Solar Permit in Lee County, Florida
Permit required
Yes, a permit is required
Adding or modifying solar PV, solar water, or solar pool heating
Quick answer
Lee County requires a Solar/Photovoltaic permit to add or modify any solar pool heater, solar hot water heater, rooftop HVAC collector, or any photovoltaic power system on any residential or commercial property. Applicable codes include the Florida Building Code 8th Edition (2023) and the National Electric Code NFPA 70 (2020).
- Issued by
- Lee County Community Development, Building and Permitting Services
- Phone
- 239-533-8329
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your Florida Department of Business and Professional Regulation license active, and under which business name? Verify it on www.myfloridalicense.com.
Florida's owner-builder rule (F.S. 489.103(7)(a)-(c)) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Lee County
- Fee schedule in force
- Official scheduleRead .
- Published in
- Fee schedule effective 2026-04-15:
$50 application fee and $35 technology fee per application plus an operational support fee;
solar plan review $25 initial, regulatory review $25, ground or roof mounted PV inspections $50 per required inspection, other solar types $75 covering up to 2 inspections.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Lee County compares in Florida
No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alachua County | Permit required | No solar-specific flat fee is published |
| Brevard County | Permit required | See schedule |
| Charlotte County | Permit required | At application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation is $50,000 or more) and a 0.025 x building-fee surcharge |
| Collier County | Permit required | See schedule |
| Hernando County | Permit required | Photovoltaic System (Res): $180.00 |
| Hillsborough County | Permit required | Residential Photovoltaic trade permit fee is $250 flat, inspection-only with no plan review; the schedule has the rest |
| Lee Countythis page | Permit required | Fee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee |
How to apply in Lee County
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Lee County Community Development, Building and Permitting Services
- 1500 Monroe St., Fort Myers, FL 33901
- Phone: 239-533-8329
- Email: econnect@leegov.com
Your Solar Permit checklist for Lee County
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: leegov.com: Solar Photovoltaic Guide.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Lee County permit portal.
- Keep the office details handy. Lee County Community Development, Building and Permitting Services. Phone: 239-533-8329. Email: econnect@leegov.com. Address: 1500 Monroe St., Fort Myers, FL 33901.
Compiled from the official sources on this page. Last checked .
Permitting activity in Lee County
In 2025, Lee County authorized permits for 13,547 new residential housing units (9,962 single-family, 3,585 in multi-family buildings), valued at $3.8B, down from 15,411 the year before. That works out to about 15.5 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 875,607.
What else needs a permit in Lee County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
Fee schedule effective 2026-04-15: $50 application fee and $35 technology fee per application plus an operational support fee, for every permit type below. The fee column shows what differs by project.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Any size | Residential accessory structure plan review $35 to $50 initial, regulatory review $25, inspections $50 per required inspection at 2,500 sq ft work area or less |
| Electrical Permit | Permit required | Any size | Electrical trade plan review $35 initial, inspections $75 per record covering up to 2 inspections |
| Fence Permit | Permit required | Any size | Residential fence plan review $35 initial, regulatory review $25, structural inspections $50 per required inspection |
| HVAC Permit | Permit required | Portable HVAC equipment and replacement of any part that does not alter the equipment's approval or make it unsafe are exempt per Florida Building Code section 105.2. | Residential mechanical plan review $25 initial, inspections $75 per record covering up to 2 inspections |
| Patio Permit | It depends | A permit is required to construct, enlarge, alter, or repair a structure, including structural slabs, unenclosed structures, porches, and screen, glass, or vinyl rooms; the county refers residents to Florida Building Code 105.2 and Land Development Code 6-117 for work not requiring a permit. | See schedule |
| Plumbing Permit | Permit required | Any size | Residential plumbing plan review $25 initial, inspections $75 per record covering up to 2 inspections |
| Pool Permit | It depends | All in-ground pool construction or renovation requires a permit; an above-ground pool requires a permit when its water depth is 24 inches or more. | Residential pool plan review $35 initial, regulatory review $25, structural, electrical, and plumbing inspections $50 per required inspection |
| Roof Replacement Permit | It depends | Under s. 553.79(1)(g) F.S., effective 2026-07-01, the county must exempt work on a single-family dwelling valued at less than $7,500 upon written request, but the exemption does not apply to structural, electrical, plumbing, mechanical, or gas work or to property in a flood hazard area. | Roofing plan review $25 initial, structural inspection $100, roofing fees assessed per structure |
| Shed Permit | Permit required | Any size | Residential accessory structure plan review $35 to $50 initial, regulatory review $25, inspections $50 per required inspection at 2,500 sq ft work area or less |
Frequently asked questions
- Do you need a solar permit in Lee County?
- Yes. Adding or modifying solar PV, solar water, or solar pool heating. If you are unsure how that applies to your project, call the Lee County Community Development, Building and Permitting Services at 239-533-8329 before you start.
- How much does a solar permit cost in Lee County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 11 Nov 2026. For the figure on your own project, call the Lee County Community Development, Building and Permitting Services at 239-533-8329.
- Where do you apply for a solar permit in Lee County?
- You can apply through the Lee County permit portal or contact the Lee County Community Development, Building and Permitting Services directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Lee County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Lee County applies this before you apply.
From the Library
Solar Permit in other Florida localities
Everything above, sourced
How this solar permit page for Lee County was verified. 4 official sources: leegov.com, leegov.com, leegov.com, leefl.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Lee County Community Development, Building and Permitting Services. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page