Bathroom Remodel Permit in Martin County, Florida
It depends
Sometimes, depending on the project
Before work begins.
Issued byMartin County Building Department
By Mario Bailey, verified against official sources
Quick answer
Martin County lists kitchen and bathroom remodels among the projects that require a permit, while painting, flooring and similar finishing work, cabinetry, and repair of toilets, sinks and faucets need none. A remodel that moves plumbing, adds circuits or alters walls needs a permit; finishes alone do not.
Typical threshold: Finish work and fixture repairs versus a remodel.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Remodel contractors usually handle the permits as part of the job. Comparing a few bids before you commit is the useful next step.
Compare bathroom remodel quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before work begins.
What a bathroom remodel permit costs in Martin County
How Martin County compares in Florida
How to apply in Martin County
In Martin County, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt.
What most bathroom remodel permit applications include:
- Creating a new bathroom or toilet room, or altering, moving, or replacing a plumbing, electrical, gas, or mechanical system as part of the remodel, is regulated work that requires a permit before work starts, usually filed as separate building, electrical, mechanical, and plumbing permit applications submitted together (IRC R105.1).
- For Martin County, the permit application itself must identify and describe the work, describe the site, state the intended use, be accompanied by construction documents, state the valuation of the work, and be signed by the applicant or their agent (IRC R105.3).
- Those construction documents have to show the location, nature, and extent of the proposed work, which in practice means a scaled existing and proposed floor plan showing every fixture, outlet, switch, and vent fan, including the code-mandated clearances around fixtures such as the water closet (IRC R106.1.1; R307.1 fixture clearances).
- For Martin County, a bathroom needs ventilation: mechanical exhaust ducted to the outside where the required openable window is absent, sized in the range of 50 cubic feet per minute intermittent (IRC R303.3; M1505).
- New or relocated bathroom receptacles must be ground-fault circuit-interrupter protected (IRC E3902.1 / NEC 210.8(A)(1)).
- Tub and shower walls have to be finished with a nonabsorbent, waterproof surface extending to a minimum height above the floor (IRC R307.2).
- Routine maintenance items such as towel bars, mirrors, paint, or floor coverings done alone are commonly permit-exempt, but that exemption ends once the work relocates fixtures or opens up wiring, piping, or walls, so a like-for-like fixture swap should be checked against the local exemption list rather than assumed (IRC R105.2).
General submittal guidance from International Residential Code (IRC), 2021 edition, Sections R105, R106, R303.3, R307, and E3902. Source. Martin County Building Department sets the exact checklist for Martin County.
Where to apply in Martin County:
Martin County Building Department
- 900 SE Ruhnke Street, Stuart, FL 34994
- Phone: (772) 288-5916
Bathroom Remodel Permit in Martin County compared with nearby Florida localities
| Locality | Permit needed? | Threshold | What each Florida schedule says | Verified |
|---|---|---|---|---|
| Martin County | It depends | Finish work and fixture repairs versus a remodel | Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building... | |
| Miami | It depends | Finish work and listed fixture swaps versus a remodel | "Residential less than estimated $2,500.00": $45.00 | |
| Tampa | It depends | Scope of work: finish-only work is exempt; fixture, plumbing, electrical or wall work is not | Fixture-only work: "Plumbing (general)" $120.00, City of Tampa Trade Permit Fee Schedule... |
Inspections and closing out your permit
In Martin County, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
- In Martin County: any construction or work covered by the permit stays subject to inspection and must remain accessible and exposed until the building official approves it (IRC R109.1).
- In Martin County: the plumbing, mechanical, and electrical rough-in has to be inspected and approved before it is covered or concealed, before fixtures or appliances are installed, and before the framing inspection, so the trade work behind the walls is signed off before drywall closes them up (IRC R109.1.2, R109.1.4).
- In Martin County: work cannot proceed past the point covered by the last approved inspection without the building official's sign-off (IRC R109.4).
- Scheduling is on the permit holder in Martin County: it is their duty to notify the building official when work is ready and to provide access for each inspection (IRC R109.3).
- In Martin County: a final inspection, covering everything required by the permit including items such as GFCI protection, closes out the job once all the permitted work is complete (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Martin County permit portal or by phone at (772) 288-5916.
Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Bathroom Remodel Permit checklist for Martin County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Finish work and fixture repairs versus a remodel. Usually needed: Before work begins.
- Budget the fee. Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75. Official fee schedule.
- Apply. In Martin County, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt. Start at the Martin County permit portal.
- Keep the office details handy. Martin County Building Department. Phone: (772) 288-5916. Address: 900 SE Ruhnke Street, Stuart, FL 34994.
- Plan for inspections. In Martin County, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a bathroom remodel permit in Martin County?
- Martin County lists kitchen and bathroom remodels among the projects that require a permit, while painting, flooring and similar finishing work, cabinetry, and repair of toilets, sinks and faucets need none. A remodel that moves plumbing, adds circuits or alters walls needs a permit; finishes alone do not. Finish work and fixture repairs versus a remodel. Always confirm with the office before starting.
- How much does a bathroom remodel permit cost in Martin County?
- Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection; the HB 803 permit exemption waiver for qualifying work under $7,500 is $75. See the official fee schedule for current amounts.
- Where do you apply for a bathroom remodel permit in Martin County?
- You can apply through the Martin County permit portal or contact the Martin County Building Department directly. The links are listed on this page.
- Can a homeowner pull a bathroom remodel permit themselves in Martin County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Martin County applies this before you apply.
From the Library
What else needs a permit in Martin County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
Fee schedule effective July 1, 2026: construction costs under $25,000 pay a $75 building fee, a $25 plan review fee and $75 per inspection, for every permit type below. The fee column shows what differs by project.
None of the 12 project types verified for Martin County carry a size or scope threshold. See the Permit needed column for each project's own answer, since there is no threshold to compare here.
| Project | Permit needed? | Typical fee |
|---|---|---|
| Deck Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Electrical Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| EV Charger Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Fence Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| HVAC Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Patio Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Plumbing Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Pool Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Roof Replacement Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Shed Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Solar Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
| Water Heater Permit | Permit required | The HB 803 permit exemption waiver for qualifying work under $7,500 is $75 |
Bathroom Remodel Permit in other Florida localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Martin County documents; the office above sets the local rules.
How this bathroom remodel permit page for Martin County was verified. 2 official sources: martin.fl.us, martin.fl.us; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Martin County Building Department. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Bathroom Remodel Permit requirements across Florida localities