Florida / Escambia County

Shed Permit in Escambia County, Florida

It depends

Sometimes, depending on the project

Before installing a shed with a poured slab or ground-set posts (any size), or a portable skid-mounted shed of 120 square feet or more, in unincorporated Escambia County or the Town of Century

Confirmed on official page Verified Escambia County Building Services Department (Building Inspections Division / Plan Review Division)

By Mario Bailey, verified against official sources

Quick answer

Escambia County requires a building permit for any utility or storage shed built with a poured concrete slab or with posts set into the ground, regardless of the shed's size. The county's only published shed exemption covers a portable, skid-mounted utility shed under 120 square feet. This applies to unincorporated Escambia County and the Town of Century, which Escambia County Building Services also permits; the City of Pensacola runs its own building department.

Typical threshold: A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.

Diagram of the 120 sq ft footprint area threshold for a shed permit in Escambia County, Florida
Threshold illustrated: 120 sq ft. Whether Escambia County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-13.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a shed with a poured slab or ground-set posts (any size), or a portable skid-mounted shed of 120 square feet or more, in unincorporated Escambia County or the Town of Century

What your shed permit must meet in Florida

Florida sheds are built under the Florida Building Code, Residential, 8th Edition (2023), which requires structures to be designed for the state's wind loads, but Florida Statutes carve out two specific size-based reductions in what a shed must resist or include.

  • As a structure, a shed is generally subject to the Florida Building Code's baseline wind-design requirement that applies to buildings and structures statewide (FBC Section 1609.1).
  • Storage sheds not designed for human habitation with a floor area of 720 square feet or less are exempt from the code's mandatory windborne-debris-impact (opening protection) standard (F.S. 553.73(10)).
  • Buildings of 400 square feet or less used in conjunction with a one- or two-family residence, which covers most sheds, are exempt from the code's door height and width requirements (F.S. 553.73(10)).

Based on Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a shed permit costs in Escambia County

Line item
shed permitNot publishedEscambia County publishes no fee for this permit type in a schedule we can verify. Ask Escambia County Building Services Department (Building Inspections Division / Plan Review Division) how the fee is calculated for your project.

How Escambia County compares in Florida

Across the Florida jurisdictions we have verified, the same threshold runs from 68 to 150, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
Alachua CountyIt dependsarea of a single storage shed, exemption available once per property
Brevard CountyIt dependsA permit is required for an accessory structure (shed) over 100 square feet.
Charlotte CountyIt dependsA building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
Escambia Countythis pageIt dependsA portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Hernando CountyIt dependsSheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met
Hillsborough CountyIt dependssheds under 150 sq ft are exempt; 150 sq ft or larger require a building permit
Lake CountyIt dependsA shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint

Closest shed permit thresholds outside Florida

Jurisdictions we cover whose limit sits nearest Escambia County's 120 sq ft.

How to apply in Escambia County

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Escambia County Building Services Department (Building Inspections Division / Plan Review Division) sets the exact checklist for Escambia County.

Where to apply in Escambia County:

Escambia County Building Services Department (Building Inspections Division / Plan Review Division)

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Escambia County permit portal or by phone at (850) 595-3550.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a shed permit in Escambia County?
Escambia County requires a building permit for any utility or storage shed built with a poured concrete slab or with posts set into the ground, regardless of the shed's size. The county's only published shed exemption covers a portable, skid-mounted utility shed under 120 square feet. This applies to unincorporated Escambia County and the Town of Century, which Escambia County Building Services also permits; the City of Pensacola runs its own building department. A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size. Always confirm with the office before starting.
How much does a shed permit cost in Escambia County?
Fees are set by Escambia County and are not published here. Contact the office for current amounts.
Where do you apply for a shed permit in Escambia County?
You can apply through the Escambia County permit portal or contact the Escambia County Building Services Department (Building Inspections Division / Plan Review Division) directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Escambia County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Escambia County applies this before you apply.

From the Library

What else needs a permit in Escambia County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?Threshold
Deck PermitPermit requiredNot specified
Electrical PermitPermit requiredNot specified
Fence PermitNo permit neededNot specified
HVAC PermitPermit requiredNot specified
Patio PermitPermit requiredNot specified
Plumbing PermitPermit requiredNot specified
Pool PermitPermit requiredNot specified
Roof Replacement PermitIt dependsA Re-Roofing Permit is required for re-roofs exceeding 2 squares (1 square equals 100 square feet, so 2 squares equals 200 square feet); roof repair work under two squares does not require a permit.
Solar PermitPermit requiredNot specified

Shed Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Escambia County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Escambia County Building Services Department (Building Inspections Division / Plan Review Division). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Shed Permit requirements across Florida localities

Look up an existing Escambia County permit record

It depends