Electrical Permit in Miami-Dade County, Florida

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

An electrical permit is required for new wiring, circuit additions, panel upgrades, and other electrical work in Miami-Dade County. Electrical permits are subsidiary permits issued under a master or primary permit. The county follows the Florida Building Code Electrical volume. Applications are submitted through the EPS Portal.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Miami-Dade County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For all new wiring, service upgrades, or electrical modifications

What electrical permit costs in Miami-Dade County

Residential wiring for new construction, additions, repairs and alterations is $0.11 per square foot of the master permit floor area subject to a $227.90 minimum electrical permit fee, per the county electrical fee sheet (rev 10/25).

Official fee schedule

How Miami-Dade County compares in Florida

No Florida jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Broward CountyPermit requiredElectrical permit is the greater of a $125 minimum base fee or 3.0% of job va...
Hillsborough CountyPermit requiredResidential Electrical (General) trade permit fee is $130 flat for inspection...
Lee CountyPermit requiredFee schedule effective 2026-04-15: $50 application fee and $35 technology fee...
Miami-Dade Countythis pagePermit requiredResidential wiring for new construction, additions, repairs and alterations i...
Orange CountyPermit requiredMinimum Electrical Permit fee is $38 flat, scaling with service amperage for...
Palm Beach CountyPermit requiredCharged by value of construction with a $75 minimum, per the PZB Building Div...
Pasco CountyIt dependsBase fee $45;

How to apply in Miami-Dade County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Miami-Dade County Department of Regulatory and Economic Resources sets the exact checklist for Miami-Dade County.

Where to apply in Miami-Dade County:

Miami-Dade County Department of Regulatory and Economic Resources

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Miami-Dade County permit portal or by phone at (786) 315-2100.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Miami-Dade County

In 2024, Miami-Dade County authorized permits for 10,608 new residential housing units (2,231 single-family, 8,377 in multi-family buildings), valued at $4.2B, down from12,781 the year before. That works out to about 3.7 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 2,838,461.

About Miami-Dade County

Miami-Dade County has about 1,085,414 housing units. The median home is valued at $425,400, against a median household income of $68,694. About 52% of homes are owner-occupied, and the typical home was built around 1980.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a electrical permit in Miami-Dade County?
An electrical permit is required for new wiring, circuit additions, panel upgrades, and other electrical work in Miami-Dade County. Electrical permits are subsidiary permits issued under a master or primary permit. The county follows the Florida Building Code Electrical volume. Applications are submitted through the EPS Portal. Always confirm with the Miami-Dade County Department of Regulatory and Economic Resources before starting.
How much does a electrical permit cost in Miami-Dade County?
Residential wiring for new construction, additions, repairs and alterations is $0.11 per square foot of the master permit floor area subject to a $227.90 minimum electrical permit fee, per the county electrical fee sheet (rev 10/25). See the official fee schedule for current amounts.
Where do you apply for a electrical permit in Miami-Dade County?
You can apply through the Miami-Dade County permit portal or contact the Miami-Dade County Department of Regulatory and Economic Resources directly. The links are listed on this page.

From the Library

What else needs a permit in Miami-Dade County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependswood deck 18 inches or less above ground is exempt; decks higher than 18 inches require a building permitNo dedicated deck line;
Fence PermitPermit requiredNot specifiedFence type determines permit type: wood and masonry fences require a Building Permit (C...
HVAC PermitPermit requiredNot specifiedAn exact change out air conditioning system is charged $24.17 per ton subject to a $227...
Patio PermitIt dependsopen concrete slabs and pavers outside the building do not require a building permit; roofed or screened patio enclosures require a permitNo dedicated patio line;
Plumbing PermitPermit requiredNot specifiedSingle family plumbing for new construction, additions or alterations is $0.140 per squ...
Pool PermitPermit requiredNot specifiedInstallation of a residential swimming pool or spa carries a flat $640 building permit...
Roof Replacement PermitIt dependsunder F.S. 553.79(1)(g) (HB 803, ch. 2026-63, effective 2026-07-01), work valued at less than $7,500 on a single-family dwelling qualifies for exemption upon a written exemption request with documentation of the nature and value of the work; the exemption excludes electrical, plumbing, structural, mechanical, and gas work and any property in a flood hazard area; the statute does not name roofing, so a non-structural reroof under that value can qualify; confirm with Miami-Dade County Department of Regulatory and Economic Resources. Much of Miami-Dade County lies in flood hazard areas where this exemption does not apply.Re-roofing is charged per square foot of roof coverage including overhangs at $0.11 for...
Shed PermitPermit requiredonly one utility shed up to 400 sq ft permitted per residential lot under County Code Section 33-20(k)A prefabricated utility shed over 100 sq ft carries a flat $147 building permit fee;
Solar PermitPermit requiredNot specifiedRoof mounted solar photovoltaic systems are $365.63 per system, or $250 per system usin...

Electrical Permit in other Florida localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with Miami-Dade County Department of Regulatory and Economic Resources. Rules change; confirm before you build. How we verify.