Guide
How Long Does a Building Permit Last? The 180-Day Rule and Extensions
Under the model code most states use, a permit dies if work does not start within 180 days or stops for 180 days between inspections. Where Florida, North Carolina, Tennessee and New Orleans set different clocks, how to ask for an extension, and what an expired permit means.
Under the model code most states build on, a building permit does not expire on a calendar date. It expires when nothing happens. Work has to start within 180 days of the permit being issued, and once it starts, no more than 180 days can pass between inspections. Keep the inspections coming and the permit stays alive.
That is the default. Florida, North Carolina and Tennessee set their own clocks by statute or state rule, and some cities set their own for trade permits. If you think your permit is close to lapsing, the next step is to check its last inspection date on your jurisdiction’s permit portal and ask the office for an extension in writing before it runs out.
The model code: 180 days, twice
Section R105.5 of the International Residential Code reads: “Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance or after commencement of work if more than 180 days pass between inspections.”
Read it as two separate clocks:
- Starting. 180 days from the day the permit is issued to begin the work.
- Continuing. Once work has begun, 180 days from one inspection to the next.
A slow project is not the problem. A project with a six-month gap in inspections is. If your contractor stops calling for inspections while waiting on materials, that gap counts.
The model code also limits how long an application can sit before a permit is issued: an application “shall be deemed to have been abandoned 180 days after the date of filing unless such application has been pursued in good faith or a permit has been issued.”
Where the clock is different
| Where | Not started | Stopped after starting | Outer limit |
|---|---|---|---|
| Model code (2024 IRC) | 180 days | 180 days between inspections | None |
| Florida, single-family permits | Florida Building Code (not quoted here) | Florida Building Code (not quoted here) | 1 year from issuance, or the next Florida Building Code edition, whichever is later |
| North Carolina | 6 months, or less if a local ordinance says so | 12 months | None in the statute |
| Tennessee, state-enforced areas | 180 days | 180 days | 2 years from issuance |
| New Orleans, electrical permits | 6 months of inactivity | 6 months of inactivity | None stated |
Florida writes it into statute: “A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later.” The same paragraph says this “does not prevent a local government from extending a building permit beyond the expiration date,” and lets the issuing office send the owner and contractor a written notice “no less than 30 days before a building permit is set to expire.”
North Carolina: a permit “expires by limitation six months, or any lesser time fixed by ordinance, after the date of issuance if the work authorized by the permit has not been commenced. If, after commencement, the work is discontinued for a period of 12 months, the permit shall immediately expire.”
Tennessee (where the State Fire Marshal’s office, not a city or county, enforces the residential code) uses both 180-day rules and adds an outer limit: “Every building permit shall expire two (2) years from the date of issue or upon the issuance of the certificate of occupancy,” unless the state finds substantial progress and grants a written extension.
New Orleans is an example of a city running its own clock on a trade permit. Its electrical permit page says: “Permit is valid for six (6) months of inactivity. After six (6) months, contractor must reapply for permit.”
How to get an extension
The model code allows one, on two conditions: “The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.”
In practice that means:
- Ask before it expires. An extension stretches a live permit. Once it lapses there is nothing left to extend, and in North Carolina the statute requires a new permit.
- Ask in writing, with the permit number, the last inspection date and the reason: a backordered window package, a contractor change, a medical delay, a lender hold.
- Say what happens next. Give the date you expect to call for the next inspection. A plan is what turns a delay into “justifiable cause”.
- Expect a limit per extension. Each one is capped at 180 days in the model text and in Tennessee’s rule; Tennessee’s rule allows “one (1) or more” of them.
The cheapest extension is often just an inspection. If any part of the work is ready to be seen, calling for that inspection restarts the 180-day count under the model code without any paperwork at all.
What an expired permit means
The work does not become legal or illegal on its own; the permit simply stops covering it. North Carolina’s statute says what follows: “No work authorized by any building permit that has expired shall be performed until a new permit has been secured.”
Expect three practical consequences:
- A new permit, and possibly new fees. An office that reissues the permit may charge again, and the work may have to meet the code in force when you reapply.
- Open permits follow the house. An expired permit with no final inspection stays on the property record and surfaces when you sell. Our guides to selling and buying a house with open or unpermitted work cover what that does to a sale, and our guide to closing on a house with open permits covers finding one before closing and who can close it.
- Uninspected work is uninspected. Anything covered up after the last passed inspection may have to be opened for the inspector.
Florida softens all three by statute. If an expired permit’s requirements “have been substantially completed, as determined by the local enforcement agency, the permit may be closed without having to obtain a new building permit,” under the code in effect when the application was received. An owner can close a permit even if someone else pulled it, either by hiring a licensed contractor or by acting as an owner-builder. The office “may close a building permit 6 years after the issuance of the permit, even in the absence of a final inspection, if the local enforcement agency determines that no apparent safety hazards exist.” And a buyer is protected: the office “may not deny issuance of a building permit to; issue a notice of violation to; or fine, penalize, sanction, or assess fees against an arms-length purchaser of a property for value solely because a building permit applied for by a previous owner of the property was not closed.”
Find out where your permit stands
Most offices show each permit’s status and inspection history online. Our guide to checking whether a permit was pulled explains how to read a permit record, and every jurisdiction in our verified index links its own portal and phone number. If the last passed inspection is more than five months old, call now, not in month six.
Method
Every quotation above was read on November 5, 2026 on the official source listed below: the 2024 International Residential Code on ICC’s own digital codes site, Florida’s and North Carolina’s statutes on their legislatures’ sites, the Tennessee Secretary of State’s copy of the State Fire Marshal rules, and the City of New Orleans permit page. Many states adopt an older edition of the model code or amend Section R105.5, and many cities set their own rules for trade permits, so the expiration rule printed on your permit card is the one that governs your job.
How Long Does a Building Permit Last? The 180-Day Rule and Extensions: figures as of 28 Sep 2026, 137 jurisdictions. Now 178.
Sources
- 2024 International Residential Code, Chapter 1, read on ICC Digital Codes: R105.5 (expiration and extensions) and R105.3.2 (time limitation of an application). (accessed )
- Florida Statutes 553.79 (2026), read on Online Sunshine: (1)(c) on the expiration notice and the 1-year life of a single-family permit, (16) on closing an open or expired permit, and (17) on protection for arms-length buyers. (accessed )
- North Carolina General Statutes 160D-1111, expiration of building permits. (accessed )
- Tennessee State Fire Marshal rules for one and two family dwellings, rule 0780-02-23-.05(7) (revised July 2020): the 180-day rules and the 2-year limit. These govern where the state, not a city or county, enforces the residential code. (accessed )
- City of New Orleans, Electrical Permit page: "Permit is valid for six (6) months of inactivity." (accessed )