Yes, a permit is required
Before installing a residential rooftop or ground-mounted solar energy system in unincorporated Fresno County
By Mario Bailey, verified against official sources
Quick answer
Fresno County states outright in Title 15 that a building permit is required to install a solar energy system, and its SolarAPP+ page warns that 'County of Fresno provides the building permit. SolarAPP+ confirmation information is not considered a building permit.' Section 15.18.030 establishes the expedited, streamlined permitting process for small residential rooftop systems required by Government Code Section 65850.5, defined as up to 10 kW AC or 30 kW thermal on a single or duplex family dwelling, and limits those projects to a single inspection unless the installation is out of compliance or a separate fire safety inspection is required. Licensed contractors can run the design through SolarAPP+ for automated review and then apply on the Citizens Portal; everything else goes through the 'Solar Installation without SolarAPP+' sub type. This applies to unincorporated Fresno County only, not to the City of Fresno, the City of Clovis or the county's other incorporated cities.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
When a permit is usually needed
Before installing a residential rooftop or ground-mounted solar energy system in unincorporated Fresno County
What a solar permit costs in Fresno County
How Fresno County compares in California
No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alameda County | Permit required | Building Inspection Department Service Fee Schedule (Schedule A, effective... |
| Contra Costa County | Permit required | Land Development Fee Schedule item 7, "Residential solar energy systems - roof... |
| Fresno Countythis page | Permit required | The Master Schedule of Fees has no solar or photovoltaic line item anywhere in... |
| Los Angeles | Permit required | Residential rooftop PV is an electrical permit with itemized per-component... |
| Los Angeles County | Permit required | Chapter 68, Section 6805 of the County of Los Angeles Building Code: 'The... |
| Orange County | Permit required | Solar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY... |
| Riverside County | Permit required | Roof Mount Solar Residential (BEL-RSLRR), described in the schedule as... |
How to apply in Fresno County
A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety sets the exact checklist for Fresno County.
Where to apply in Fresno County:
Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety
- 2220 Tulare Street, Suite A, Fresno, CA 93721 (Development Services and Capital Projects Division; the offices are in Annex A and Annex B of the Fresno County Plaza at Tulare and M streets)
- Phone: 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line)
- Email: PlanCheckBuildingCode2@fresnocountyca.gov
Inspections and closing out your permit
Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Fresno County permit portal or by phone at 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line).
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Fresno County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing a residential rooftop or ground-mounted solar energy system in unincorporated Fresno County.
- Budget the fee. The Master Schedule of Fees has no solar or photovoltaic line item anywhere in Section 2500. Title 15 Section 15.18.030.D.3 requires the county to publish the standard building permit application, the amount of any required fee and a standard small residential rooftop solar plan form and checklist. Contractors using SolarAPP+ are separately charged a processing fee by SolarAPP+ before applying to the county. Official fee schedule.
- Apply. A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Fresno County permit portal.
- Keep the office details handy. Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety. Phone: 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line). Address: 2220 Tulare Street, Suite A, Fresno, CA 93721 (Development Services and Capital Projects Division; the offices are in Annex A and Annex B of the Fresno County Plaza at Tulare and M streets).
- Plan for inspections. Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Fresno County?
- Fresno County states outright in Title 15 that a building permit is required to install a solar energy system, and its SolarAPP+ page warns that 'County of Fresno provides the building permit. SolarAPP+ confirmation information is not considered a building permit.' Section 15.18.030 establishes the expedited, streamlined permitting process for small residential rooftop systems required by Government Code Section 65850.5, defined as up to 10 kW AC or 30 kW thermal on a single or duplex family dwelling, and limits those projects to a single inspection unless the installation is out of compliance or a separate fire safety inspection is required. Licensed contractors can run the design through SolarAPP+ for automated review and then apply on the Citizens Portal; everything else goes through the 'Solar Installation without SolarAPP+' sub type. This applies to unincorporated Fresno County only, not to the City of Fresno, the City of Clovis or the county's other incorporated cities. Always confirm with the Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety before starting.
- How much does a solar permit cost in Fresno County?
- The Master Schedule of Fees has no solar or photovoltaic line item anywhere in Section 2500. Title 15 Section 15.18.030.D.3 requires the county to publish the standard building permit application, the amount of any required fee and a standard small residential rooftop solar plan form and checklist. Contractors using SolarAPP+ are separately charged a processing fee by SolarAPP+ before applying to the county. See the official fee schedule for current amounts.
- Where do you apply for a solar permit in Fresno County?
- You can apply through the Fresno County permit portal or contact the Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Fresno County?
- Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner-builder from contractor licensing when the owner personally performs the work, or uses only wage employees, on their own property and does not intend the improvements for sale. A homeowner may also directly hire licensed trade contractors for up to four single-family residences a year, or improve their own principal residence without a general contractor's license, as long as they have actually lived there for the 12 months before the work is finished. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a building permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a $500 civil penalty. Confirm how Fresno County applies this before you apply.
From the Library
What else needs a permit in Fresno County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | Permit required | Not specified | No flat deck permit fee is published. |
| Electrical Permit | Permit required | Not specified | Section 2511 Electrical Code Fees, FY 2026-27: Issuing permits $42.77 each |
| Fence Permit | It depends | Fences not over 7 feet high are on the county's published list of work exempt from a building permit | The Master Schedule of Fees publishes no flat fence permit fee. |
| HVAC Permit | Permit required | Not specified | Section 2510 Mechanical Code Fees, FY 2026-27: Issuing each permit $42.77 |
| Patio Permit | Permit required | Not specified | No flat patio permit fee is published. |
| Plumbing Permit | Permit required | Not specified | Section 2512 Plumbing Code Fees, FY 2026-27: Alteration, repair or addition of a drain... |
| Pool Permit | It depends | Prefabricated pools accessory to a Group R-3 occupancy are exempt from a building permit only when they are less than 24 inches deep, hold not more than 5,000 gallons, and are installed entirely above ground | Special Services Fees item 21, 'Installation of private swimming pool or spa includes... |
| Roof Replacement Permit | Permit required | Not specified | Special Services Fees item 16, 'Re-roofing of existing buildings including pre-roof... |
| Shed Permit | It depends | One-story detached accessory structures used as tool and storage sheds, playhouses and similar uses are exempt from a building permit when the floor area is not greater than 120 square feet | For a shed between 120 and 240 square feet the county charges for the Item No. |
Solar Permit in other California localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Fresno County documents; the office above sets the local rules.
Verified by a person against the sources above on , not confirmed with Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Solar Permit requirements across California localities
Permit office
Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety
559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line)Permit portal