Deck Permit in Lee County, Florida
Permit required
Yes, a permit is required
Building, adding to, or remodeling a deck
Quick answer
Lee County requires a Residential Accessory Structure permit to build, add to, or remodel a deck. A Notice of Commencement is required when project value is greater than $5,000.
- Issued by
- Lee County Community Development, Building and Permitting Services
- Phone
- 239-533-8329
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
If a contractor builds your deck, they usually handle the permit as part of the job. Compare a few bids before you commit.
Compare deck contractor quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
Deck size, height and setback rules in Lee County
- Setback
- A deck must meet the street setbacks, the waterbody setbacks, and the same rear and side lot line setbacks as other residential accessory structures (Section 34-1174(d)). library.municode.com: land development code
- Also required
- An unroofed deck or patio may be no more than three and one-half feet above grade unless it meets the setbacks for the house itself (outside a special flood hazard area), or, in a special flood hazard area, sits at or below the lowest permitted habitable floor elevation and keeps a rear setback of at least ten feet. library.municode.com: land development code
- Setback
- On a waterfront lot, a deck no higher than three and one-half feet above grade that is fenced, or screened on at least three sides, may come no closer than five feet to a seawalled canal or seawalled natural water body, ten feet to a non-seawalled artificial water body, or 25 feet to a non-seawalled natural water body. library.municode.com: land development code
What your deck permit must meet in Florida
In Florida a residential deck is built to the Florida Building Code, Residential (8th Edition, 2023), which is based on the 2021 IRC with statewide wind amendments. The governing concern is wind rather than frost: the deck and its attachment to the house must be designed for the local ultimate design wind speed, and it must meet the guard, stair, and connection requirements.
- Guards are required on any deck walking surface more than 30 inches above the grade or floor below, with a minimum guard height of 36 inches (FBC-R R312).
- Guard infill and balusters must be spaced so a 4-inch sphere cannot pass through; on the open side of stairs a 4 3/8 inch sphere limit applies (FBC-R R312).
- The deck must be constructed for the local ultimate design wind speed (Vult) taken from Figure R301.2(4), not a fixed minimum (FBC-R R301.2.1).
- Decks must be positively anchored to the primary structure for both vertical and lateral loads; the prescriptive lateral connection uses hold-down tension devices at not less than 2 locations within 24 inches of each end, each rated at least 1,500 lb, and joists framed to a ledger require approved joist hangers (FBC-R R507.8).
- Stairs when present allow a maximum riser height of 7 3/4 inches, a minimum tread depth of 10 inches, and a minimum stair width of 36 inches (FBC-R R311.7).
- Stair handrails are required on any flight with 4 or more risers, mounted 34 to 38 inches above the tread nosing (FBC-R R311.7).
- There is no frost-depth footing requirement in Florida; deck footings and piers are governed by wind uplift and lateral connection detailing. In the High-Velocity Hurricane Zone (Miami-Dade and Broward counties), additional wind-design and product-approval requirements apply.
Based on Florida Building Code, Residential (8th Edition, 2023): R312 guards, R311.7 stairs, R301.2.1 wind speed, R507.8 deck attachment. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What a deck permit costs in Lee County
- Fee schedule in force
- Official scheduleRead .
- Published in
- Fee schedule effective 2026-04-15:
$50 application fee and $35 technology fee per application plus an operational support fee;
residential accessory structure plan review $35 to $50 initial, regulatory review $25, inspections $50 per required inspection at 2,500 sq ft work area or less.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Lee County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | Permit required | Any size |
| Broward County | Permit required | Any size |
| Charlotte County | Permit required | Any size |
| Clay County | Permit required | an elevated deck, as distinct from other deck work |
| Hernando County | Permit required | Any size |
| Hillsborough County | It depends | decks are not on the county's list of exempt work; the county says a project not on that list most likely requires a permit; confirm with Development Services |
| Lee Countythis page | Permit required | Any size |
How to apply in Lee County
General guide, not specific to this office
What a deck permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a deck permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Lee County Community Development, Building and Permitting Services
- 1500 Monroe St., Fort Myers, FL 33901
- Phone: 239-533-8329
- Email: econnect@leegov.com
Your Deck Permit checklist for Lee County
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: leegov.com: Residential Shed and Deck Guide.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Lee County permit portal.
