Quick answer
A building permit is required for all residential swimming pools and spas in Miami-Dade County. Pools must be enclosed by a barrier at least 48 inches above grade per Miami-Dade County Code Section 33-12 and Florida Building Code requirements. Separate electrical and plumbing subsidiary permits may also be required.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Miami-Dade County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
Before constructing any residential swimming pool or spa
What your pool permit must meet in Florida
Florida residential pools are built under the Florida Building Code, Residential, 8th Edition (2023), which the Legislature requires to incorporate the safety-feature and barrier standards of the Residential Swimming Pool Safety Act (Florida Statutes Chapter 515).
- State law requires the Florida Building Code to uniformly implement the pool-safety statutes by including standards for residential swimming pool barriers, pool covers, latching devices, and door and window exit alarms (F.S. 553.73).
- A new residential pool must be built with at least one of five listed safety features, not necessarily a fence: a compliant barrier, an approved safety pool cover, exit alarms on doors and windows with access to the pool, self-closing self-latching doors, or a certified pool alarm (F.S. 515.27).
- If a barrier is used, it must be at least 4 feet high on the outside and may not have gaps, openings, indentations, or structural components that could let a young child crawl under, squeeze through, or climb over it, placed far enough from the water's edge that a child who gets past it does not immediately fall in (F.S. 515.29).
- Pool gates must open outward away from the pool, be self-closing, and have a self-latching device with its release mechanism on the pool side, positioned out of a young child's reach (F.S. 515.29).
- Where a removable mesh safety barrier is used, it must comply with ASTM F2286 and may not be installed on top of an above-ground or on-ground pool (FBC-R, 8th Edition change).
Based on Florida Statutes Chapter 515 (Residential Swimming Pool Safety Act, ss. 515.27, 515.29) as implemented by the Florida Building Code, Residential, 8th Edition (2023), Chapter 45. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What pool permit costs in Miami-Dade County
Installation of a residential swimming pool or spa carries a flat $640 building permit fee with separate electrical and plumbing sub-permits required, per Implementing Order 4-63 effective 6/30/2025.
How Miami-Dade County compares in Florida
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Broward County | Permit required | Not specified |
| Hillsborough County | Permit required | Not specified |
| Lee County | It depends | All in-ground pool construction or renovation requires a permit; an above-ground pool requires a permit when its water depth is 24 inches or more. |
| Miami-Dade Countythis page | Permit required | Not specified |
| Orange County | Permit required | Not specified |
| Palm Beach County | It depends | Portable or manufactured pools and spas less than 24 inches deep need no permit; all in-ground pools, larger above-ground pools, and spas require a Building Permit (Type 3(E) for 1 and 2 unit dwellings) plus applicable electrical, plumbing, and pool-barrier sub-permits, and must satisfy Florida's residential pool safety-feature requirements under F.S. 515.27 before final inspection. |
| Pasco County | Permit required | Only residential pool resurfacing is exempt; new pool or spa construction requires a building permit. |
How to apply in Miami-Dade County
A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. Miami-Dade County Department of Regulatory and Economic Resources sets the exact checklist for Miami-Dade County.
Where to apply in Miami-Dade County:
Miami-Dade County Department of Regulatory and Economic Resources
- 11805 SW 26 Street, Miami, FL 33175
- Phone: (786) 315-2100
- Email: permitcenter@miamidade.gov
Inspections and closing out your permit
Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Miami-Dade County permit portal or by phone at (786) 315-2100.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Miami-Dade County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before constructing any residential swimming pool or spa.
- Budget the fee. Installation of a residential swimming pool or spa carries a flat $640 building permit fee with separate electrical and plumbing sub-permits required, per Implementing Order 4-63 effective 6/30/2025. Official fee schedule.
- Apply. A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Miami-Dade County permit portal.
- Keep the office details handy. Miami-Dade County Department of Regulatory and Economic Resources. Phone: (786) 315-2100. Address: 11805 SW 26 Street, Miami, FL 33175.
