districts and exempts panels of 4 square feet or less from those zoning regulations.
- Issued by
- Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)
- Phone
- 901-222-8300
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your Tennessee Board for Licensing Contractors license active, and under which business name? Verify it on search.cloud.commerce.tn.gov.
Tennessee's owner-builder rule (T.C.A. 62-6-103; Tenn. Comp. R. & Regs. 0780-02-23-.01(1)(i), -.05(3), -.05(4)(b)2.; Tenn. Comp. R. & Regs. 0780-02-01-.05(2)(a)) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Memphis
- Fee schedule in force
- Official scheduleRead .
- No solar line item.
- Residential photovoltaic work is billed on the electrical schedule: E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00, and E-6.2 EXISTING RESIDENTIAL 1&2 FAMILY OCCUPANCIES at $30.00 for 1 to 5 circuits or $45.00 for over 5 circuits, which provides 2 inspections, per the 2022 Fee Schedule, Electrical Permit and Inspection Fees Schedule.
- All fees exclude an administrative charge of $4.00 and a residential surcharge of $1.00, so $5.00 is added to the residential total, per the 2022 Fee Schedule.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in Memphis
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement)
- 6465 Mullins Station Road, Memphis, TN 38134
- Phone: 901-222-8300
- Email: develop901@memphistn.gov
Solar Permit in Memphis compared with nearby Tennessee localities
| Locality | Permit needed? | Threshold | What each Tennessee schedule says | Verified |
|---|---|---|---|---|
| Memphis | Permit required | Any size | Residential photovoltaic work is billed on the electrical schedule: E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00; the schedule has the rest | |
| Nashville | Permit required | Any size | $75 minimum permit fee | |
| Williamson County | Not confirmed | Not confirmed | The structural mounting permit bills under the Section B101 valuation table starting at $15 for the first $1,000 plus $5 per additional thousand |
Your Solar Permit checklist for Memphis
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: develop901.com: construction enforcement.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Memphis permit portal.
- Keep the office details handy. Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Phone: 901-222-8300. Email: develop901@memphistn.gov. Address: 6465 Mullins Station Road, Memphis, TN 38134.
Compiled from the official sources on this page. Last checked .
What else needs a permit in Memphis
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | 200 square feet of deck area, taken with a 30 inch height above grade at any point, no attachment to the dwelling and no service to the exit door required by Section R311.4 | See schedule |
| Electrical Permit | Permit required | Any size | E-0 fee issuance cost per permit $20.00, E3.1 minimum fee $15.00; the schedule has the rest |
| Fence Permit | Permit required | Any size | See schedule |
| HVAC Permit | Permit required | Any size | M-0 fee issuance cost per permit $20.00; the schedule has the rest |
| Plumbing Permit | It depends | whether the work only stops a leak or clears a stoppage without replacing, rearranging or removing pipe, valve or fixture components | Permit issuance $20.00, plus $4.00 for issuing each permit (data processing) and a $1.00 residential surcharge; the schedule has the rest |
| Pool Permit | It depends | prefabricated swimming pools, measured by the depth of the pool | POOL OR RETAINING WALL $5.00/1,000 (NO MAX) with a $70.00 minimum, per the 2022 Fee Schedule, Building Section, Residential Fees; the schedule has the rest |
| Roof Replacement Permit | It depends | whether decking, structural members or equipment supports are modified | See schedule |
| Shed Permit | Permit required | Any size | See schedule |
Frequently asked questions
- Do you need a solar permit in Memphis?
- Yes, before installing, altering or replacing a rooftop or ground mounted photovoltaic system. If you are unsure how that applies to your project, call the permit office at 901-222-8300 before you start.
- How much does a solar permit cost in Memphis?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Aug 2026. For the figure on your own project, call the permit office at 901-222-8300.
- Where do you apply for a solar permit in Memphis?
- You can apply through the Memphis permit portal or contact the Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement) directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Memphis?
- Under Tennessee law (T.C.A. 62-6-103; Tenn. Comp. R. & Regs. 0780-02-23-.01(1)(i), -.05(3), -.05(4)(b)2.; Tenn. Comp. R. & Regs. 0780-02-01-.05(2)(a)): Tennessee lets a homeowner act as their own builder. Under T.C.A. 62-6-103, as the State Fire Marshal's Office explains it, an owner may construct a single residence once every two years for personal use without a contractor's license, so long as the home is not for resale, lease, or rent, and anyone the homeowner hires whose portion of the work is $25,000 or more must be a licensed contractor. In state permit areas the owner pulls a property owner's permit, limited by rule to one per 24 month period, and the work is subject to the same inspections and fees as a contractor's job; proof of licensure is waived at permit purchase only when the owner personally performs the work. For electrical work, a homeowner may wire their own residence only after obtaining a residential property owner's electrical permit, which covers only the applicant and immediate family, does not authorize help from anyone unlicensed, and is limited to one per 12 month period unless the owner lost the home to fire or windstorm. Confirm how Memphis applies this before you apply.
From the Library
Solar Permit in other Tennessee localities
Everything above, sourced
How this solar permit page for Memphis was verified. 2 official sources: develop901.com, shelbycountytn.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Memphis and Shelby County Division of Planning and Development, Office of Construction Code Enforcement (Construction Enforcement). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page