It depends

Sometimes, depending on the project

Before installing a tool or storage shed over 120 square feet, one with electrical/HVAC/plumbing, or one not built by the owner on their own residence, in unincorporated Lake County

Confirmed on official page Verified Office of Building Services

By Mario Bailey, verified against official sources

Quick answer

Lake County exempts a one-story detached tool or storage shed from needing a building permit only when it is built by the property owner on the owner's own personal residence, has a footprint of 120 square feet or less, and has no electrical, HVAC, fuel gas, or plumbing. A shed exceeding any of those conditions, including one installed by a contractor, goes through the county's Residential Accessory Structure permit process. This applies to unincorporated Lake County; the cities of Clermont, Leesburg, Eustis, Mount Dora, Tavares, and other incorporated municipalities in the county run their own building departments.

Typical threshold: A shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint.

Diagram of the 120 sq ft footprint area threshold for a shed permit in Lake County, Florida
Threshold illustrated: 120 sq ft. Whether Lake County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-13.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a tool or storage shed over 120 square feet, one with electrical/HVAC/plumbing, or one not built by the owner on their own residence, in unincorporated Lake County

What your shed permit must meet in Florida

Florida sheds are built under the Florida Building Code, Residential, 8th Edition (2023), which requires structures to be designed for the state's wind loads, but Florida Statutes carve out two specific size-based reductions in what a shed must resist or include.

  • As a structure, a shed is generally subject to the Florida Building Code's baseline wind-design requirement that applies to buildings and structures statewide (FBC Section 1609.1).
  • Storage sheds not designed for human habitation with a floor area of 720 square feet or less are exempt from the code's mandatory windborne-debris-impact (opening protection) standard (F.S. 553.73(10)).
  • Buildings of 400 square feet or less used in conjunction with a one- or two-family residence, which covers most sheds, are exempt from the code's door height and width requirements (F.S. 553.73(10)).

Based on Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a shed permit costs in Lake County

Line item
shed permitBy formulaNo shed-specific line item is published in the FY 2026 Adopted Fee Schedule; a shed that exceeds the exemption is filed as a Residential Accessory Structure permit (checklist CL1), which the schedule does not price as a separate itemized rate.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Lake County compares in Florida

Across the Florida jurisdictions we have verified, the same threshold runs from 68 to 150, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
Alachua CountyIt dependsarea of a single storage shed, exemption available once per property
Brevard CountyIt dependsA permit is required for an accessory structure (shed) over 100 square feet.
Charlotte CountyIt dependsA building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
Escambia CountyIt dependsA portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Hernando CountyIt dependsSheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met
Hillsborough CountyIt dependssheds under 150 sq ft are exempt; 150 sq ft or larger require a building permit
Lake Countythis pageIt dependsA shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint

Closest shed permit thresholds outside Florida

Jurisdictions we cover whose limit sits nearest Lake County's 120 sq ft.

How to apply in Lake County

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Office of Building Services sets the exact checklist for Lake County.

Where to apply in Lake County:

Office of Building Services

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Lake County permit portal or by phone at 352-343-9653.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a shed permit in Lake County?
Lake County exempts a one-story detached tool or storage shed from needing a building permit only when it is built by the property owner on the owner's own personal residence, has a footprint of 120 square feet or less, and has no electrical, HVAC, fuel gas, or plumbing. A shed exceeding any of those conditions, including one installed by a contractor, goes through the county's Residential Accessory Structure permit process. This applies to unincorporated Lake County; the cities of Clermont, Leesburg, Eustis, Mount Dora, Tavares, and other incorporated municipalities in the county run their own building departments. A shed built by the property owner on the owner's own personal residence, with no electrical, HVAC, fuel gas, or plumbing, is exempt from a building permit up to a 120-square-foot footprint. Always confirm with the office before starting.
How much does a shed permit cost in Lake County?
No shed-specific line item is published in the FY 2026 Adopted Fee Schedule; a shed that exceeds the exemption is filed as a Residential Accessory Structure permit (checklist CL1), which the schedule does not price as a separate itemized rate. See the official fee schedule for current amounts.
Where do you apply for a shed permit in Lake County?
You can apply through the Lake County permit portal or contact the Office of Building Services directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Lake County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Lake County applies this before you apply.

From the Library

What else needs a permit in Lake County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsA deck built by the property owner on the owner's own personal residence is exempt from a building permit if it does not exceed 30 inches above grade and a 120-square-foot footprintNo deck-specific line item is published in the FY 2026 Adopted Fee Schedule
Electrical PermitPermit requiredNot specifiedResidential Trades - Electric, Plumbing, Mechanical, Gas (to include new, change-outs...
Fence PermitIt dependsMasonry or concrete fences 4 feet or less in height, and fences of any other material 6 feet or less in height, are exempt from a building permit under the county's Chapter 6 building-code amendmentResidential Walls and Fences (includes gates & seawalls
HVAC PermitPermit requiredNot specifiedResidential Trades - Electric, Plumbing, Mechanical, Gas (to include new, change-outs...
Plumbing PermitPermit requiredNot specifiedResidential Trades - Electric, Plumbing, Mechanical, Gas (to include new, change-outs...
Pool PermitIt dependsStorable swimming or wading pools capable of holding water to a maximum depth of 42 inches, or pools with nonmetallic molded polymeric or inflatable fabric walls regardless of dimension, are exempt from a building permit except for non-cord-and-plug electrical workPrivate Above-ground Swimming Pools or self contained spa (includes electric): $91.00
Roof Replacement PermitPermit requiredNot specifiedResidential Roofing (per square foot): $0.03, per the county's FY 2026 Adopted Fee...
Solar PermitPermit requiredNot specifiedNo solar/photovoltaic line item is published in the FY 2026 Adopted Fee Schedule

Shed Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Lake County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Office of Building Services. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page