Before building a deck greater than 100 square feet in area, or more than 30 inches above grade on any side, in unincorporated Leon County
Quick answer
Leon County requires a building permit for a deck once it exceeds 100 square feet in area or rises more than 30 inches above grade on any side; the county's FAQ joins the two triggers with "and/or," so either one alone requires the permit. Decks under both thresholds are not addressed as needing a permit on the county's published FAQ. This applies to unincorporated Leon County; the City of Tallahassee operates its own building department and may set different rules.
- Typical threshold
- Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it).
- Issued by
- Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division
- Phone
- 850-606-1300
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
If a contractor builds your deck, they usually handle the permit as part of the job. Compare a few bids before you commit.
Compare deck contractor quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What your deck permit must meet in Florida
In Florida a residential deck is built to the Florida Building Code, Residential (8th Edition, 2023), which is based on the 2021 IRC with statewide wind amendments. The governing concern is wind rather than frost: the deck and its attachment to the house must be designed for the local ultimate design wind speed, and it must meet the guard, stair, and connection requirements.
- Guards are required on any deck walking surface more than 30 inches above the grade or floor below, with a minimum guard height of 36 inches (FBC-R R312).
- Guard infill and balusters must be spaced so a 4-inch sphere cannot pass through; on the open side of stairs a 4 3/8 inch sphere limit applies (FBC-R R312).
- The deck must be constructed for the local ultimate design wind speed (Vult) taken from Figure R301.2(4), not a fixed minimum (FBC-R R301.2.1).
- Decks must be positively anchored to the primary structure for both vertical and lateral loads; the prescriptive lateral connection uses hold-down tension devices at not less than 2 locations within 24 inches of each end, each rated at least 1,500 lb, and joists framed to a ledger require approved joist hangers (FBC-R R507.8).
- Stairs when present allow a maximum riser height of 7 3/4 inches, a minimum tread depth of 10 inches, and a minimum stair width of 36 inches (FBC-R R311.7).
- Stair handrails are required on any flight with 4 or more risers, mounted 34 to 38 inches above the tread nosing (FBC-R R311.7).
- There is no frost-depth footing requirement in Florida; deck footings and piers are governed by wind uplift and lateral connection detailing. In the High-Velocity Hurricane Zone (Miami-Dade and Broward counties), additional wind-design and product-approval requirements apply.
Based on Florida Building Code, Residential (8th Edition, 2023): R312 guards, R311.7 stairs, R301.2.1 wind speed, R507.8 deck attachment. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What a deck permit costs in Leon County
- Fee schedule in force
- Official scheduleRead .
- Published in
- Fee Schedule, "Construction Not Under Roof" flat-fee category:
"Decks, Docks, Ramps, Boardwalks, etc. $271.52."
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Leon County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Alachua County | Permit required | Any size |
| Broward County | Permit required | Any size |
| Charlotte County | Permit required | Any size |
| Clay County | Permit required | an elevated deck, as distinct from other deck work |
| Hernando County | Permit required | Any size |
| Leon Countythis page | It depends | Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it). |
| Manatee County | It depends | All attached decks require a building permit regardless of size. A detached deck requires a permit if it is over 30 inches high or over 120 square feet; a detached deck under 30 inches high and under 120 square feet does not require a permit. |
How to apply in Leon County
General guide, not specific to this office
What a deck permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a deck permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division
- 435 N. Macomb Street, Renaissance Center, 2nd Floor, Tallahassee, FL 32301
- Phone: 850-606-1300
- Email: PooleJ@LeonCountyFL.gov
Your Deck Permit checklist for Leon County
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it). Read the rule where we read it: cms.leoncountyfl.gov: Building Plans Review and Inspection.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Leon County permit portal.
- Keep the office details handy. Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division. Phone: 850-606-1300. Email: PooleJ@LeonCountyFL.gov. Address: 435 N. Macomb Street, Renaissance Center, 2nd Floor, Tallahassee, FL 32301.
Compiled from the official sources on this page. Last checked .
Permitting activity in Leon County
In 2025, Leon County authorized permits for 2,047 new residential housing units (617 single-family, 1,430 in multi-family buildings), valued at $437M, up from 1,765 the year before. That works out to about 6.8 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 299,048.
What else needs a permit in Leon County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Electrical Permit | Permit required | Any size | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Electrical Plan Review $0.10 per sq ft, Electrical Inspection $0.09 per sq ft |
| Fence Permit | It depends | Traditional fences (chain link, wooden, etc.) do not need a building permit; a solid wall does. | See schedule |
| HVAC Permit | Permit required | Any size | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Mechanical Plan Review $0.07 per sq ft, Mechanical Inspection $0.06 per sq ft |
| Patio Permit | It depends | Patio covers, sunrooms, and screen or pool enclosures are handled as aluminum structures requiring a permit; a plain open, unroofed, at-grade patio slab is not separately addressed in any published county page found. | See schedule |
| Plumbing Permit | Permit required | Any size | Fee Schedule, Residential Plan Review/Inspection (sq ft based): Plumbing Plan Review $0.05 per sq ft, Plumbing Inspection $0.04 per sq ft |
| Pool Permit | Permit required | Applies to private residential swimming pools, hot tubs, or non-portable spas containing water over 24 inches deep. | See schedule |
| Roof Replacement Permit | Permit required | Any size | Fee Schedule, "Repair Work and Exterior Alteration Permits" flat-fee category: "Re-roof or Roof Re-cover $241.45." |
| Shed Permit | It depends | Sheds over 100 square feet in area require a building permit; sheds of any size are still subject to Development Services and Environmental Services review for location, setbacks from boundary lines, easements, and floodplain. | See schedule |
| Solar Permit | Permit required | Any size | Fee Schedule, "Solar Installation Permits" flat-fee category: "Solar Photovoltaic Systems $180.00," "Solar Water Heating Systems $180.00." |
Frequently asked questions
- Do you need a deck permit in Leon County?
- It depends on the project. Decks greater than 100 square feet in area, or more than 30 inches above grade on any side, require a building permit (either condition alone triggers it). If you are unsure how that applies to your project, call the permit office at 850-606-1300 before you start.
- How much does a deck permit cost in Leon County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 13 Aug 2026. For the figure on your own project, call the permit office at 850-606-1300.
- Where do you apply for a deck permit in Leon County?
- You can apply through the Leon County permit portal or contact the Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a deck permit themselves in Leon County?
- Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Leon County applies this before you apply.
From the Library
Deck Permit in other Florida localities
Everything above, sourced
How this deck permit page for Leon County was verified. 2 official sources: cms.leoncountyfl.gov, cms.leoncountyfl.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Development Support & Environmental Management (DSEM), Building Plans Review and Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page