Tennessee / Nashville

Solar Permit in Nashville, Tennessee

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

An Electrical Photovoltaic (PV) permit is required for residential solar installations in Nashville. Structural capacity verification and a scaled roof plan showing panel layout are required. The department makes best efforts to review completed residential applications within 30 days. Minimum permit fee is $75.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Nashville, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before installing a residential solar PV system

What solar permit costs in Nashville

$75 minimum permit fee.

Official fee schedule

How to apply in Nashville

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Metro Nashville Codes and Building Safety Department sets the exact checklist for Nashville.

Where to apply in Nashville:

Metro Nashville Codes and Building Safety Department

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Nashville permit portal or by phone at 615-862-6500.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Nashville

In 2024, Nashville authorized permits for 6,799 new residential housing units (2,662 single-family, 4,137 in multi-family buildings), valued at $1.2B, down from11,158 the year before. That works out to about 10.1 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 671,295.

About Nashville

Nashville has about 333,074 housing units. The median home is valued at $383,100, against a median household income of $75,197. About 53% of homes are owner-occupied, and the typical home was built around 1985.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a solar permit in Nashville?
An Electrical Photovoltaic (PV) permit is required for residential solar installations in Nashville. Structural capacity verification and a scaled roof plan showing panel layout are required. The department makes best efforts to review completed residential applications within 30 days. Minimum permit fee is $75. Always confirm with the Metro Nashville Codes and Building Safety Department before starting.
How much does a solar permit cost in Nashville?
$75 minimum permit fee. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Nashville?
You can apply through the Nashville permit portal or contact the Metro Nashville Codes and Building Safety Department directly. The links are listed on this page.

From the Library

What else needs a permit in Nashville

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedBilled as a residential building permit at $5 per $1,000 of total valuation plus a $25...
Electrical PermitPermit requiredNot specifiedFlat minimum of $75 per permit with itemized add-on charges for circuits, panels, servi...
Fence PermitNo permit neededNot specifiedNo permit fee;
HVAC PermitPermit requiredNot specifiedFlat minimum of $75 per gas/mechanical permit plus $32 per 100,000 Btuh or fraction for...
Patio PermitPermit requiredNot specifiedUses the same residential building permit rate as decks, $5 per $1,000 of valuation plu...
Plumbing PermitPermit requiredNot specifiedFlat minimum of $75 per permit plus $11 per plumbing fixture, per Metro Code 16.12.220...
Pool PermitPermit requiredNot specifiedBilled as a residential building permit at $5 per $1,000 of valuation plus a $25 zoning...
Roof Replacement PermitNo permit neededNot specifiedRoof work beyond normal maintenance (repairs over 33 percent of roof area) is billed as...
Shed PermitIt dependsaccessory structures 100 sq ft or larger require a permit; structures under 100 sq ft may not require a permitSheds of 100 sq ft or more are billed as a residential building permit at $5 per $1,000...

Solar Permit in other Tennessee localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with Metro Nashville Codes and Building Safety Department. Rules change; confirm before you build. How we verify.