California / Los Angeles County

Solar Permit in Los Angeles County, California

Permit required

Yes, a permit is required

Before installing a rooftop photovoltaic, solar water heating, or solar pool heating system. Systems meeting the Chapter 68 criteria go through the expedited path, and a system meeting the online eligibility list can be self-issued as an Express Solar Roof Mount Residential permit through EPIC-LA. Anything failing an eligibility item goes to plan check as a Solar Roof Mount Residential permit.

Confirmed on official page Verified Los Angeles County Public Works, Building and Safety Division

By Mario Bailey, verified against official sources

Quick answer

A permit is always required for solar in unincorporated Los Angeles County; there is no size below which one is waived. What size changes is the processing path. Chapter 68 gives an expedited process for small residential rooftop solar on one- or two-family dwellings, defined as photovoltaic systems no larger than 10 kilowatts alternating current or solar thermal systems for service water heating and pool heating no larger than 30 kilowatts thermal. A combined solar energy permit may be issued for photovoltaic systems covering all building and electrical work, with a separate plumbing permit if one is needed. Submittals use the county's standard electrical plan, a roof plan showing fire access pathways and labeling, the expedited structural criteria, and a signed Form A, B, or C affidavit confirming the array will not go on an unpermitted structure. A single combination inspection covers the structural, electrical, and plumbing components.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?

When a permit is usually needed

Before installing a rooftop photovoltaic, solar water heating, or solar pool heating system. Systems meeting the Chapter 68 criteria go through the expedited path, and a system meeting the online eligibility list can be self-issued as an Express Solar Roof Mount Residential permit through EPIC-LA. Anything failing an eligibility item goes to plan check as a Solar Roof Mount Residential permit.

What a solar permit costs in Los Angeles County

Line item
solar permitBy formulaChapter 68, Section 6805 of the County of Los Angeles Building Code: 'The combined permit fee for small residential rooftop photovoltaic systems shall not exceed $500 unless modified by or in accordance with Government Code Section 66015 or other applicable law.' The same section charges the underlying fees per Section 107 of the Building Code, Section 82-8 of the Electrical Code, and Sections 103.10 and 103.11 of the Plumbing Code. The county's Plumbing Code Fee Schedule (Title 28, Ord. No. 2013-0050) effective July 1, 2026 separately lists $81.78 for each solar potable water-heating system including water heater and vent, and the $41.35 permit issuance fee applies.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Los Angeles County compares in California

No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alameda CountyPermit requiredBuilding Inspection Department Service Fee Schedule (Schedule A, effective...
Contra Costa CountyPermit requiredLand Development Fee Schedule item 7, "Residential solar energy systems - roof...
Fresno CountyPermit requiredThe Master Schedule of Fees has no solar or photovoltaic line item anywhere in...
Los AngelesPermit requiredResidential rooftop PV is an electrical permit with itemized per-component...
Los Angeles Countythis pagePermit requiredChapter 68, Section 6805 of the County of Los Angeles Building Code: 'The...
Orange CountyPermit requiredSolar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY...
Riverside CountyPermit requiredRoof Mount Solar Residential (BEL-RSLRR), described in the schedule as...

How to apply in Los Angeles County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Los Angeles County Public Works, Building and Safety Division sets the exact checklist for Los Angeles County.

Where to apply in Los Angeles County:

Los Angeles County Public Works, Building and Safety Division

  • Los Angeles County Public Works, Building and Safety Division, 3rd Floor, 900 S. Fremont Avenue, Alhambra, CA 91803
  • Phone: 626-458-3173

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Los Angeles County permit portal or by phone at 626-458-3173.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Los Angeles County?
A permit is always required for solar in unincorporated Los Angeles County; there is no size below which one is waived. What size changes is the processing path. Chapter 68 gives an expedited process for small residential rooftop solar on one- or two-family dwellings, defined as photovoltaic systems no larger than 10 kilowatts alternating current or solar thermal systems for service water heating and pool heating no larger than 30 kilowatts thermal. A combined solar energy permit may be issued for photovoltaic systems covering all building and electrical work, with a separate plumbing permit if one is needed. Submittals use the county's standard electrical plan, a roof plan showing fire access pathways and labeling, the expedited structural criteria, and a signed Form A, B, or C affidavit confirming the array will not go on an unpermitted structure. A single combination inspection covers the structural, electrical, and plumbing components. Always confirm with the Los Angeles County Public Works, Building and Safety Division before starting.
How much does a solar permit cost in Los Angeles County?
Chapter 68, Section 6805 of the County of Los Angeles Building Code: 'The combined permit fee for small residential rooftop photovoltaic systems shall not exceed $500 unless modified by or in accordance with Government Code Section 66015 or other applicable law.' The same section charges the underlying fees per Section 107 of the Building Code, Section 82-8 of the Electrical Code, and Sections 103.10 and 103.11 of the Plumbing Code. The county's Plumbing Code Fee Schedule (Title 28, Ord. No. 2013-0050) effective July 1, 2026 separately lists $81.78 for each solar potable water-heating system including water heater and vent, and the $41.35 permit issuance fee applies. See the official fee schedule for current amounts.
How long does a solar permit take in Los Angeles County?
Plan check review completed within one to three business days on receipt of a complete small residential rooftop solar energy system application. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a solar permit in Los Angeles County?
You can apply through the Los Angeles County permit portal or contact the Los Angeles County Public Works, Building and Safety Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Los Angeles County?
Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner-builder from contractor licensing when the owner personally performs the work, or uses only wage employees, on their own property and does not intend the improvements for sale. A homeowner may also directly hire licensed trade contractors for up to four single-family residences a year, or improve their own principal residence without a general contractor's license, as long as they have actually lived there for the 12 months before the work is finished. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a building permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a $500 civil penalty. Confirm how Los Angeles County applies this before you apply.

From the Library

What else needs a permit in Los Angeles County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsheight of the deck surface above grade; the exemption also requires the deck not to be over any basement or story below and not to be part of an accessible routeNo deck line item is published.
Electrical PermitPermit requiredNot specifiedElectrical Code Fee Schedule (Title 27 of the County of Los Angeles Code, Ord No.
Fence PermitIt dependsheight of a fence or freestanding block wall measured from the lowest adjacent grade; a masonry or concrete fence must also be set back from a public way at least a distance equal to its height to stay exemptNo fence line item is published.
HVAC PermitPermit requiredNot specifiedMechanical Code Fee Schedule (Title 29 of the County of Los Angeles Code, Ord No.
Patio PermitIt dependsNot specifiedNo patio line item is published.
Plumbing PermitPermit requiredNot specifiedPlumbing Code Fee Schedule (Title 28 of the Los Angeles Code, Ord.
Pool PermitIt dependsdepth of a prefabricated pool or other body of water accessory to a one- or two-family (Group R-3) home; the same exemption also reaches pools that do not exceed 5,000 gallons and are installed entirely above adjacent gradeThere is no single pool price.
Roof Replacement PermitPermit requiredNot specifiedNo reroofing line item is published.
Shed PermitIt dependsgross floor area of a one-story detached accessory building; the exemption also requires the height not to exceed 12 feet and the maximum roof projection not to exceed 24 inchesNo shed line item is published.

Solar Permit in other California localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Los Angeles County documents; the office above sets the local rules.

Verified by a person against the sources above on , not confirmed with Los Angeles County Public Works, Building and Safety Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page