- Plan for inspections. Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked 2026-06-18.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Miami-Dade County
In 2024, Miami-Dade County authorized permits for 10,608 new residential housing units (2,231 single-family, 8,377 in multi-family buildings), valued at $4.2B, down from12,781 the year before. That works out to about 3.7 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 2,838,461.
About Miami-Dade County
Miami-Dade County has about 1,085,414 housing units. The median home is valued at $425,400, against a median household income of $68,694. About 52% of homes are owner-occupied, and the typical home was built around 1980.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a pool permit in Miami-Dade County?
- A building permit is required for all residential swimming pools and spas in Miami-Dade County. Pools must be enclosed by a barrier at least 48 inches above grade per Miami-Dade County Code Section 33-12 and Florida Building Code requirements. Separate electrical and plumbing subsidiary permits may also be required. Always confirm with the Miami-Dade County Department of Regulatory and Economic Resources before starting.
- How much does a pool permit cost in Miami-Dade County?
- Installation of a residential swimming pool or spa carries a flat $640 building permit fee with separate electrical and plumbing sub-permits required, per Implementing Order 4-63 effective 6/30/2025. See the official fee schedule for current amounts.
- Where do you apply for a pool permit in Miami-Dade County?
- You can apply through the Miami-Dade County permit portal or contact the Miami-Dade County Department of Regulatory and Economic Resources directly. The links are listed on this page.
From the Library
What else needs a permit in Miami-Dade County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | wood deck 18 inches or less above ground is exempt; decks higher than 18 inches require a building permit | No dedicated deck line; |
| Electrical Permit | Permit required | Not specified | Residential wiring for new construction, additions, repairs and alterations is $0.11 pe... |
| Fence Permit | Permit required | Not specified | Fence type determines permit type: wood and masonry fences require a Building Permit (C... |
| HVAC Permit | Permit required | Not specified | An exact change out air conditioning system is charged $24.17 per ton subject to a $227... |
| Patio Permit | It depends | open concrete slabs and pavers outside the building do not require a building permit; roofed or screened patio enclosures require a permit | No dedicated patio line; |
| Plumbing Permit | Permit required | Not specified | Single family plumbing for new construction, additions or alterations is $0.140 per squ... |
| Roof Replacement Permit | It depends | under F.S. 553.79(1)(g) (HB 803, ch. 2026-63, effective 2026-07-01), work valued at less than $7,500 on a single-family dwelling qualifies for exemption upon a written exemption request with documentation of the nature and value of the work; the exemption excludes electrical, plumbing, structural, mechanical, and gas work and any property in a flood hazard area; the statute does not name roofing, so a non-structural reroof under that value can qualify; confirm with Miami-Dade County Department of Regulatory and Economic Resources. Much of Miami-Dade County lies in flood hazard areas where this exemption does not apply. | Re-roofing is charged per square foot of roof coverage including overhangs at $0.11 for... |
| Shed Permit | Permit required | only one utility shed up to 400 sq ft permitted per residential lot under County Code Section 33-20(k) | A prefabricated utility shed over 100 sq ft carries a flat $147 building permit fee; |
| Solar Permit | Permit required | Not specified | Roof mounted solar photovoltaic systems are $365.63 per system, or $250 per system usin... |
Pool Permit in other Florida localities
Official sources
Verified by a person against the sources above on 2026-06-18, not confirmed with Miami-Dade County Department of Regulatory and Economic Resources. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-18Report an error on this page
Permit office
Miami-Dade County Department of Regulatory and Economic Resources
(786) 315-2100Permit portalFlorida rule changes
- Broward County, FL updates building permit fee schedule (Ordinance 2025-038)
Ord. 2025-038 · 2026-07-25
- Florida waives permits for small single-family jobs under $7,500 (HB 803)
ch. 2026-63 (HB 803), F.S. 553.79 · 2026-07-25
Compare
Pool Permit across Florida