It depends

Sometimes, depending on the project

Before installing a shed with a poured slab or ground-set posts (any size), or a portable skid-mounted shed of 120 square feet or more, in unincorporated Escambia County or the Town of Century

Quick answer

Escambia County requires a building permit for any utility or storage shed built with a poured concrete slab or with posts set into the ground, regardless of the shed's size. The county's only published shed exemption covers a portable, skid-mounted utility shed under 120 square feet. This applies to unincorporated Escambia County and the Town of Century, which Escambia County Building Services also permits; the City of Pensacola runs its own building department.

Diagram of the 120 sq ft footprint area threshold for a shed permit in Escambia County, Florida
Threshold illustrated: 120 sq ft. Whether Escambia County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-13.
Typical threshold
A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Issued by
Escambia County Building Services Department (Building Inspections Division / Plan Review Division)
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

If a contractor builds or places your shed, they usually handle any required permit. Compare a few bids before you commit.

Compare contractor quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What your shed permit must meet in Florida

Florida sheds are built under the Florida Building Code, Residential, 8th Edition (2023), which requires structures to be designed for the state's wind loads, but Florida Statutes carve out two specific size-based reductions in what a shed must resist or include.

  • As a structure, a shed is generally subject to the Florida Building Code's baseline wind-design requirement that applies to buildings and structures statewide (FBC Section 1609.1).
  • Storage sheds not designed for human habitation with a floor area of 720 square feet or less are exempt from the code's mandatory windborne-debris-impact (opening protection) standard (F.S. 553.73(10)).
  • Buildings of 400 square feet or less used in conjunction with a one- or two-family residence, which covers most sheds, are exempt from the code's door height and width requirements (F.S. 553.73(10)).

Based on Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a shed permit costs in Escambia County

Permit fee
Not published

Escambia County publishes no fee for this permit type in a schedule we can verify. Ask Escambia County Building Services Department (Building Inspections Division / Plan Review Division) how the fee is calculated for your project.

How Escambia County compares in Florida

Across the Florida jurisdictions we have verified, the same threshold runs from 68 to 150, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
Alachua CountyIt dependsarea of a single storage shed, exemption available once per property
Brevard CountyIt dependsA permit is required for an accessory structure (shed) over 100 square feet.
Charlotte CountyIt dependsA building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
Escambia Countythis pageIt dependsA portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Hernando CountyIt dependsSheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met
Hillsborough CountyIt dependssheds less than 150 sq ft are exempt; sheds over 150 sq ft require a building permit; the county pages do not clearly place a shed of exactly 150 sq ft
Lake CountyIt dependsA shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint

How to apply in Escambia County

General guide, not specific to this office

What a shed permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a shed permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Escambia County Building Services Department (Building Inspections Division / Plan Review Division)

Permitting activity in Escambia County

In 2025, Escambia County authorized permits for 1,398 new residential housing units (1,366 single-family, 32 in multi-family buildings), valued at $411M, down from 1,462 the year before. That works out to about 4.2 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 333,834.

What else needs a permit in Escambia County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?Threshold
Deck PermitPermit requiredAny size
Electrical PermitPermit requiredAny size
Fence PermitNo permit neededExempt
HVAC PermitPermit requiredAny size
Patio PermitPermit requiredAny size
Plumbing PermitPermit requiredAny size
Pool PermitPermit requiredAny size
Roof Replacement PermitIt dependsA Re-Roofing Permit is required for re-roofs exceeding 2 squares (1 square equals 100 square feet, so 2 squares equals 200 square feet); roof repair work under two squares does not require a permit.
Solar PermitPermit requiredAny size

Frequently asked questions

Do you need a shed permit in Escambia County?
It depends on the project. A portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size. If you are unsure how that applies to your project, call the permit office at (850) 595-3550 before you start.
How much does a shed permit cost in Escambia County?
We found no published fee for a shed permit in Escambia County. To learn how it is calculated for your project, call the permit office at (850) 595-3550.
Where do you apply for a shed permit in Escambia County?
You can apply through the Escambia County permit portal or contact the Escambia County Building Services Department (Building Inspections Division / Plan Review Division) directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Escambia County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Escambia County applies this before you apply.

From the Library

Shed Permit in other Florida localities

Everything above, sourced

How this shed permit page for Escambia County was verified. 2 official sources: myescambia.com, myescambia.com. Last checked by Mario Bailey, not confirmed with Escambia County Building Services Department (Building Inspections Division / Plan Review Division). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

It depends
Check my project