Bathroom Remodel Permit in Sioux Falls, South Dakota
It depends
Sometimes, depending on the project
Before a remodel that alters the room or its structure, replaces or rearranges plumbing, or adds circuits or five or more electrical devices.
Issued byCity of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office)
By Mario Bailey, verified against official sources
Quick answer
Sioux Falls lists remodels among projects that need a building permit, but its residential code exempts painting, papering, tiling, carpeting, cabinets, countertops and similar finish work. Plumbing work in a bathroom needs a separate plumbing permit unless it is only stopping a leak, clearing a stoppage or removing and reinstalling a toilet without replacing valves, pipes or fixtures. Electrical work needs an electrical permit once it reaches five or more outlets, switches, receptacles or fixtures or adds a new circuit pair or a circuit over 30 amps.
Typical threshold: Finish work (tiling, cabinets, countertops, painting) and removing and reinstalling a toilet are exempt; remodels, new or moved plumbing, and five or more new electrical devices need permits.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Remodel contractors usually handle the permits as part of the job. Comparing a few bids before you commit is the useful next step.
Compare bathroom remodel quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before a remodel that alters the room or its structure, replaces or rearranges plumbing, or adds circuits or five or more electrical devices.
What a bathroom remodel permit costs in Sioux Falls
How to apply in Sioux Falls
In Sioux Falls, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt.
What most bathroom remodel permit applications include:
- Creating a new bathroom or toilet room, or altering, moving, or replacing a plumbing, electrical, gas, or mechanical system as part of the remodel, is regulated work that requires a permit before work starts, usually filed as separate building, electrical, mechanical, and plumbing permit applications submitted together (IRC R105.1).
- For Sioux Falls, the permit application itself must identify and describe the work, describe the site, state the intended use, be accompanied by construction documents, state the valuation of the work, and be signed by the applicant or their agent (IRC R105.3).
- Those construction documents have to show the location, nature, and extent of the proposed work, which in practice means a scaled existing and proposed floor plan showing every fixture, outlet, switch, and vent fan, including the code-mandated clearances around fixtures such as the water closet (IRC R106.1.1; R307.1 fixture clearances).
- For Sioux Falls, a bathroom needs ventilation: mechanical exhaust ducted to the outside where the required openable window is absent, sized in the range of 50 cubic feet per minute intermittent (IRC R303.3; M1505).
- New or relocated bathroom receptacles must be ground-fault circuit-interrupter protected (IRC E3902.1 / NEC 210.8(A)(1)).
- Tub and shower walls have to be finished with a nonabsorbent, waterproof surface extending to a minimum height above the floor (IRC R307.2).
- Routine maintenance items such as towel bars, mirrors, paint, or floor coverings done alone are commonly permit-exempt, but that exemption ends once the work relocates fixtures or opens up wiring, piping, or walls, so a like-for-like fixture swap should be checked against the local exemption list rather than assumed (IRC R105.2).
General submittal guidance from International Residential Code (IRC), 2021 edition, Sections R105, R106, R303.3, R307, and E3902. Source. City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office) sets the exact checklist for Sioux Falls.
Where to apply in Sioux Falls:
City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office)
- Building Services, City Center (first floor), 231 N. Dakota Avenue, Sioux Falls, SD 57104
- Phone: (605) 367-8670
Inspections and closing out your permit
In Sioux Falls, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
- In Sioux Falls: any construction or work covered by the permit stays subject to inspection and must remain accessible and exposed until the building official approves it (IRC R109.1).
- In Sioux Falls: the plumbing, mechanical, and electrical rough-in has to be inspected and approved before it is covered or concealed, before fixtures or appliances are installed, and before the framing inspection, so the trade work behind the walls is signed off before drywall closes them up (IRC R109.1.2, R109.1.4).
- In Sioux Falls: work cannot proceed past the point covered by the last approved inspection without the building official's sign-off (IRC R109.4).
- Scheduling is on the permit holder in Sioux Falls: it is their duty to notify the building official when work is ready and to provide access for each inspection (IRC R109.3).
- In Sioux Falls: a final inspection, covering everything required by the permit including items such as GFCI protection, closes out the job once all the permitted work is complete (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Sioux Falls permit portal or by phone at (605) 367-8670.
Inspection sequence from International Residential Code (IRC), 2021 edition, Section R109 (Inspections). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Bathroom Remodel Permit checklist for Sioux Falls
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Finish work (tiling, cabinets, countertops, painting) and removing and reinstalling a toilet are exempt; remodels, new or moved plumbing, and five or more new electrical devices need permits. Usually needed: Before a remodel that alters the room or its structure, replaces or rearranges plumbing, or adds circuits or five or more electrical devices.
