Can You Close on a House With Open Permits? What Buyers and Sellers Can Do
An open permit is work that was permitted but never signed off, and it stays with the house. How to find one before closing, what a written open-permit search costs where we read it, who can close it, and the Florida law that protects a buyer from a previous owner's unclosed permit.
Usually yes, but not always on your timeline. An open permit means the work was permitted and never got its final inspection. It stays on the property’s record after the sale, a lender or title company may refuse to close until it is resolved, and whoever owns the house when the office comes asking is usually the one who has to deal with it, though Florida shields an arms-length buyer from penalties for a previous owner’s open permit (below). The fix is almost always cheaper before closing than after.
- What it is
- Permitted work with no passed final inspection
- Does it follow the house
- Yes, it stays on the property record
- Who can close it in Florida
- The owner, through any licensed contractor or as an owner-builderFlorida Statutes 553.79(16)
- Written search we read
- From $43.75 a search to $58 an hourMiami-Dade County, City of Miami, Homestead, St. Johns County
- Best time to fix
- Before the contract, or as a condition of it
The next step for a buyer: before your inspection period ends, get the property’s permit history from the office that permits the address, and read the status of every permit on it. For a seller: do the same before you list.
Open, expired, closed: what the status means
A permit record carries a status, and three words matter at a sale.
- Issued or active: the permit was pulled and the work may still be under way. On a house that has been finished and lived in for years, an issued permit with no final inspection is what people mean by an open permit.
- Expired: the permit lapsed before the final inspection. Under the model code most states adopt, that happens when work does not start within 180 days of issue or stops for 180 days between inspections. Our guide to how long a building permit lasts covers the clocks and the extensions.
- Finaled, closed or completed: the final inspection passed. This is the status you want on every permit at the address.
An open permit is not the same as work with no permit at all. The office has the application, any plans, and a record of the inspections that passed, so closing it is usually a matter of finishing what the last inspection asked for and calling for the final. Work with no permit is a different problem, covered in our guides to buying and selling a house with unpermitted work.
How to find open permits before closing
Start with the office’s online records. Each permit-search page on this site links the record search we verified for that office, what it searches by and whether it needs an account; our guide to finding out whether a permit was pulled explains how to read the result.
For a closing, many Florida offices also run a written open-permit search and send back a written answer, which is also something you can hand to a title company or lender. What the ones we read on November 18, 2026 charge:
| Office | What you ask for | Price | Turnaround |
|---|---|---|---|
| Miami-Dade County (unincorporated areas) | Open permit search, by email with the address and folio number | $43.75 per address or folio | No time stated; the department confirms the search was performed and sends the results |
| City of Miami | Complete permit history search | $44.00, nonrefundable; $10.00 for a single search such as building, electrical or plumbing permits | Invoice within three business days; records about 20 working days after payment; copies billed separately |
| City of Homestead | Open permit search | Residential $58.00 an hour | 3 business days |
| St. Johns County | Open permit search request, covering permits issued in the last 10 years | $56.00 an hour, one-hour minimum, paid up front | An initial response within three business days |
Order a search the day the contract is signed: at the City of Miami, the records take about 20 working days. Two things the table shows that a buyer can miss.
The right office depends on the address, not the county. Miami-Dade County, the City of Miami and the City of Homestead all sit in one county and run three separate searches at three prices. A county search does not cover a city that permits its own buildings. If the property is inside a city, ask the city.
A permit search is not a title search. St. Johns County’s form says so in plain words: the search “does not constitute a valid or proper Title Search and should not be used as such.” It also looks back only 10 years, “open permits issued within the 10-year period preceding the date of your inquiry,” so for an older house ask for the full permit history too. The same form warns that there “may be additional permits issued and/or required from other governmental entities such as water management districts, state or federal agencies.” An open permit is a building department fact; a lien or a code enforcement case is a separate record, and in unincorporated Miami-Dade it is a separate search: a lien records search, $250 per folio or address, that reports work without permit, expired permit and unsafe structures violations, among others.
Who can close an open permit
The person who pulled the permit is usually the contractor, but the person the office will hold to it is the owner. Florida writes the owner’s options into statute, and they are a useful model even outside Florida.
