Florida / Lee County

Solar Permit in Lee County, Florida

Permit required

Yes, a permit is required

Adding or modifying solar PV, solar water, or solar pool heating

Confirmed on official page Verified

Issued byLee County Community Development, Building and Permitting Services

By Mario Bailey, verified against official sources

Quick answer

Lee County requires a Solar/Photovoltaic permit to add or modify any solar pool heater, solar hot water heater, rooftop HVAC collector, or any photovoltaic power system on any residential or commercial property. Applicable codes include the Florida Building Code 8th Edition (2023) and the National Electric Code NFPA 70 (2020).

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Adding or modifying solar PV, solar water, or solar pool heating

What a solar permit costs in Lee County

Line item
solar permitBy formulaFee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee; solar plan review $25 initial, regulatory review $25, ground or roof mounted PV inspections $50 per required inspection, other solar types $75 covering up to 2 inspections.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Lee County compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alachua CountyPermit requiredNo solar-specific flat fee is published
Brevard CountyPermit requiredBrevard's Residential Solar Photovoltaic Permit Application fee table lists a...
Charlotte CountyPermit requiredAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if...
Collier CountyPermit requiredFee Schedule (Resolution 2025-231, effective January 1, 2026), Solar Permit...
Hernando CountyPermit requiredPhotovoltaic System (Res): $180.00
Hillsborough CountyPermit requiredResidential Photovoltaic trade permit fee is $250 flat, inspection-only with...
Lee Countythis pagePermit requiredFee schedule effective 2026-04-15: $50 application fee and $35 technology fee...

How to apply in Lee County

In Lee County, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • For Lee County, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • For Lee County, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • For Lee County, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Lee County Community Development, Building and Permitting Services sets the exact checklist for Lee County.

Where to apply in Lee County:

Lee County Community Development, Building and Permitting Services

Solar Permit in Lee County compared with nearby Florida localities

LocalityPermit needed?ThresholdWhat each Florida schedule saysVerified
Lee CountyPermit requiredNot specifiedFee schedule effective 2026-04-15: $50 application fee and $35 technology fee per...
Alachua CountyPermit requiredNot specifiedNo solar-specific flat fee is published
Brevard CountyPermit requiredNot specifiedBrevard's Residential Solar Photovoltaic Permit Application fee table lists a Building...
Broward CountyPermit requiredNot specifiedNot published
Charlotte CountyPermit requiredNot specifiedAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation...

Inspections and closing out your permit

In Lee County, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. In Lee County: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. In Lee County: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. In Lee County: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. In Lee County: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. In Lee County: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. In Lee County: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Lee County permit portal or by phone at 239-533-8329.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Lee County?
Lee County requires a Solar/Photovoltaic permit to add or modify any solar pool heater, solar hot water heater, rooftop HVAC collector, or any photovoltaic power system on any residential or commercial property. Applicable codes include the Florida Building Code 8th Edition (2023) and the National Electric Code NFPA 70 (2020). Always confirm with the Lee County Community Development, Building and Permitting Services before starting.
How much does a solar permit cost in Lee County?
Fee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee; solar plan review $25 initial, regulatory review $25, ground or roof mounted PV inspections $50 per required inspection, other solar types $75 covering up to 2 inspections. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Lee County?
You can apply through the Lee County permit portal or contact the Lee County Community Development, Building and Permitting Services directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Lee County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Lee County applies this before you apply.

From the Library

What else needs a permit in Lee County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

Fee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee, for every permit type below. The fee column shows what differs by project.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNot specifiedResidential accessory structure plan review $35 to $50 initial, regulatory review $25...
Electrical PermitPermit requiredNot specifiedElectrical trade plan review $35 initial, inspections $75 per record covering up to 2...
Fence PermitPermit requiredNot specifiedResidential fence plan review $35 initial, regulatory review $25, structural inspections...
HVAC PermitPermit requiredPortable HVAC equipment and replacement of any part that does not alter the equipment's approval or make it unsafe are exempt per Florida Building Code section 105.2.Residential mechanical plan review $25 initial, inspections $75 per record covering up...
Patio PermitIt dependsA permit is required to construct, enlarge, alter, or repair a structure, including structural slabs, unenclosed structures, porches, and screen, glass, or vinyl rooms; the county refers residents to Florida Building Code 105.2 and Land Development Code 6-117 for work not requiring a permit.Fees follow the residential accessory structure table when the patio is permitted as an...
Plumbing PermitPermit requiredNot specifiedResidential plumbing plan review $25 initial, inspections $75 per record covering up to...
Pool PermitIt dependsAll in-ground pool construction or renovation requires a permit; an above-ground pool requires a permit when its water depth is 24 inches or more.Residential pool plan review $35 initial, regulatory review $25, structural, electrical...
Roof Replacement PermitIt dependsUnder s. 553.79(1)(g) F.S., effective 2026-07-01, the county must exempt work on a single-family dwelling valued at less than $7,500 upon written request, but the exemption does not apply to structural, electrical, plumbing, mechanical, or gas work or to property in a flood hazard area.Roofing plan review $25 initial, structural inspection $100, roofing fees assessed per...
Shed PermitPermit requiredNot specifiedResidential accessory structure plan review $35 to $50 initial, regulatory review $25...

Solar Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Lee County documents; the office above sets the local rules.

How this solar permit page for Lee County was verified. 3 official sources: leegov.com, leegov.com, leegov.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Lee County Community Development, Building and Permitting Services. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Solar Permit requirements across Florida localities

Solar permit rules nationwide

Look up an existing Lee County permit record

Permit required
Get quotes