- Budget the fee. 2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). Plumbing and electrical permits are separate, on the MEP valuation schedule ($40 up to $5,000 of trade valuation). Official fee schedule.
- Apply. In Sioux Falls, a bathroom remodel that creates a new bathroom or touches its plumbing, wiring, or walls needs a building permit application, typically filed as separate building, electrical, mechanical, and plumbing permits submitted together and backed by a floor plan showing the fixture layout. A simple like-for-like fixture swap with no other work is often exempt. Start at the Sioux Falls permit portal.
- Keep the office details handy. City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office). Phone: (605) 367-8670. Address: Building Services, City Center (first floor), 231 N. Dakota Avenue, Sioux Falls, SD 57104.
- Plan for inspections. In Sioux Falls, once the permit is issued, the work stays subject to inspection at each stage, and the plumbing, mechanical, and electrical rough-in must be inspected and approved before the walls are closed up. A final inspection, made after everything required by the permit is done, closes out the job.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a bathroom remodel permit in Sioux Falls?
- Sioux Falls lists remodels among projects that need a building permit, but its residential code exempts painting, papering, tiling, carpeting, cabinets, countertops and similar finish work. Plumbing work in a bathroom needs a separate plumbing permit unless it is only stopping a leak, clearing a stoppage or removing and reinstalling a toilet without replacing valves, pipes or fixtures. Electrical work needs an electrical permit once it reaches five or more outlets, switches, receptacles or fixtures or adds a new circuit pair or a circuit over 30 amps. Finish work (tiling, cabinets, countertops, painting) and removing and reinstalling a toilet are exempt; remodels, new or moved plumbing, and five or more new electrical devices need permits. Always confirm with the office before starting.
- How much does a bathroom remodel permit cost in Sioux Falls?
- 2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). Plumbing and electrical permits are separate, on the MEP valuation schedule ($40 up to $5,000 of trade valuation). See the official fee schedule for current amounts.
- Where do you apply for a bathroom remodel permit in Sioux Falls?
- You can apply through the Sioux Falls permit portal or contact the City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office) directly. The links are listed on this page.
- Can a homeowner pull a bathroom remodel permit themselves in Sioux Falls?
- Under South Dakota law (SDCL 36-16-15; 36-25-17; ARSD 20:44:18:06): Yes, for your own home. No electrical license is needed to wire your own residence (a detached owner-occupied single-family dwelling) and its accessory structures, your own farmstead, or a single-family home you are building and will live in, but the work must be reported, permitted and inspected, and failing to report it is a Class 2 misdemeanor (36-16-15). The homeowner wiring permit is limited to one every three years, only for a home you occupy and do not rent out, and only you or your spouse may do the wiring (ARSD 20:44:18:06). No plumbing license is needed for plumbing in a home you own and occupy, or one you are building to live in, if the work meets the state plumbing code (36-25-17); a homeowner plumbing installation certificate is still required. Whether an owner may pull a local building permit is set by the city or county. Confirm how Sioux Falls applies this before you apply.
From the Library
What else needs a permit in Sioux Falls
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | ...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":... |
| Electrical Permit | It depends | Number of outlets, switches, receptacles or fixtures installed; two new circuits of 30 amps or less, one new circuit over 30 amps, any service change, or equipment over 5 kilowatts also needs a permit | ...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for... |
| EV Charger Permit | It depends | Equipment rating of the charger; one new circuit over 30 amps also needs a permit | ...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for... |
| Fence Permit | Permit required | Any size | "The permit fee is $20." (Fences page) |
| HVAC Permit | Permit required | Any size | ...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for... |
| Plumbing Permit | It depends | Stopping leaks, clearing stoppages and removing and reinstalling a toilet are exempt; replacing or rearranging valves, pipes or fixtures needs a permit | ...of Ordinances 150.302, 2024 UPC adopted by Ord. 6-26, passed 1-20-2026): "$0.01 to... |
| Pool Permit | It depends | Prefabricated swimming pools; the barrier rules apply to pools with 24 inches or more of water | ...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":... |
| Roof Replacement Permit | Permit required | Any size | Flat $40: "The $40 minimum fee includes all residential re-shingle permits, siding... |
| Shed Permit | Permit required | Any size | "The minimum permit fee is $40.00 for accessory structures under 200 ft2" (Detached... |
| Solar Permit | Permit required | Any size | ...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":... |
| Water Heater Permit | Permit required | Any size | Plumbing permit, Table 104.5 (Code of Ordinances 150.302): $40 for "$0.01 to $5,000.00"... |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Sioux Falls documents; the office above sets the local rules.
How this bathroom remodel permit page for Sioux Falls was verified. 2 official sources: siouxfalls.gov, codelibrary.amlegal.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Bathroom Remodel Permit requirements across South Dakota localities