Florida / Jacksonville

Solar Permit in Jacksonville, Florida

Permit required

Yes, a permit is required

Before installing a solar water heater, solar collector system, or rooftop solar photovoltaic array at a residence in the City of Jacksonville (Duval County)

Quick answer

Solar equipment in the City of Jacksonville's consolidated Duval County jurisdiction is billed under the standard trade fee schedules: the Plumbing Permit Fees list a specific Solar water heater line item and the Mechanical Permit Fees list a specific Solar collector system line item, both under Municipal Code Section 320.409, confirming those solar installations are permitted work. No single dedicated city statement for rooftop solar photovoltaic (electric) panels was found; a PV array is electrical work, and the Building Inspection Division's general rule is that electrical work must be done only by certified contractors and craftsmen and requires its own permit. This applies only inside the consolidated city-county limits; the beach cities and Baldwin permit solar installations through their own building departments.

Issued by
Building Inspection Division (City of Jacksonville Department of Public Works)
From an official source Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your Florida Department of Business and Professional Regulation license active, and under which business name? Verify it on www.myfloridalicense.com.

Florida's owner-builder rule (F.S. 489.103(7)(a)-(c)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in Jacksonville

Fee schedule in force
Official scheduleRead .
Published in
City Fees schedule (Municipal Code Section 320.409):

Plumbing Permit Fees lists a Solar water heater line item at $21.00;

Mechanical Permit Fees lists a Solar collector system line item at $22.00.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Jacksonville compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alachua CountyPermit requiredNo solar-specific flat fee is published
Brevard CountyPermit requiredSee schedule
Charlotte CountyPermit requiredAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge
Collier CountyPermit requiredSee schedule
Hernando CountyPermit requiredPhotovoltaic System (Res): $180.00
Hillsborough CountyPermit requiredResidential Photovoltaic trade permit fee is $250 flat, inspection-only with no plan review; the schedule has the rest
Jacksonvillethis pagePermit requiredCity Fees schedule (Municipal Code Section 320.409): Plumbing Permit Fees lists a Solar water heater line item at $21.00

How to apply in Jacksonville

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Building Inspection Division (City of Jacksonville Department of Public Works)

  • 214 North Hogan Street, 2nd Floor, Room 280 (Ed Ball Building), Jacksonville, FL 32202
  • Phone: (904) 255-8500

Permitting activity in Jacksonville

In 2025, Jacksonville authorized permits for 5,890 new residential housing units (3,611 single-family, 2,279 in multi-family buildings), valued at $1.1B, down from 6,398 the year before. That works out to about 6.4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 920,570.

What else needs a permit in Jacksonville

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeSee schedule
Electrical PermitPermit requiredAny sizeSee schedule
Fence PermitNo permit neededExemptNot published
HVAC PermitIt dependsA permit is required for mechanical work such as installing or replacing air conditioning and heating equipment. It is not required for connecting portable heating, ventilation, cooling, or evaporative-cooling equipment; for replacing a part within a single existing piece of equipment; or for a self-contained refrigeration system with 10 pounds or less of refrigerant run by a motor of 1 horsepower or less.See schedule
Patio PermitIt dependsNo permit for a plain patio slabNot published
Plumbing PermitIt dependsA permit is required for plumbing work such as fixture installation, water heater replacement, and sewer or water-service connections. It is not required for replacing plumbing fixtures after the stop (excluding water heaters), stopping leaks, or clearing drain stoppages, provided the repair does not involve or require replacing or rearranging valves, pipes, or fixtures.See schedule
Pool PermitPermit requiredAny sizeSee schedule
Roof Replacement PermitPermit requiredAny sizeSee schedule
Shed PermitPermit requiredA building permit is required for a residential shed of any size. Sheds 150 square feet or larger (or with a job cost of $5,000 or more) additionally require structural design drawings signed and sealed by a Florida-licensed design professional and a plans-examiner review before the permit is issued; sheds under that size and cost, with no final inspection required, can often be issued the same visit.See schedule

Frequently asked questions

Do you need a solar permit in Jacksonville?
Yes, before installing a solar water heater, solar collector system, or rooftop solar photovoltaic array at a residence in the City of Jacksonville (Duval County). If you are unsure how that applies to your project, call the permit office at (904) 255-8500 before you start.
How much does a solar permit cost in Jacksonville?
The fee wording from the official schedule is in the cost table on this page, as we read it on 17 Nov 2026. For the figure on your own project, call the permit office at (904) 255-8500.
Where do you apply for a solar permit in Jacksonville?
You can apply through the Jacksonville permit portal or contact the Building Inspection Division (City of Jacksonville Department of Public Works) directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Jacksonville?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Jacksonville applies this before you apply.

From the Library

Solar Permit in other Florida localities

Everything above, sourced

How this solar permit page for Jacksonville was verified. 2 official sources: jacksonville.gov, jacksonville.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Building Inspection Division (City of Jacksonville Department of Public Works). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page