South Dakota / Sioux Falls

Solar Permit in Sioux Falls, South Dakota

Permit required

Yes, a permit is required

Before installing a rooftop or ground-mounted solar photovoltaic system.

Confirmed on official page Verified

Issued byCity of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office)

By Mario Bailey, verified against official sources

Quick answer

Sioux Falls publishes no solar-specific page or rule, but its residential code requires a permit before anyone installs or alters a structure or its electrical system, and it has no exemption for solar. In practice the City issues rooftop solar under Residential Building permits, and connecting the system to the home's service needs a City electrical permit. Work is done by City-licensed contractors or by an owner-occupant under homeowner's permits.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?

South Dakota's owner-builder rule (SDCL 36-16-15; 36-25-17; ARSD 20:44:18:06) sets what you may do on your own home without hiring anyone. Read the statute.

When a permit is usually needed

Before installing a rooftop or ground-mounted solar photovoltaic system.

What a solar permit costs in Sioux Falls

Line item
solar permitBy formula2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). The electrical side is a separate permit on the MEP valuation schedule ($40 up to $5,000 of electrical valuation).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Sioux Falls

In Sioux Falls, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • For Sioux Falls, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • For Sioux Falls, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • For Sioux Falls, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office) sets the exact checklist for Sioux Falls.

Where to apply in Sioux Falls:

City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office)

  • Building Services, City Center (first floor), 231 N. Dakota Avenue, Sioux Falls, SD 57104
  • Phone: (605) 367-8670

Inspections and closing out your permit

In Sioux Falls, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. In Sioux Falls: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. In Sioux Falls: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. In Sioux Falls: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. In Sioux Falls: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. In Sioux Falls: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. In Sioux Falls: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Sioux Falls permit portal or by phone at (605) 367-8670.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Sioux Falls?
Sioux Falls publishes no solar-specific page or rule, but its residential code requires a permit before anyone installs or alters a structure or its electrical system, and it has no exemption for solar. In practice the City issues rooftop solar under Residential Building permits, and connecting the system to the home's service needs a City electrical permit. Work is done by City-licensed contractors or by an owner-occupant under homeowner's permits. Always confirm with the City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office) before starting.
How much does a solar permit cost in Sioux Falls?
2026 Building Permit Valuation/Fee Schedule (City of Sioux Falls, fee schedule dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule": "$1-4,000" $40.00; "$4,001-25,000" "$32.50 for the first $2,000 plus $6.00 for each additional $1,000 or fraction thereof, to and including $25,000"; "$25,001-50,000" "$170.50 for the first $25,000 plus $4.50 for each additional $1,000 or fraction thereof". Residential projects have no plan review fee (Residential Plan Review page). The electrical side is a separate permit on the MEP valuation schedule ($40 up to $5,000 of electrical valuation). See the official fee schedule for current amounts.
Where do you apply for a solar permit in Sioux Falls?
You can apply through the Sioux Falls permit portal or contact the City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Sioux Falls?
Under South Dakota law (SDCL 36-16-15; 36-25-17; ARSD 20:44:18:06): Yes, for your own home. No electrical license is needed to wire your own residence (a detached owner-occupied single-family dwelling) and its accessory structures, your own farmstead, or a single-family home you are building and will live in, but the work must be reported, permitted and inspected, and failing to report it is a Class 2 misdemeanor (36-16-15). The homeowner wiring permit is limited to one every three years, only for a home you occupy and do not rent out, and only you or your spouse may do the wiring (ARSD 20:44:18:06). No plumbing license is needed for plumbing in a home you own and occupy, or one you are building to live in, if the work meets the state plumbing code (36-25-17); a homeowner plumbing installation certificate is still required. Whether an owner may pull a local building permit is set by the city or county. Confirm how Sioux Falls applies this before you apply.

From the Library

What else needs a permit in Sioux Falls

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsFinish work (tiling, cabinets, countertops, painting) and removing and reinstalling a toilet are exempt; remodels, new or moved plumbing, and five or more new electrical devices need permits...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":...
Deck PermitPermit requiredAny size...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":...
Electrical PermitIt dependsNumber of outlets, switches, receptacles or fixtures installed; two new circuits of 30 amps or less, one new circuit over 30 amps, any service change, or equipment over 5 kilowatts also needs a permit...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for...
EV Charger PermitIt dependsEquipment rating of the charger; one new circuit over 30 amps also needs a permit...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for...
Fence PermitPermit requiredAny size"The permit fee is $20." (Fences page)
HVAC PermitPermit requiredAny size...Permit Fees (City of Sioux Falls PDF): the fee is set on the MEP valuation, $40 for...
Plumbing PermitIt dependsStopping leaks, clearing stoppages and removing and reinstalling a toilet are exempt; replacing or rearranging valves, pipes or fixtures needs a permit...of Ordinances 150.302, 2024 UPC adopted by Ord. 6-26, passed 1-20-2026): "$0.01 to...
Pool PermitIt dependsPrefabricated swimming pools; the barrier rules apply to pools with 24 inches or more of water...dated 01/01/2026), "Residential Occupancies Building Permit Fee Schedule":...
Roof Replacement PermitPermit requiredAny sizeFlat $40: "The $40 minimum fee includes all residential re-shingle permits, siding...
Shed PermitPermit requiredAny size"The minimum permit fee is $40.00 for accessory structures under 200 ft2" (Detached...
Water Heater PermitPermit requiredAny sizePlumbing permit, Table 104.5 (Code of Ordinances 150.302): $40 for "$0.01 to $5,000.00"...

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Sioux Falls documents; the office above sets the local rules.

How this solar permit page for Sioux Falls was verified. 2 official sources: siouxfalls.gov, codelibrary.amlegal.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Sioux Falls Planning and Development Services, Building Services (zoning permits from the Zoning office). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across South Dakota localities

Solar permit rules nationwide

Permit required
Get quotes