Florida / Marion County

Shed Permit in Marion County, Florida

It depends

Sometimes, depending on the project

Before installing a pre-manufactured or accessory shed of 100 square feet or larger in unincorporated Marion County

From an official source Verified Building Safety

By Mario Bailey, verified against official sources

Quick answer

Marion County's building permit fee schedule lists a specific fee for pre-manufactured sheds of 100 square feet and larger, plus a separate fee for residential aluminum accessory structures including pre-fab sheds. This applies to unincorporated Marion County; the cities of Ocala, Belleview, and Dunnellon have their own building departments. Homeowners should confirm the exact size cutoff with Building Safety before assuming a small shed is exempt.

Typical threshold: The county's shed permit fee category applies to pre-manufactured sheds of 100 square feet and larger.

Diagram of the 100 sq ft footprint area threshold for a shed permit in Marion County, Florida
Threshold illustrated: 100 sq ft. Whether Marion County requires a permit above or below this measurement is stated in the verdict on this page, verified 2026-08-08.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a pre-manufactured or accessory shed of 100 square feet or larger in unincorporated Marion County

What your shed permit must meet in Florida

Florida sheds are built under the Florida Building Code, Residential, 8th Edition (2023), which requires structures to be designed for the state's wind loads, but Florida Statutes carve out two specific size-based reductions in what a shed must resist or include.

  • As a structure, a shed is generally subject to the Florida Building Code's baseline wind-design requirement that applies to buildings and structures statewide (FBC Section 1609.1).
  • Storage sheds not designed for human habitation with a floor area of 720 square feet or less are exempt from the code's mandatory windborne-debris-impact (opening protection) standard (F.S. 553.73(10)).
  • Buildings of 400 square feet or less used in conjunction with a one- or two-family residence, which covers most sheds, are exempt from the code's door height and width requirements (F.S. 553.73(10)).

Based on Florida Statutes 553.73(10); Florida Building Code, 8th Edition (2023), Section 1609.1. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.

What a shed permit costs in Marion County

Line item
shed permitBy formulaPre-manufactured Sheds (100 sq. ft. and larger): $110.00; Residential Aluminum Structures (Includes Pre-Fab Sheds): $135.00, per Resolution 25-R-295 (effective Oct. 1, 2025).
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Marion County compares in Florida

Across the Florida jurisdictions we have verified, the same threshold runs from 68 to 150, so a project that is exempt here may still need a permit one county over.

JurisdictionPermit needed?Threshold
Alachua CountyIt dependsarea of a single storage shed, exemption available once per property
Brevard CountyIt dependsA permit is required for an accessory structure (shed) over 100 square feet.
Charlotte CountyIt dependsA building permit is not required for plastic or rubber manufactured type sheds 68 square feet or less in area, though they must comply with zoning setbacks and be moved and secured if there is the threat of a tropical storm.
Escambia CountyIt dependsA portable, skid-mounted utility shed under 120 square feet does not require a permit; any utility shed with a poured slab or a post installed into the earth requires a permit regardless of size.
Hernando CountyIt dependsSheds with impervious roof coverings of 120 square feet or less do not require a Zoning permit, provided other county regulations (setbacks, floodplain rules, one detached accessory building per parcel, etc.) are met
Hillsborough CountyIt dependssheds under 150 sq ft are exempt; 150 sq ft or larger require a building permit
Marion Countythis pageIt dependsThe county's shed permit fee category applies to pre-manufactured sheds of 100 square feet and larger

Closest shed permit thresholds outside Florida

Jurisdictions we cover whose limit sits nearest Marion County's 100 sq ft.

How to apply in Marion County

A residential shed permit application, once the shed is large enough to require one, is a set of construction documents that show what will be built and prove it meets the adopted residential code. In practice that means a written permit application, a scaled site plan locating the shed and its distances to the property lines, and construction documents covering the shed's foundation or anchoring system and its framing.

What most shed permit applications include:

  • A written permit application identifying the proposed work and describing the property by its address or legal description, filed with the building department before construction begins (IRC R105.3).
  • A scaled site plan showing the shed's size and location and its dimensioned distances to all property lines so required setbacks can be verified before the permit is issued (IRC R106.2).
  • Construction documents showing the shed's foundation: freestanding accessory structures at or under the code's small-structure size and eave-height limits (600 square feet and a 10 foot eave height in the model code) are exempt from continuous footings but must still be shown supported on undisturbed soil or engineered fill and anchored to resist wind-induced uplift and overturning (IRC R403.1).
  • Where the shed does sit on a continuous foundation with a wood sill plate, anchor bolt or approved strap details tying the sill plate to the foundation (IRC R403.1.6).
  • Roof framing details showing the rafter-to-wall or truss-to-wall connections, since even a shed exempt from continuous footings must be anchored to resist wind-induced uplift and overturning (IRC R403.1; R802.11).

General submittal guidance from IRC R105.3 (permit application), R106.2 (site plan), R403.1 (footings and anchorage for accessory structures), and R403.1.6 (sill anchorage), 2021 IRC. Source. Building Safety sets the exact checklist for Marion County.

