California / Sacramento County
Solar Permit in Sacramento County, California
Permit required
Yes, a permit is required
Before installing a rooftop photovoltaic system, a PV system with battery storage, or solar panels serving a swimming pool.
Issued bySacramento County Community Development, Building Permits and Inspection Division
By Mario Bailey, verified against official sources
Quick answer
Photovoltaic systems require a permit in unincorporated Sacramento County, and the county has adopted SolarAPP+ to satisfy California's expedited residential solar permitting mandate. Licensed contractors run the design through SolarAPP+ for automated review, then apply in the Accela portal under "Residential Solar Permit with SolarApp" and the permit auto-issues on payment. SolarAPP+ is contractor-only and does not cover ballasted systems, building-integrated PV, or anything other than a permitted main dwelling rooftop. Solar for a swimming pool is separately listed as permit-required.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your California Contractors State License Board (CSLB) license active, and under which business name? Verify it on www.cslb.ca.gov.
California's owner-builder rule (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5) sets what you may do on your own home without hiring anyone. Read the statute.
When a permit is usually needed
Before installing a rooftop photovoltaic system, a PV system with battery storage, or solar panels serving a swimming pool.
What a solar permit costs in Sacramento County
How Sacramento County compares in California
No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alameda County | Permit required | ...less than 35 Kva per system (when no plan review is required) $280.00 for... |
| Contra Costa County | Permit required | ...photovoltaic systems 15 kW or less: Building Permit/inspection $86.00 per... |
| Fresno County | Permit required | See schedule |
| Los Angeles | Permit required | ...per-component fees per the LADBS Electrical Permit Fee Schedule: $6 per... |
| Los Angeles County | Permit required | ...for small residential rooftop photovoltaic systems shall not exceed $500... |
| Orange County | Permit required | Solar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY... |
| Sacramento Countythis page | Permit required | See schedule |
How to apply in Sacramento County
In Sacramento County, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- For Sacramento County, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- For Sacramento County, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- For Sacramento County, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Sacramento County Community Development, Building Permits and Inspection Division sets the exact checklist for Sacramento County.
Where to apply in Sacramento County:
Sacramento County Community Development, Building Permits and Inspection Division
- Building Assistance Center, 9800 Goethe Road, Sacramento, CA 95827
- Phone: 916-875-5296
- Email: rudolphr@saccounty.gov
Solar Permit in Sacramento County compared with nearby California localities
| Locality | Permit needed? | Threshold | What each California schedule says | Verified |
|---|---|---|---|---|
| Sacramento County | Permit required | Any size | See schedule | |
| Alameda County | Permit required | Any size | ...energy system less than 35 Kva per system (when no plan review is required) $280.00... | |
| Contra Costa County | Permit required | Any size | ...mount," photovoltaic systems 15 kW or less: Building Permit/inspection $86.00 per... | |
| Fresno County | Permit required | Any size | See schedule | |
| Los Angeles | Permit required | Any size | ...with itemized per-component fees per the LADBS Electrical Permit Fee Schedule: $6... |
Inspections and closing out your permit
In Sacramento County, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- In Sacramento County: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- In Sacramento County: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- In Sacramento County: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- In Sacramento County: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- In Sacramento County: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- In Sacramento County: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Sacramento County permit portal or by phone at 916-875-5296.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for Sacramento County
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing a rooftop photovoltaic system, a PV system with battery storage, or solar panels serving a swimming pool.
- Budget the fee. The county publishes no dollar amount for a residential solar permit, but the SolarAPP+ page states: "A processing fee will be charged by SolarApp+ NREL." That NREL charge is separate from and additional to the county permit fee, which is set by Sacramento County Code Chapter 16.90 on ecode360 (HTTP 403 to automated requests, so no figures were transcribed) and quoted in the Accela portal, plus the Technology (IT) Cost Recovery Fee under County Code Section 16.140.010. Official fee schedule.
- Apply. In Sacramento County, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the Sacramento County permit portal.
- Keep the office details handy. Sacramento County Community Development, Building Permits and Inspection Division. Phone: 916-875-5296. Address: Building Assistance Center, 9800 Goethe Road, Sacramento, CA 95827.
- Plan for inspections. In Sacramento County, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in Sacramento County?
- Photovoltaic systems require a permit in unincorporated Sacramento County, and the county has adopted SolarAPP+ to satisfy California's expedited residential solar permitting mandate. Licensed contractors run the design through SolarAPP+ for automated review, then apply in the Accela portal under "Residential Solar Permit with SolarApp" and the permit auto-issues on payment. SolarAPP+ is contractor-only and does not cover ballasted systems, building-integrated PV, or anything other than a permitted main dwelling rooftop. Solar for a swimming pool is separately listed as permit-required. Always confirm with the Sacramento County Community Development, Building Permits and Inspection Division before starting.
- How much does a solar permit cost in Sacramento County?
- The county publishes no dollar amount for a residential solar permit, but the SolarAPP+ page states: "A processing fee will be charged by SolarApp+ NREL." That NREL charge is separate from and additional to the county permit fee, which is set by Sacramento County Code Chapter 16.90 on ecode360 (HTTP 403 to automated requests, so no figures were transcribed) and quoted in the Accela portal, plus the Technology (IT) Cost Recovery Fee under County Code Section 16.140.010. See the official fee schedule for current amounts.
- How long does a solar permit take in Sacramento County?
- Auto-issued online once permit payment has been made, for contractor submittals cleared through SolarAPP+. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Sacramento County?
- You can apply through the Sacramento County permit portal or contact the Sacramento County Community Development, Building Permits and Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Sacramento County?
- Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how Sacramento County applies this before you apply.
From the Library
What else needs a permit in Sacramento County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | deck area, where the deck is also no more than 30 inches above grade at any point, is not attached to a dwelling, and does not serve a required exit door | See schedule |
| Electrical Permit | Permit required | Any size | See schedule |
| Fence Permit | It depends | fence height, measured from the grade on the right-of-way side when the fence sits within 5 feet of the public right-of-way and otherwise from the highest grade on either side | See schedule |
| HVAC Permit | Permit required | Any size | See schedule |
| Patio Permit | It depends | floor area of a detached, not fully enclosed patio cover, pergola, arbor or trellis that is also no taller than 12 feet and stands 5 feet or more from the property line | See schedule |
| Plumbing Permit | Permit required | Any size | See schedule |
| Pool Permit | It depends | depth of water the structure holds; the permit exemption is limited to prefabricated pools | See schedule |
| Roof Replacement Permit | Permit required | Any size | See schedule |
| Shed Permit | It depends | floor area of a one-story detached structure designed for storage with no electrical or plumbing installed | See schedule |
Solar Permit in other California localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Sacramento County documents; the office above sets the local rules.
How this solar permit page for Sacramento County was verified. 2 official sources: development.saccounty.gov, development.saccounty.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Sacramento County Community Development, Building Permits and Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare Solar Permit requirements across California localities