Florida / Broward County

Solar Permit in Broward County, Florida

Permit required

We could not confirm this

Before installing any rooftop solar PV system

Based on building code Verified

Issued byBroward County Building Code Division

By Mario Bailey, verified against official sources

Quick answer

A building and electrical permit is required for residential rooftop solar PV installations in unincorporated Broward County under the Florida Building Code. The GoSOLAR program page previously cited returned a 404 error and could not be verified. Solar is not explicitly listed on the Broward BuildingPermits page but is required under Florida Building Code for any rooftop structural installation. Incorporated municipalities in Broward each set their own permit process.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing any rooftop solar PV system

What a solar permit costs in Broward County

Line item
solar permitNot publishedBroward County publishes no fee for this permit type in a schedule we can verify. Ask Broward County Building Code Division how the fee is calculated for your project.

How Broward County compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alachua CountyPermit requiredNo solar-specific flat fee is published
Brevard CountyPermit requiredBrevard's Residential Solar Photovoltaic Permit Application fee table lists a...
Broward Countythis pagePermit requiredNot published
Charlotte CountyPermit requiredAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if...
Collier CountyPermit requiredFee Schedule (Resolution 2025-231, effective January 1, 2026), Solar Permit...
Hernando CountyPermit requiredPhotovoltaic System (Res): $180.00
Hillsborough CountyPermit requiredResidential Photovoltaic trade permit fee is $250 flat, inspection-only with...

How to apply in Broward County

In Broward County, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • For Broward County, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • For Broward County, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • For Broward County, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Broward County Building Code Division sets the exact checklist for Broward County.

Where to apply in Broward County:

Broward County Building Code Division

  • 2307 W Broward Blvd Suite 300, Fort Lauderdale, FL 33312
  • Phone: (954) 765-4400
  • Email: building@broward.org

Solar Permit in Broward County compared with nearby Florida localities

LocalityPermit needed?ThresholdWhat each Florida schedule saysVerified
Broward CountyPermit requiredNot specifiedNot published
Alachua CountyPermit requiredNot specifiedNo solar-specific flat fee is published
Brevard CountyPermit requiredNot specifiedBrevard's Residential Solar Photovoltaic Permit Application fee table lists a Building...
Charlotte CountyPermit requiredNot specifiedAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation...
Clay CountyNot confirmedNot specifiedNot published

Inspections and closing out your permit

In Broward County, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. In Broward County: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. In Broward County: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. In Broward County: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. In Broward County: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. In Broward County: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. In Broward County: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Broward County permit portal or by phone at (954) 765-4400.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Broward County

In 2024, Broward County authorized permits for 1,655 new residential housing units (697 single-family, 958 in multi-family buildings), valued at $409M, down from 3,047 the year before. That works out to about 0.8 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 2,037,472.

About Broward County

Broward County has about 863,128 housing units. The median home is valued at $380,400, against a median household income of $74,534. About 63% of homes are owner-occupied, and the typical home was built around 1980.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a solar permit in Broward County?
A building and electrical permit is required for residential rooftop solar PV installations in unincorporated Broward County under the Florida Building Code. The GoSOLAR program page previously cited returned a 404 error and could not be verified. Solar is not explicitly listed on the Broward BuildingPermits page but is required under Florida Building Code for any rooftop structural installation. Incorporated municipalities in Broward each set their own permit process. Always confirm with the Broward County Building Code Division before starting.
How much does a solar permit cost in Broward County?
Fees are set by Broward County and are not published here. Contact the office for current amounts.
Where do you apply for a solar permit in Broward County?
You can apply through the Broward County permit portal or contact the Broward County Building Code Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Broward County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Broward County applies this before you apply.

From the Library

What else needs a permit in Broward County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedNo separate deck fee line
Electrical PermitPermit requiredNot specifiedElectrical permit is the greater of a $125 minimum base fee or 3.0% of job value, per...
Fence PermitPermit requiredNot specifiedNo separate fence fee line
HVAC PermitPermit requiredNot specifiedMechanical (air conditioning and ventilation) permit is the greater of a $125 minimum...
Patio PermitPermit requiredNot specifiedNo separate patio fee line
Plumbing PermitPermit requiredNot specifiedPlumbing permit is the greater of a $125 minimum base fee or 3.0% of job value, per...
Pool PermitPermit requiredNot specifiedPool work needs separate Structural, Plumbing, Mechanical and Electrical permit...
Roof Replacement PermitIt dependsunder F.S. 553.79(1)(g) (HB 803, ch. 2026-63, effective 2026-07-01), work valued at less than $7,500 on a single-family dwelling qualifies for exemption upon a written exemption request with documentation of the nature and value of the work; the exemption excludes electrical, plumbing, structural, mechanical, and gas work and any property in a flood hazard area; the statute does not name roofing, so a non-structural reroof under that value can qualify; confirm with Broward County Building Code Division.Structural permit with a roofing-specific minimum: the greater of a $250 minimum base...
Shed PermitPermit requiredNot specifiedNo separate shed fee line

Solar Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Broward County documents; the office above sets the local rules.

How this solar permit page for Broward County was verified. 1 official source: broward.org. Last checked by Mario Bailey, not confirmed with Broward County Building Code Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page