- Keep the office details handy. Lee County Community Development, Building and Permitting Services. Phone: 239-533-8329. Email: econnect@leegov.com. Address: 1500 Monroe St., Fort Myers, FL 33901.
Compiled from the official sources on this page. Last checked .
Permitting activity in Lee County
In 2025, Lee County authorized permits for 13,547 new residential housing units (9,962 single-family, 3,585 in multi-family buildings), valued at $3.8B, down from 15,411 the year before. That works out to about 15.5 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 875,607.
What else needs a permit in Lee County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
Fee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee, for every permit type below. The fee column shows what differs by project.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Electrical Permit | Permit required | Any size | Electrical trade plan review $35 initial, inspections $75 per record covering up to 2 inspections |
| Fence Permit | Permit required | Any size | Residential fence plan review $35 initial, regulatory review $25, structural inspections $50 per required inspection |
| HVAC Permit | Permit required | Portable HVAC equipment and replacement of any part that does not alter the equipment's approval or make it unsafe are exempt per Florida Building Code section 105.2. | Residential mechanical plan review $25 initial, inspections $75 per record covering up to 2 inspections |
| Patio Permit | It depends | A permit is required to construct, enlarge, alter, or repair a structure, including structural slabs, unenclosed structures, porches, and screen, glass, or vinyl rooms; the county refers residents to Florida Building Code 105.2 and Land Development Code 6-117 for work not requiring a permit. | See schedule |
| Plumbing Permit | Permit required | Any size | Residential plumbing plan review $25 initial, inspections $75 per record covering up to 2 inspections |
| Pool Permit | It depends | All in-ground pool construction or renovation requires a permit; an above-ground pool requires a permit when its water depth is 24 inches or more. | Residential pool plan review $35 initial, regulatory review $25, structural, electrical, and plumbing inspections $50 per required inspection |
| Roof Replacement Permit | It depends | Under s. 553.79(1)(g) F.S., effective 2026-07-01, the county must exempt work on a single-family dwelling valued at less than $7,500 upon written request, but the exemption does not apply to structural, electrical, plumbing, mechanical, or gas work or to property in a flood hazard area. | Roofing plan review $25 initial, structural inspection $100, roofing fees assessed per structure |
| Shed Permit | Permit required | Any size | Residential accessory structure plan review $35 to $50 initial, regulatory review $25, inspections $50 per required inspection at 2,500 sq ft work area or less |
| Solar Permit | Permit required | Any size | Solar plan review $25 initial, regulatory review $25, ground or roof mounted PV inspections $50 per required inspection; the schedule has the rest |
Frequently asked questions
- Do you need a deck permit in Lee County?
- Yes. Building, adding to, or remodeling a deck. If you are unsure how that applies to your project, call the Lee County Community Development, Building and Permitting Services at 239-533-8329 before you start.
- How much does a deck permit cost in Lee County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the Lee County Community Development, Building and Permitting Services at 239-533-8329.
- Where do you apply for a deck permit in Lee County?
- You can apply through the Lee County permit portal or contact the Lee County Community Development, Building and Permitting Services directly. The links are listed on this page.
- Can a homeowner pull a deck permit themselves in Lee County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Lee County applies this before you apply.
From the Library
Deck Permit in other Florida localities
Everything above, sourced
How this deck permit page for Lee County was verified. 5 official sources: leegov.com, leegov.com, leegov.com, leegov.com, leefl.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Lee County Community Development, Building and Permitting Services. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page