Patio Permit in Greensboro, North Carolina

It depends

Sometimes, depending on the project

Before building an elevated patio that needs retaining walls or foundation walls, and before roofing over an existing patio or porch.

From an official source Verified City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections)

By Mario Bailey, verified against official sources

Quick answer

Greensboro publishes no stand-alone patio answer, but it does draw one line for patios. Its Residential Plan Review page treats an elevated patio that requires retaining walls or foundation walls as an addition needing a site plan, and treats any new roofed area, including a new roof over an existing patio, the same way. Against that, the city's general rules are that a building permit is required any time you cover new ground, and that construction costing $40,000 or less needs no permit unless it falls into one of six listed carve-outs, none of which obviously reaches a plain at-grade concrete slab. Treat a raised or roofed patio as permitted work and call Development Services at 336-373-2155 before pouring a flat slab, because the city does not publish a verdict on that case.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before building an elevated patio that needs retaining walls or foundation walls, and before roofing over an existing patio or porch.

What a patio permit costs in Greensboro

Line item
patio permitBy formulaBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Greensboro compares in North Carolina

No North Carolina jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
CharlottePermit requiredNo patio-specific line item is published on either side.
Greensborothis pageIt dependsBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit...
Mecklenburg CountyIt dependsTrade permit priced off total construction value with a $59.70 minimum for...
Wake CountyPermit requiredPlanning and Development Fees, as of 1/1/22: 'Zoning Permit (Land use, Home...

How to apply in Greensboro

Applying for a patio permit means submitting a site plan and framing plans for a roofed patio cover, since a cover is treated as its own permitted structure regardless of size. A plain concrete or paver patio slab at or near grade is, by contrast, often exempt from that same building permit requirement.

What most patio permit applications include:

  • Filing a permit application with the local building department, which only the property owner or an authorized agent may sign, since a patio cover is treated as its own permitted structure regardless of size (IRC R105.1).
  • A scaled site plan showing the new patio cover's size and location relative to the house and other existing structures, with dimensioned distances to all property lines so required setbacks can be verified before the permit is approved (IRC R106.2).
  • Construction documents such as a framing plan and elevation, showing rafter or beam sizes and spacing, the distance between supporting posts, and the method of attachment to the house, drawn with enough clarity for the building official to confirm the work will conform to the code (IRC R106.1).
  • For the roof structure itself, plans showing compliance with the patio cover appendix's structural limits, such as adequate footing sizes for the applied post loads, since a shallow slab on grade may substitute for a deeper footing only in limited cases up to about 750 pounds of load per post (IRC Appendix AH, Section AH105.2).
  • By contrast, an at grade concrete or paver patio that is not attached to the dwelling and stays within the code's small flatwork thresholds, similar to a sidewalk, driveway, or low deck under 200 square feet and 30 inches high, commonly needs no building permit at all, so none of the plan review steps above apply (IRC R105.2).

General submittal guidance from 2021 International Residential Code (IRC), Sections R105 and R106, with Appendix AH Patio Covers (named Appendix H in the 2012, 2015, and 2018 editions). Source. City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections) sets the exact checklist for Greensboro.

Where to apply in Greensboro:

City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections)

  • Development Services, Melvin Municipal Office Building, Upper Ground Level, Room UG10, 300 W. Washington St., Greensboro, NC 27401
  • Phone: 336-373-2155
  • Email: DevelopmentServices2@greensboro-nc.gov

Inspections and closing out your permit

A permitted patio cover follows the same footing, frame, and final inspection sequence used for any small accessory structure, since the posts and roof framing have to be checked before they are covered and again once the work is done. An at grade patio slab that qualifies as exempt flatwork usually needs no building inspection at all, because inspections only attach to work that required a permit in the first place.

  1. A footing inspection once the excavation, forms, and any reinforcing steel are in place but before concrete is poured, confirming the posts supporting a patio cover will bear on adequate footings (IRC R109.1.1).
  2. A frame inspection after the rafters, beams, posts, and any required rough in work are in place but before the roof sheathing or covering material conceals them, since a solid patio cover roof cannot be signed off once it is covered without this check (IRC R109.1.4).
  3. A final inspection once all permitted work, including roofing and post anchorage, is complete, which the code requires before the structure may be used (IRC R109.1.6).
  4. An at grade concrete or paver patio that qualifies as exempt flatwork under the permit rules is not subject to any of these inspection stages, since the inspection sequence only attaches to work that required a permit in the first place (IRC R105.2).
  5. Each inspection has to be requested by the permit holder rather than happening automatically, and the approved plans and permit card need to be on site and available when the inspector arrives (IRC R109.3).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Greensboro permit portal or by phone at 336-373-2155.

