Florida / Miami-Dade County

Solar Permit in Miami-Dade County, Florida

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

A building permit is required for residential solar photovoltaic systems in Miami-Dade County. The application must include an Electrical Fee Sheet (Category 34), structural plans, roof layout drawings, wind load calculations, and electrical diagrams per NEC Article 690. Projects using renewable energy may qualify for Green Building Expedited review under Miami-Dade County Code Section 8-6.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Miami-Dade County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before installing any residential solar PV system

What solar permit costs in Miami-Dade County

Roof mounted solar photovoltaic systems are $365.63 per system, or $250 per system using the county's prescribed standardized mounting detail, per the county electrical fee sheet (rev 10/25).

Official fee schedule

How Miami-Dade County compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Hillsborough CountyPermit requiredResidential Photovoltaic trade permit fee is $250 flat, inspection-only with...
Lee CountyPermit requiredFee schedule effective 2026-04-15: $50 application fee and $35 technology fee...
Miami-Dade Countythis pagePermit requiredRoof mounted solar photovoltaic systems are $365.63 per system, or $250 per s...
Orange CountyPermit requiredNo dedicated solar line;
Palm Beach CountyPermit requiredCharged by value of construction with a $75 minimum for a solar photovoltaic...
Pasco CountyPermit requiredBase permit fee $45;
Pinellas CountyPermit requiredFlat fee by system type: photovoltaic systems $250 each, solar domestic water...

How to apply in Miami-Dade County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Miami-Dade County Department of Regulatory and Economic Resources sets the exact checklist for Miami-Dade County.

Where to apply in Miami-Dade County:

Miami-Dade County Department of Regulatory and Economic Resources

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Miami-Dade County permit portal or by phone at (786) 315-2100.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Miami-Dade County

In 2024, Miami-Dade County authorized permits for 10,608 new residential housing units (2,231 single-family, 8,377 in multi-family buildings), valued at $4.2B, down from12,781 the year before. That works out to about 3.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 2,838,461.

About Miami-Dade County

Miami-Dade County has about 1,085,414 housing units. The median home is valued at $425,400, against a median household income of $68,694. About 52% of homes are owner-occupied, and the typical home was built around 1980.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a solar permit in Miami-Dade County?
A building permit is required for residential solar photovoltaic systems in Miami-Dade County. The application must include an Electrical Fee Sheet (Category 34), structural plans, roof layout drawings, wind load calculations, and electrical diagrams per NEC Article 690. Projects using renewable energy may qualify for Green Building Expedited review under Miami-Dade County Code Section 8-6. Always confirm with the Miami-Dade County Department of Regulatory and Economic Resources before starting.
How much does a solar permit cost in Miami-Dade County?
Roof mounted solar photovoltaic systems are $365.63 per system, or $250 per system using the county's prescribed standardized mounting detail, per the county electrical fee sheet (rev 10/25). See the official fee schedule for current amounts.
Where do you apply for a solar permit in Miami-Dade County?
You can apply through the Miami-Dade County permit portal or contact the Miami-Dade County Department of Regulatory and Economic Resources directly. The links are listed on this page.

From the Library

What else needs a permit in Miami-Dade County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependswood deck 18 inches or less above ground is exempt; decks higher than 18 inches require a building permitNo dedicated deck line;
Electrical PermitPermit requiredNot specifiedResidential wiring for new construction, additions, repairs and alterations is $0.11 pe...
Fence PermitPermit requiredNot specifiedFence type determines permit type: wood and masonry fences require a Building Permit (C...
HVAC PermitPermit requiredNot specifiedAn exact change out air conditioning system is charged $24.17 per ton subject to a $227...
Patio PermitIt dependsopen concrete slabs and pavers outside the building do not require a building permit; roofed or screened patio enclosures require a permitNo dedicated patio line;
Plumbing PermitPermit requiredNot specifiedSingle family plumbing for new construction, additions or alterations is $0.140 per squ...
Pool PermitPermit requiredNot specifiedInstallation of a residential swimming pool or spa carries a flat $640 building permit...
Roof Replacement PermitIt dependsunder F.S. 553.79(1)(g) (HB 803, ch. 2026-63, effective 2026-07-01), work valued at less than $7,500 on a single-family dwelling qualifies for exemption upon a written exemption request with documentation of the nature and value of the work; the exemption excludes electrical, plumbing, structural, mechanical, and gas work and any property in a flood hazard area; the statute does not name roofing, so a non-structural reroof under that value can qualify; confirm with Miami-Dade County Department of Regulatory and Economic Resources. Much of Miami-Dade County lies in flood hazard areas where this exemption does not apply.Re-roofing is charged per square foot of roof coverage including overhangs at $0.11 for...
Shed PermitPermit requiredonly one utility shed up to 400 sq ft permitted per residential lot under County Code Section 33-20(k)A prefabricated utility shed over 100 sq ft carries a flat $147 building permit fee;

Solar Permit in other Florida localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with Miami-Dade County Department of Regulatory and Economic Resources. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-18Report an error on this page

Compare Solar Permit requirements across Florida localities