Florida / St. Johns County

Solar Permit in St. Johns County, Florida

Permit required

Yes, a permit is required

Before installing a thermal or photovoltaic solar system in unincorporated St. Johns County

Quick answer

St. Johns County's fee schedule carries a dedicated Solar Permit Fees section with separate Thermal and Photovoltaic Permit charges, and the county's Photovoltaic Energy Check List requires a completed Building Permit Application (citing FBC Section 105.3) plus PV worksheets, system specifications, and a one-line diagram. This applies to unincorporated St. Johns County; St. Augustine and St. Augustine Beach have their own building departments. Roof-mounted systems additionally require a structural engineering letter per the county's checklist.

Issued by
Building Services Division, Growth Management Department
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your Florida Department of Business and Professional Regulation license active, and under which business name? Verify it on www.myfloridalicense.com.

Florida's owner-builder rule (F.S. 489.103(7)(a)-(c)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in St. Johns County

Fee schedule in force
Official scheduleRead .
  • Solar Permit Fees (F.S. 553.80): Permit Issuance $16.00 with a minimum permit fee of $50.00;
  • Thermal Permit $34.00;
  • Photovoltaic Permit $34.00;
  • Plan Review Fee $53.00 per hour, per St. Johns County's Schedule of Fees and Services, Exhibit A (amended 09/15/2026).

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How St. Johns County compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alachua CountyPermit requiredNo solar-specific flat fee is published
Brevard CountyPermit requiredSee schedule
Charlotte CountyPermit requiredAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge
Collier CountyPermit requiredSee schedule
Hernando CountyPermit requiredPhotovoltaic System (Res): $180.00
Hillsborough CountyPermit requiredResidential Photovoltaic trade permit fee is $250 flat, inspection-only with no plan review; the schedule has the rest
St. Johns Countythis pagePermit requiredSolar Permit Fees (F.S. 553.80): Permit Issuance $16.00 with a minimum permit fee of $50.00

How to apply in St. Johns County

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Building Services Division, Growth Management Department

  • 4040 Lewis Speedway, St. Augustine, FL 32084
  • Phone: 904-827-6800
  • Email: bldcodes@sjcfl.us

Permitting activity in St. Johns County

In 2025, St. Johns County authorized permits for 4,735 new residential housing units (3,554 single-family, 1,181 in multi-family buildings), valued at $1.2B, down from 5,575 the year before. That works out to about 13.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 346,328.

What else needs a permit in St. Johns County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeDeck permits fall under the general Building Services Fees table: Permit Issuance Fees $20.00; the schedule has the rest
Electrical PermitPermit requiredAny sizeElectrical Permit Fees (F.S. 553-80): Permit Issuance Fee $16.00; the schedule has the rest
Fence PermitPermit requiredAny sizeFence permits fall under the general Building Services Fees table: Permit Issuance Fees $20.00; the schedule has the rest
HVAC PermitPermit requiredAny sizeMechanical Permit Fees (F.S. 553.80): Permit Issuance $16.00 with a minimum permit fee of $50.00
Patio PermitPermit requiredAny sizePatio permits fall under the general Building Services Fees table: Permit Issuance Fees $20.00; the schedule has the rest
Plumbing PermitPermit requiredAny sizePlumbing Permit Fees (F.S. 553-80): Permit Issuance Fee $16.00 with a minimum permit fee of $50.00, plus $6.00 for each plumbing fixture, floor drain, or trap
Pool PermitPermit requiredpool surface area per the LDC regulated-pool definition, which also uses a 2 foot depth testSwimming Pool Fees (F.S. 553-80): Permit Issuance $16.00
Roof Replacement PermitPermit requiredAny sizeRoof replacement permits fall under the general Building Services Fees table: Permit Issuance Fees $20.00; the schedule has the rest
Shed PermitPermit requiredAny sizeShed permits fall under the general Building Services Fees table: Permit Issuance Fees $20.00; the schedule has the rest

Frequently asked questions

Do you need a solar permit in St. Johns County?
Yes, before installing a thermal or photovoltaic solar system in unincorporated St. Johns County. If you are unsure how that applies to your project, call the Building Services Division, Growth Management Department at 904-827-6800 before you start.
How much does a solar permit cost in St. Johns County?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the Building Services Division, Growth Management Department at 904-827-6800.
Where do you apply for a solar permit in St. Johns County?
You can apply through the St. Johns County permit portal or contact the Building Services Division, Growth Management Department directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in St. Johns County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how St. Johns County applies this before you apply.

From the Library

Solar Permit in other Florida localities

Everything above, sourced

How this solar permit page for St. Johns County was verified. 2 official sources: sjcfl.us, sjcfl.us; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Building Services Division, Growth Management Department. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project