Inspection sequence from 2021 International Residential Code (IRC), Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a patio permit in Greensboro?
Greensboro publishes no stand-alone patio answer, but it does draw one line for patios. Its Residential Plan Review page treats an elevated patio that requires retaining walls or foundation walls as an addition needing a site plan, and treats any new roofed area, including a new roof over an existing patio, the same way. Against that, the city's general rules are that a building permit is required any time you cover new ground, and that construction costing $40,000 or less needs no permit unless it falls into one of six listed carve-outs, none of which obviously reaches a plain at-grade concrete slab. Treat a raised or roofed patio as permitted work and call Development Services at 336-373-2155 before pouring a flat slab, because the city does not publish a verdict on that case. Always confirm with the City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections) before starting.
How much does a patio permit cost in Greensboro?
Building Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'. The residential Alt/Add column charges the $85.00 minimum on construction values up to $11,000 and rises above that ($88.00 at $12,000, $127.00 at $25,000, $302.00 at $100,000, then '$100,000 - 500,000 = $302.00 PLUS $2.00 PER $1,000'). 'STATE LICENSED CONTRACTORS: Add $10.00 to all Residential Permits'. 'DOUBLE PERMIT FEE: BUILDING PERMIT FEES WILL BE DOUBLED IF WORK IS BEGUN BEFORE SECURING A PERMIT'. The department page adds that 'The minimum permit fee for building, electrical, mechanical, and plumbing permits has increased from $75 to $85.'. See the official fee schedule for current amounts.
Where do you apply for a patio permit in Greensboro?
You can apply through the Greensboro permit portal or contact the City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections) directly. The links are listed on this page.
Can a homeowner pull a patio permit themselves in Greensboro?
Under North Carolina law (N.C. Gen. Stat. 87-1(a), 87-1(b)(2), 87-14(a)(1), 160D-1113, 160D-1115): A North Carolina homeowner may pull the permit and do the work. G.S. 87-1(a) reaches general contracting only where the cost of the undertaking is $40,000 or more, and G.S. 87-1(b)(2) then exempts a person who constructs or alters a building on land that person owns, provided the building is intended solely for occupancy by that person and his family after completion and the person complies with G.S. 87-14. There is no outright ban on selling, but there is a look-back that works like one: if the building is not occupied solely by the person and his family for at least 12 months following completion, the statute presumes the person did not intend the building solely for that occupancy, which defeats the exemption. G.S. 87-14(a)(1) requires an owner claiming the exemption to execute a verified affidavit attesting that they own the property, that they will personally superintend and manage all aspects of the construction and will not delegate that duty to anyone unlicensed, and that they will be personally present for all inspections required by the State Building Code unless a licensed architect sealed the plans. The inspector transmits that affidavit to the Licensing Board, and if the Board determines the exemption was not available the building permit is revoked under G.S. 160D-1115. The exemption removes the general contractor license requirement only. It does not exempt the work from permits or inspections, and G.S. 160D-1113 provides that when a permit is held by an owner exempt under 87-1(b)(2), no inspection may be conducted without the owner present unless an architect sealed the plans. Confirm how Greensboro applies this before you apply.

From the Library

What else needs a permit in Greensboro

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsNot specifiedBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'.
Electrical PermitIt dependsNot specifiedElectrical Permit Fee Schedule, Document #4100 dated 7/16/24: 'Minimum Permit Fee 85.00'.
HVAC PermitPermit requiredNot specifiedMechanical Permit Fee Schedule, Document #4200 dated 7/16/24: 'Minimum Inspection Fee $...
Plumbing PermitIt dependsNot specifiedPlumbing Permit Fee Schedule, Document #4300 dated 7/16/24: 'Minimum Permit/Inspection...
Pool PermitPermit requiredNot specifiedBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'.
Roof Replacement PermitIt dependscost of the construction, installation, repair, replacement or alterationBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'.
Shed PermitIt dependslength, width or height of the accessory buildingBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'.
Solar PermitPermit requiredNot specifiedBuilding Permit Fee Schedule, Document #1005 dated 12/19/24: 'Minimum permit fee - $85'.

Patio Permit in other North Carolina localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Greensboro documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with City of Greensboro Engineering and Inspections Department, Development Services Division (Building Inspections). Rules change; confirm before you build. How we verify.