Under Florida Statutes 553.79(16)(a), “A property owner, regardless of whether the property owner is the one listed on the application for the building permit, may close a building permit” in one of two ways. The owner “may retain the original contractor listed on the permit or hire a different contractor appropriately licensed in this state to perform the work necessary to satisfy the conditions of the permit and to obtain any necessary inspections in order to close the permit.” A replacement contractor “is not liable for any defects in the work performed by the original contractor and is only liable for the work that he or she performs.” Or the owner “may assume the role of an owner-builder.”
Two more provisions make old open permits easier to clear in Florida:
- An expired permit whose requirements “have been substantially completed, as determined by the local enforcement agency,” may be closed “without having to obtain a new building permit,” under the code in effect when the office received the application (553.79(16)(b)).
- The office “may close a building permit 6 years after the issuance of the permit, even in the absence of a final inspection, if the local enforcement agency determines that no apparent safety hazards exist” (553.79(16)(c)). The word is may: it is the office’s call, not the owner’s right.
Outside Florida, no state statute we have read sets the owner’s options this plainly. In practice the path is the same: the original contractor or a new licensed one finishes what the last inspection asked for and schedules the final, or the owner reopens or reissues the permit and does it. Ask the office which of those it allows before anyone picks up a tool.
If you are the buyer
Florida protects an arms-length buyer from a previous owner’s unclosed permit. Under 553.79(17)(a), the office “may not deny issuance of a building permit to; issue a notice of violation to; or fine, penalize, sanction, or assess fees against an arms-length purchaser of a property for value solely because a building permit applied for by a previous owner of the property was not closed.” The office keeps “all rights and remedies against the property owner and contractor listed on the permit.”
Read that protection for what it covers: penalties and permit denials aimed at you because of the old permit. It does not sign off the work. The deck or the re-roof is still uninspected, and an insurer, a lender, or your own buyer years later can still ask about it.
Unincorporated Miami-Dade adds a disclosure the seller must put in the contract or a same-day addendum, signed and dated by the buyer: “Many home inspections do not check for illegal construction or outstanding building or zoning code violations. You should have an inspection conducted to check for these issues before entering into a contract to purchase residential property. If illegal construction or outstanding code violations are identified after you purchase the property, you may be responsible for addressing such issues at your own expense.”
What a buyer can ask for, in the contract and before the inspection period ends:
- The written open-permit search or the full permit history, from the office that permits the address.
- That the seller close every open permit before closing, with the passed final inspection on the record.
- If that cannot happen in time, an escrow holdback from the seller’s proceeds, released when the final passes, or a price that reflects the work left.
- Copies of the permit, the approved plans and the inspection results, so the next contractor is not starting blind.
Your agent and a real estate attorney licensed where the house sits write the contract language. Nothing here is legal advice.
If you are the seller
Look before you list. A permit you forgot about, a water heater from eight years ago, a fence, a re-roof after a storm, is the kind of record that turns up in a buyer’s search two weeks before closing. If you find one:
- Call the office and ask what the permit still needs: often only the final inspection.
- Call the contractor who pulled it. If they are gone, hire another licensed contractor to finish and call for the final, or ask the office whether you may close it as the owner.
- If the permit expired, ask whether it can be closed as substantially completed or must be reissued, and what that costs.
- Keep the passed final in your closing file, and answer your state’s disclosure form with it in hand. Our selling guide shows what ten states’ forms ask.
Find the office for the address
Every jurisdiction on this site has its office, phone and portal on its own page; start from the jurisdiction index. In Florida, the Florida penalty page carries the state’s rules for work that was never permitted at all.
Sources
- Florida Statutes 553.79, read on Online Sunshine: (16) on who may close an open or expired permit and the 6-year closure, (17) on protection for arms-length purchasers. (accessed )
- Miami-Dade County Regulatory and Economic Resources, Buying and Selling Residential Properties: the seller disclosure on illegal construction in unincorporated Miami-Dade, the $250 lien records search, and the open permit search at $43.75 per address or folio. (accessed )
- City of Miami, Request Building Records: $44.00 complete permit history search, $10.00 per individual search, nonrefundable. (accessed )
- City of Homestead Building Department, Request for Information form: Open Permit Search, 3 business days, residential $58.00 an hour. (accessed )
- St. Johns County Building Department, Open Permit Search Request: Administrative Research fee of $56.00 an hour with a one-hour minimum, an initial response within three business days, and the statement that the search is not a title search. (accessed )
Get rule-change alerts
We catch permit rule and fee changes in our verification passes and post them to the rule tracker. Get them by email instead.