Florida / Miami-Dade County

Electrical Permit in Miami-Dade County, Florida

Permit required

Yes, a permit is required

For all new wiring, service upgrades, or electrical modifications

Confirmed on official page Verified

Issued byMiami-Dade County Department of Regulatory and Economic Resources

By Mario Bailey, verified against official sources

Quick answer

An electrical permit is required for new wiring, circuit additions, panel upgrades, and other electrical work in Miami-Dade County. Electrical permits are subsidiary permits issued under a master or primary permit. The county follows the Florida Building Code Electrical volume. Applications are submitted through the EPS Portal.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

For all new wiring, service upgrades, or electrical modifications

What an electrical permit costs in Miami-Dade County

Line item
electrical permitBy formulaResidential wiring for new construction, additions, repairs and alterations is $0.11 per square foot of the master permit floor area subject to a $227.90 minimum electrical permit fee, per the county electrical fee sheet (rev 10/25).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Miami-Dade County compares in Florida

JurisdictionPermit needed?Threshold
Alachua CountyPermit requiredNot specified
Brevard CountyIt dependsPermits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring.
Broward CountyPermit requiredNot specified
Charlotte CountyPermit requiredNot specified
Clay CountyPermit requiredNot specified
Collier CountyPermit requiredPermits shall not be required for the following: ... Electrical: 1. Repair work performed by licensed electrical contractors that does not exceed $1,500.00 in value of materials and labor. 2. Repair or replace existing light fixtures and ceiling fans. 3. Repair or replace electrical wall switches and wall outlet devices of 20 amps or less and 120 volts. 4. Repair/replace low voltage (under 77 volts) devices.
Miami-Dade Countythis pagePermit requiredNot specified

How to apply in Miami-Dade County

In Miami-Dade County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For Miami-Dade County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For Miami-Dade County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Miami-Dade County Department of Regulatory and Economic Resources sets the exact checklist for Miami-Dade County.

Where to apply in Miami-Dade County:

Miami-Dade County Department of Regulatory and Economic Resources

Electrical Permit in Miami-Dade County compared with nearby Florida localities

LocalityPermit needed?ThresholdWhat each Florida schedule saysVerified
Miami-Dade CountyPermit requiredNot specifiedResidential wiring for new construction, additions, repairs and alterations is $0.11 per...
Alachua CountyPermit requiredNot specifiedNo electrical-specific flat fee is published
Brevard CountyIt dependsPermits are required for the installation or replacement of electrical wiring, meter cans, and breaker panels; this does not include changing fixtures that do not require moving or changing wiring.Brevard's Residential Electrical Permit Application fee table lists a Building Code...
Broward CountyPermit requiredNot specifiedElectrical permit is the greater of a $125 minimum base fee or 3.0% of job value, per...
Charlotte CountyPermit requiredNot specifiedAt application: flat fee $90, plus a building fee of 0.004 x ICC valuation (if valuation...

Inspections and closing out your permit

In Miami-Dade County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In Miami-Dade County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In Miami-Dade County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In Miami-Dade County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In Miami-Dade County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In Miami-Dade County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In Miami-Dade County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In Miami-Dade County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Miami-Dade County permit portal or by phone at (786) 315-2100.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Miami-Dade County

In 2024, Miami-Dade County authorized permits for 10,608 new residential housing units (2,231 single-family, 8,377 in multi-family buildings), valued at $4.2B, down from 12,781 the year before. That works out to about 3.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 2,838,461.

About Miami-Dade County

Miami-Dade County has about 1,085,414 housing units. The median home is valued at $425,400, against a median household income of $68,694. About 52% of homes are owner-occupied, and the typical home was built around 1980.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need an electrical permit in Miami-Dade County?
An electrical permit is required for new wiring, circuit additions, panel upgrades, and other electrical work in Miami-Dade County. Electrical permits are subsidiary permits issued under a master or primary permit. The county follows the Florida Building Code Electrical volume. Applications are submitted through the EPS Portal. Always confirm with the Miami-Dade County Department of Regulatory and Economic Resources before starting.
How much does an electrical permit cost in Miami-Dade County?
Residential wiring for new construction, additions, repairs and alterations is $0.11 per square foot of the master permit floor area subject to a $227.90 minimum electrical permit fee, per the county electrical fee sheet (rev 10/25). See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Miami-Dade County?
You can apply through the Miami-Dade County permit portal or contact the Miami-Dade County Department of Regulatory and Economic Resources directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Miami-Dade County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Miami-Dade County applies this before you apply.

From the Library

What else needs a permit in Miami-Dade County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependswood deck 18 inches or less above ground is exempt; decks higher than 18 inches require a building permitNo dedicated deck line
Fence PermitPermit requiredNot specifiedFence type determines permit type: wood and masonry fences require a Building Permit...
HVAC PermitPermit requiredNot specifiedAn exact change out air conditioning system is charged $24.17 per ton subject to a...
Patio PermitIt dependsopen concrete slabs and pavers outside the building do not require a building permit; roofed or screened patio enclosures require a permitNo dedicated patio line
Plumbing PermitPermit requiredNot specifiedSingle family plumbing for new construction, additions or alterations is $0.140 per...
Pool PermitPermit requiredNot specifiedInstallation of a residential swimming pool or spa carries a flat $640 building permit...
Roof Replacement PermitIt dependsunder F.S. 553.79(1)(g) (HB 803, ch. 2026-63, effective 2026-07-01), work valued at less than $7,500 on a single-family dwelling qualifies for exemption upon a written exemption request with documentation of the nature and value of the work; the exemption excludes electrical, plumbing, structural, mechanical, and gas work and any property in a flood hazard area; the statute does not name roofing, so a non-structural reroof under that value can qualify; confirm with Miami-Dade County Department of Regulatory and Economic Resources. Much of Miami-Dade County lies in flood hazard areas where this exemption does not apply.Re-roofing is charged per square foot of roof coverage including overhangs at $0.11 for...
Shed PermitPermit requiredonly one utility shed up to 400 sq ft permitted per residential lot under County Code Section 33-20(k)A prefabricated utility shed over 100 sq ft carries a flat $147 building permit fee
Solar PermitPermit requiredNot specifiedRoof mounted solar photovoltaic systems are $365.63 per system, or $250 per system using...

Electrical Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Miami-Dade County documents; the office above sets the local rules.

How this electrical permit page for Miami-Dade County was verified. 2 official sources: miamidade.gov, miamidade.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Miami-Dade County Department of Regulatory and Economic Resources. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Florida localities

Electrical permit rules nationwide

Look up an existing Miami-Dade County permit record

Permit required
Get quotes