Shed Permit in Leon County, Florida
It depends
Sometimes, depending on the project
Before installing a shed over 100 square feet in unincorporated Leon County; smaller sheds still require Development Services/Environmental Services site review even though no building permit is needed
By Mario Bailey, verified against official sources
Quick answer
Leon County requires a building permit for any shed larger than 100 square feet. Sheds at or under that size still are not exempt from all county review: they must be reviewed by the Development Services and Environmental Services Divisions for setbacks from boundary lines, easements, floodplain, and similar site factors. This applies to unincorporated Leon County; the City of Tallahassee runs its own building department.
Typical threshold: Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain.

Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing a shed over 100 square feet in unincorporated Leon County; smaller sheds still require Development Services/Environmental Services site review even though no building permit is needed
What your shed permit must meet in Florida
Florida sheds are built under the Florida Building Code, Residential, 8th Edition (2023), which requires structures to be designed for the state's wind loads, but Florida Statutes carve out two specific size-based reductions in what a shed must resist or include.
- As a structure, a shed is generally subject to the Florida Building Code's baseline wind-design requirement that applies to buildings and structures statewide (FBC Section 1609.1).
- Storage sheds not designed for human habitation with a floor area of 720 square feet or less are exempt from the code's mandatory windborne-debris-impact (opening protection) standard (F.S. 553.73(10)).
- Buildings of 400 square feet or less used in conjunction with a one- or two-family residence, which covers most sheds, are exempt from the code's door height and width requirements (F.S. 553.73(10)).
Based on Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What a shed permit costs in Leon County
How Leon County compares in Florida
Across the Florida jurisdictions we have verified, the same threshold runs from 68 to 150, so a project that is exempt here may still need a permit one county over.
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | It depends | area of a single storage shed, exemption available once per property |
| Brevard County | It depends | A permit is required for an accessory structure (shed) over 100 square feet. |
| Charlotte County | It depends | A building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm. |
| Escambia County | It depends | A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size. |
| Hernando County | It depends | Sheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met |
| Hillsborough County | It depends | sheds under 150 sq ft are exempt; 150 sq ft or larger require a building permit |
| Leon Countythis page | It depends | Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain. |
Closest shed permit thresholds outside Florida
Jurisdictions we cover whose limit sits nearest Leon County's 100 sq ft.
- Arlington, Texas, floor area of a one-story detached tool or storage shed
- Cincinnati, Ohio, total floor area of a shed accessory to a one-, two- or three-family dwelling
- Nashville, Tennessee, accessory structures 100 sq ft or larger require a permit; structures under 100 sq ft may not require a permit
- Cook County, Illinois, prefabricated storage containers
How to apply in Leon County
A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.
What most shed permit applications include:
- A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
- A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
- Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
- Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
- Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).
General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division sets the exact checklist for Leon County.
Where to apply in Leon County:
Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division
- 435 N. Macomb Street, Renaissance Center, 2nd Floor, Tallahassee, FL 32301
- Phone: 850-606-1300
- Email: PooleJ@LeonCountyFL.gov
Inspections and closing out your permit
A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
- Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
- Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
- Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
- For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Leon County permit portal or by phone at 850-606-1300.
Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Shed Permit checklist for Leon County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain. Usually needed: Before installing a shed over 100 square feet in unincorporated Leon County; smaller sheds still require Development Services/Environmental Services site review even though no building permit is needed.
- Budget the fee. Fee Schedule, Residential One and Two-Family category, which covers "detached accessory structures" and is billed "Based on sq. ft. under roof": Building Plan Review $0.16 per sq ft plus Building Inspection $0.15 per sq ft (additional trades billed separately if applicable). Official fee schedule.
- Apply. A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing. Start at the Leon County permit portal.
- Keep the office details handy. Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division. Phone: 850-606-1300. Address: 435 N. Macomb Street, Renaissance Center, 2nd Floor, Tallahassee, FL 32301.
- Plan for inspections. A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a shed permit in Leon County?
- Leon County requires a building permit for any shed larger than 100 square feet. Sheds at or under that size still are not exempt from all county review: they must be reviewed by the Development Services and Environmental Services Divisions for setbacks from boundary lines, easements, floodplain, and similar site factors. This applies to unincorporated Leon County; the City of Tallahassee runs its own building department. Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain. Always confirm with the office before starting.
- How much does a shed permit cost in Leon County?
- Fee Schedule, Residential One and Two-Family category, which covers "detached accessory structures" and is billed "Based on sq. ft. under roof": Building Plan Review $0.16 per sq ft plus Building Inspection $0.15 per sq ft (additional trades billed separately if applicable). See the official fee schedule for current amounts.
- How long does a shed permit take in Leon County?
- In Leon County, a shed permit typically takes 5 days is the county's published typical approval time for "Accessory Structures"; the Accela portal's own Building record-type list names this category "Residential Accessory Structure," the category a shed permit would fall under. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a shed permit in Leon County?
- You can apply through the Leon County permit portal or contact the Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a shed permit themselves in Leon County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Leon County applies this before you apply.
From the Library
What else needs a permit in Leon County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it). | Fee Schedule, "Construction Not Under Roof" flat-fee category: "Decks, Docks, Ramps... |
| Electrical Permit | Permit required | Not specified | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Electrical Plan Review... |
| Fence Permit | It depends | Traditional fences (chain link, wooden, etc.) do not need a building permit; a solid wall does. | The Fee Schedule (Development Support & Environmental Management Department Fee... |
| HVAC Permit | Permit required | Not specified | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Mechanical Plan Review... |
| Patio Permit | It depends | Patio covers, sunrooms, and screen or pool enclosures are handled as aluminum structures requiring a permit; a plain open, unroofed, at-grade patio slab is not separately addressed in any published county page found. | The Fee Schedule has no line item named "Patio" or "Aluminum Structure" |
| Plumbing Permit | Permit required | Not specified | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Plumbing Plan Review... |
| Pool Permit | Permit required | Applies to private residential swimming pools, hot tubs, or non-portable spas containing water over 24 inches deep. | Fee Schedule, "Swimming Pools" flat-fee category: "Above-Ground Pools $180.00,"... |
| Roof Replacement Permit | Permit required | Not specified | Fee Schedule, "Repair Work and Exterior Alteration Permits" flat-fee category: "Re-roof... |
| Solar Permit | Permit required | Not specified | Fee Schedule, "Solar Installation Permits" flat-fee category: "Solar Photovoltaic... |
Shed Permit in other Florida localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Leon County documents; the office above sets the local rules.
- IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC
- IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC
- Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1
Verified by a person against the sources above on , not confirmed with Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Permit office
Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division
850-606-1300Permit portalFlorida rule changes
- Broward County, FL updates building permit fee schedule (Ordinance 2025-038)
Ord. 2025-038 ·
- Florida waives permits for small single-family jobs under $7,500 (HB 803)
ch. 2026-63 (HB 803), F.S. 553.79 ·
Compare
Shed Permit across Florida