California / Contra Costa County
Solar Permit in Contra Costa County, California
Permit required
Yes, a permit is required
Before installing a rooftop or ground-mounted photovoltaic system, a solar thermal system, an energy storage system, or a backup generator. Ground-mounted systems also need planning approval.
Quick answer
Contra Costa County requires a building permit for solar and lists solar, energy storage systems, and backup generators among the projects that need one. The county offers an optional expedited path, SolarAPP+, for qualifying residential rooftop retrofit systems: the contractor runs the design through the automated NREL SolarAPP+ code check, then applies on the ePermits Center choosing the "SolarAPP+ Approved Permit" type, and the county's own page states "The permit will be auto-issued and emailed to you in a few minutes." SolarAPP+ eligibility is limited to parcels in unincorporated Contra Costa County or the cities of Clayton, Hercules, Lafayette, and Orinda and the Town of Moraga, main dwelling rooftop permitted residential structures only, with no ballasted systems, no mobile home parks, no FEMA Special Flood Hazard Area parcels, no Buchanan Field or Byron Airport safety zone parcels, and no registered historic properties. Projects outside those limits go through standard plan review.
- Issued by
- Contra Costa County Department of Conservation and Development, Building Inspection Division
- Phone
- 925-655-2700
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your California Contractors State License Board (CSLB) license active, and under which business name? Verify it on www.cslb.ca.gov.
California's owner-builder rule (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5) sets what you may do on your own home without hiring anyone. Read the statute.
What a solar permit costs in Contra Costa County
- Fee schedule in force
- Official scheduleRead . We tried to re-read it on and could not confirm the figure above, so treat it as of the earlier date and check the schedule.
- Published in
- Land Development Fee Schedule item 7, "Residential solar energy systems - roof mount and ground mount," photovoltaic systems 15 kW or less:
- Building Permit/inspection $86.00 per permit, Plan Check $86.00 per permit, and Electrical Review $100.00 per permit;
- above 15 kW the same combined charge adds $15.00 per kW above 15 kW. Thermal systems 10 kWth or less are $86.00 each for Building Permit/inspection, Plan Check, and Plumbing Review, plus $15.00 per kWth above 10 kWth.
- SolarAPP+ separately charges the installer $35.00 for a solar system and $25.00 for an energy storage add-on, on top of county permit fees.
- Fee schedule adopted May 24, 2022, effective August 10, 2022.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How Contra Costa County compares in California
No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alameda County | Permit required | See schedule |
| Contra Costa Countythis page | Permit required | See schedule |
| Fresno County | Permit required | See schedule |
| Los Angeles | Permit required | See schedule |
| Los Angeles County | Permit required | See schedule |
| Orange County | Permit required | Solar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY 2024-25, $448 for FY 2025-26, $455 for FY 2026-27 |
| Riverside County | Permit required | See schedule |
How to apply in Contra Costa County
General guide, not specific to this office
What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
Contra Costa County Department of Conservation and Development, Building Inspection Division
- Application and Permit Center, 30 Muir Road, Martinez, CA 94553
- Phone: 925-655-2700
- Email: permits@dcd.cccounty.us
Your Solar Permit checklist for Contra Costa County
- Confirm the requirement. Yes, a permit is required. Read the rule where we read it: contracosta.ca.gov: Permit information.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the Contra Costa County permit portal.
- Keep the office details handy. Contra Costa County Department of Conservation and Development, Building Inspection Division. Phone: 925-655-2700. Email: permits@dcd.cccounty.us. Address: Application and Permit Center, 30 Muir Road, Martinez, CA 94553.
Compiled from the official sources on this page. Last checked .
Permitting activity in Contra Costa County
In 2025, Contra Costa County authorized permits for 1,163 new residential housing units (970 single-family, 193 in multi-family buildings), valued at $421M, down from 2,155 the year before. That works out to about 1 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 1,170,070.
What else needs a permit in Contra Costa County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | area of a deck that is also no more than 30 inches above grade at any point, is not attached to a dwelling, and does not serve a code-required exit door | No deck-specific flat fee is published |
| Electrical Permit | Permit required | Any size | See schedule |
| Fence Permit | It depends | height of a fence, with concrete and masonry walls treated as walls rather than fences | See schedule |
| HVAC Permit | Permit required | Any size | See schedule |
| Patio Permit | It depends | roof area of a trellis, arbor, or pergola accessory to a residence, treated by the county as a one-story detached accessory structure | See schedule |
| Plumbing Permit | Permit required | Any size | See schedule |
| Pool Permit | It depends | depth of a prefabricated pool accessory to a one or two family dwelling that is installed entirely above ground and holds no more than 5,000 gallons | The Building Valuation Data Supplement sets a "Swimming pool, lump sum of: $39,514.98" valuation; the schedule has the rest |
| Roof Replacement Permit | Permit required | Any size | Land Development Fee Schedule item 14, "Re-Roofs - Residential": Building Permit / Inspection $150.00 per permit and Processing $38.00 per permit |
| Shed Permit | It depends | floor area of a one-story detached accessory structure | No shed-specific flat fee is published |
Frequently asked questions
- Do you need a solar permit in Contra Costa County?
- Yes, before installing a rooftop or ground-mounted photovoltaic system, a solar thermal system, an energy storage system, or a backup generator. Ground-mounted systems also need planning approval. If you are unsure how that applies to your project, call the permit office at 925-655-2700 before you start.
- How much does a solar permit cost in Contra Costa County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 15 Aug 2026. For the figure on your own project, call the permit office at 925-655-2700.
- How long does a solar permit take in Contra Costa County?
- SolarAPP+ approved permits are auto-issued and emailed within a few minutes of application. Standard building permit applications get an initial completeness review in 4 to 5 business days before plan review begins. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in Contra Costa County?
- You can apply through the Contra Costa County permit portal or contact the Contra Costa County Department of Conservation and Development, Building Inspection Division directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in Contra Costa County?
- Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how Contra Costa County applies this before you apply.
From the Library
Solar Permit in other California localities
Everything above, sourced
How this solar permit page for Contra Costa County was verified. 1 official source: contracosta.ca.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Contra Costa County Department of Conservation and Development, Building Inspection Division. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page