Where to apply in Marion County:

Building Safety

Inspections and closing out your permit

A permitted shed is inspected in stages as it goes up: the foundation or the anchors that hold it down before they are covered, the framing before it is enclosed, and a final inspection once the shed is finished. Each stage checks the items that would be hidden or unsafe if skipped.

  1. Foundation or anchor inspection: called after any required footings, piers, or ground anchors are set and any forms or reinforcing steel are in place, but before concrete is placed, so the foundation or anchoring system can be verified before it is covered (IRC R109.1.1).
  2. Frame inspection: after the shed is framed, sheathed, and braced, the inspector checks the framing, bracing, fasteners, and the roof connections that resist wind uplift, before those elements are covered (IRC R109.1.4 frame inspection; R403.1 anchorage).
  3. Final inspection: made after the permitted work is complete and before the shed is used; work may not proceed past any inspection stage without the building official's approval (IRC R109.1.6 final inspection; R109.4 approval required).
  4. For a pre-fabricated or kit shed, the manufacturer's installation instructions must be on site at the time of inspection so the inspector can confirm the anchoring and assembly match the design (IRC R106.1.2).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Marion County permit portal or by phone at 352-438-2400.

Inspection sequence from IRC R109.1.1 (foundation inspection), R109.1.4 (frame inspection), R109.1.6 (final inspection), and R106.1.2 (manufacturer's instructions on site), 2021 IRC. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a shed permit in Marion County?
Marion County's building permit fee schedule lists a specific fee for pre-manufactured sheds of 100 square feet and larger, plus a separate fee for residential aluminum accessory structures including pre-fab sheds. This applies to unincorporated Marion County; the cities of Ocala, Belleview, and Dunnellon have their own building departments. Homeowners should confirm the exact size cutoff with Building Safety before assuming a small shed is exempt. The county's shed permit fee category applies to pre-manufactured sheds of 100 square feet and larger. Always confirm with the office before starting.
How much does a shed permit cost in Marion County?
Pre-manufactured Sheds (100 sq. ft. and larger): $110.00; Residential Aluminum Structures (Includes Pre-Fab Sheds): $135.00, per Resolution 25-R-295 (effective Oct. 1, 2025). See the official fee schedule for current amounts.
Where do you apply for a shed permit in Marion County?
You can apply through the Marion County permit portal or contact the Building Safety directly. The links are listed on this page.
Can a homeowner pull a shed permit themselves in Marion County?
Under Florida law (F.S. 489.103(7)(a)-(c)): Florida lets you pull your own permit as an owner-builder under section 489.103(7), Florida Statutes, which exempts property owners from the contractor licensing law when they act as their own contractor and provide direct, onsite supervision of all work not performed by licensed contractors. The exemption covers building or improving a one-family or two-family residence or a farm outbuilding for your own occupancy or use, and commercial buildings only up to a $75,000 cost, and the property may not be built or improved for sale or lease. If you sell or lease the property within 1 year after completing the work, the law presumes it was built for sale or lease, which violates the exemption. To qualify, you must personally appear and sign the building permit application and sign a state-prescribed disclosure statement acknowledging that you are the party legally and financially responsible for the construction, that you must provide direct, onsite supervision, and that unlicensed people you use must be your own employees, bringing federal tax withholding and workers' compensation obligations. You may not hire an unlicensed person to act as your contractor and may not delegate supervision to anyone who is not licensed for the work being done; if these requirements are violated, the local permitting agency shall withhold final approval, revoke the permit, or pursue unlicensed-activity remedies. A separate narrow branch of the exemption also lets an owner take over and complete a permit on a one-family or two-family residence when the original contractor substantially completed the project. Confirm how Marion County applies this before you apply.

From the Library

What else needs a permit in Marion County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsThe county's deck permit fee applies to decks over 1 step in heightDeck (Over 1 step in height): $110.00, per Resolution 25-R-295 (effective Oct.
Electrical PermitPermit requiredNot specifiedRes Electrical Scope: $100.00, per Resolution 25-R-295 (effective Oct.
Fence PermitPermit requiredNot specifiedFence/Wall/Entrance-way (Res or Com): $125.00, per the county's construction permit fee...
HVAC PermitIt dependsInstalling an A/C unit under three tons that is cord-and-plug connected to an existing electrical outlet and not connected to ductwork does not require a permitRes Mechanical Scope: $100.00, per Resolution 25-R-295 (effective Oct.
Plumbing PermitPermit requiredNot specifiedRes Plumbing Scope: $100.00, per Resolution 25-R-295 (effective Oct.
Pool PermitPermit requiredPools larger than or equal to 24 inches in depth, above ground or in ground, require a permitRes Pool/Spa (Pool In-ground/Whirlpool Non-Portable): $250.00
Roof Replacement PermitPermit requiredRoofing repair of 100 square feet or less does not require a permitRes Re-Roof (Roof-over Alum, Shingles, Metal or MH): $125.00 plus $20 per unit, per...
Solar PermitPermit requiredNot specifiedSolar-Photovoltaic Elec/Potable or Non-Potable (Res or Com): $140.00, per Resolution...

Shed Permit in other Florida localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Marion County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Building Safety. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Shed Permit requirements across Florida localities

Look up an existing Marion County permit record

It depends
Get quotes