California / Sacramento County
Solar Permit in Sacramento County, California
Permit required
Yes, a permit is required
Before installing a rooftop photovoltaic system, a PV system with battery storage, or solar panels serving a swimming pool.
Quick answer
Photovoltaic systems require a permit in unincorporated Sacramento County, and the county has adopted SolarAPP+ to satisfy California's expedited residential solar permitting mandate. Licensed contractors run the design through SolarAPP+ for automated review, then apply in the Accela portal under "Residential Solar Permit with SolarApp" and the permit auto-issues on payment. SolarAPP+ is contractor-only and does not cover ballasted systems, building-integrated PV, or anything other than a permitted main dwelling rooftop. Solar for a swimming pool is separately listed as permit-required.
- Issued by
- Sacramento County Community Development, Building Permits and Inspection Division
- Phone
- 916-875-5296
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your California Contractors State License Board (CSLB) license active, and under which business name? Verify it on www.cslb.ca.gov.
California's owner-builder rule (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Sacramento County
- Fee schedule in force
- Official scheduleRead .
The county publishes no dollar amount for a residential solar permit, but the SolarAPP+ page states: "A processing fee will be charged by SolarApp+ NREL."
That NREL charge is separate from and additional to the county permit fee, which is set by Sacramento County Code Chapter 16.90 on ecode360 (we quote no figures from it) and quoted in the Accela portal, plus the Technology (IT) Cost Recovery Fee under County Code Section 16.140.010.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Sacramento County compares in California
No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alameda County | Permit required | See schedule |
| Contra Costa County | Permit required | See schedule |
| Fresno County | Permit required | See schedule |
| Los Angeles | Permit required | See schedule |
| Los Angeles County | Permit required | See schedule |
| Orange County | Permit required | Solar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY 2024-25, $448 for FY 2025-26, $455 for FY 2026-27 |
| Sacramento Countythis page | Permit required | See schedule |
How to apply in Sacramento County
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Sacramento County Community Development, Building Permits and Inspection Division
- Building Assistance Center, 9800 Goethe Road, Sacramento, CA 95827
- Phone: 916-875-5296
- Email: rudolphr@saccounty.gov
Your Solar Permit checklist for Sacramento County
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: development.saccounty.gov: building permits inspection.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Sacramento County permit portal.
- Keep the office details handy. Sacramento County Community Development, Building Permits and Inspection Division. Phone: 916-875-5296. Email: rudolphr@saccounty.gov. Address: Building Assistance Center, 9800 Goethe Road, Sacramento, CA 95827.
Compiled from the official sources on this page. Last checked .
Permitting activity in Sacramento County
In 2025, Sacramento County authorized permits for 6,561 new residential housing units (4,629 single-family, 1,932 in multi-family buildings), valued at $1.8B, down from 6,747 the year before. That works out to about 4.1 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 1,618,460.
What else needs a permit in Sacramento County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | deck area, where the deck is also no more than 30 inches above grade at any point, is not attached to a dwelling, and does not serve a required exit door | See schedule |
| Electrical Permit | Permit required | Any size | See schedule |
| Fence Permit | It depends | fence height, measured from the grade on the right-of-way side when the fence sits within 5 feet of the public right-of-way and otherwise from the highest grade on either side | See schedule |
| HVAC Permit | Permit required | Any size | See schedule |
| Patio Permit | It depends | floor area of a detached, not fully enclosed patio cover, pergola, arbor or trellis that is also no taller than 12 feet and stands 5 feet or more from the property line | See schedule |
| Plumbing Permit | Permit required | Any size | See schedule |
| Pool Permit | It depends | depth of water the structure holds; the permit exemption is limited to prefabricated pools | See schedule |
| Roof Replacement Permit | Permit required | Any size | See schedule |
| Shed Permit | It depends | floor area of a one-story detached structure designed for storage with no electrical or plumbing installed | See schedule |
Frequently asked questions
- Do you need a solar permit in Sacramento County?
- Yes, before installing a rooftop photovoltaic system, a PV system with battery storage, or solar panels serving a swimming pool. If you are unsure how that applies to your project, call the Sacramento County Community Development, Building Permits and Inspection Division at 916-875-5296 before you start.
- How much does a solar permit cost in Sacramento County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the Sacramento County Community Development, Building Permits and Inspection Division at 916-875-5296.
- How long does a solar permit take in Sacramento County?
- Auto-issued online once permit payment has been made, for contractor submittals cleared through SolarAPP+. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Sacramento County?
- You can apply through the Sacramento County permit portal or contact the Sacramento County Community Development, Building Permits and Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Sacramento County?
- Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how Sacramento County applies this before you apply.
From the Library
Solar Permit in other California localities
Everything above, sourced
How this solar permit page for Sacramento County was verified. 2 official sources: development.saccounty.gov, development.saccounty.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Sacramento County Community Development, Building Permits and Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page