California / Fresno County

Electrical Permit in Fresno County, California

Permit required

Yes, a permit is required

Before installing, altering or reconnecting residential electrical wiring or service in unincorporated Fresno County

Quick answer

Electrical work in unincorporated Fresno County is permitted by the county Building Official, not by a state agency or the utility: Title 15 Chapter 15.16 adopts the California Electrical Code and adds county amendments, including a rule that a residential service disconnected for a year or more cannot be reconnected without an inspection under permit. Section 2511 of the Master Schedule of Fees prices electrical permits by outlet, circuit and motor size for alterations, and per dwelling unit by floor area for new construction or a complete remodel. The county also limits permits for new electrical service to installations serving a connected load or approved use allowed by the property's zoning. This applies to unincorporated Fresno County only, not to the City of Fresno, the City of Clovis or the county's other incorporated cities.

Issued by
Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety
Confirmed on official page Verified

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

What an electrical permit costs in Fresno County

Fee schedule in force
Official scheduleRead .
Published in
Section 2511 Electrical Code Fees, FY 2026-27:
  • Issuing permits $42.77 each;
  • Wiring outlets $1.80 each;
  • Each circuit (remodel work only) $13.51 each;
  • minimum electrical permit fee $65.84.
  • New construction or complete remodel of a dwelling is charged per dwelling unit by size, for example $124.37 for 0 to 750 sq. ft., $224.54 for 1,001 to 1,500 sq. ft. and $419.81 for 2,501 to 3,000 sq. ft., which includes all wiring, outlets, fixtures, one 200 amp maximum main service and one 200 amp maximum sub panel.
  • Agricultural pump or wind motor work has a $131.12 minimum.

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Fresno County compares in California

No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alameda CountyPermit requiredSee schedule
Contra Costa CountyPermit requiredSee schedule
Fresno Countythis pagePermit requiredSee schedule
Los AngelesPermit requiredSee schedule
Los Angeles CountyPermit requiredSee schedule
Orange CountyPermit requiredElectrical Permit Application Flat Fee, 1 to 75 fixtures: $340 for FY 2024-25, $356 for FY 2025-26, $362 for FY 2026-27
Riverside CountyPermit requiredResidential Electrical (BEL-RELE): $448.20 fixed fee

How to apply in Fresno County

General guide, not specific to this office

What an electrical permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an electrical permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety

  • 2220 Tulare Street, Suite A, Fresno, CA 93721 (Development Services and Capital Projects Division; the offices are in Annex A and Annex B of the Fresno County Plaza at Tulare and M streets)
  • Phone: 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line)
  • Email: PlanCheckBuildingCode2@fresnocountyca.gov

Permitting activity in Fresno County

In 2025, Fresno County authorized permits for 2,271 new residential housing units (2,002 single-family, 269 in multi-family buildings), valued at $734M, down from 2,439 the year before. That works out to about 2.2 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 1,035,456.

What else needs a permit in Fresno County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredAny sizeNo flat deck permit fee is published
Fence PermitIt dependsFences not over 7 feet high are on the county's published list of work exempt from a building permitThe Master Schedule of Fees publishes no flat fence permit fee
HVAC PermitPermit requiredAny sizeSection 2510 Mechanical Code Fees, FY 2026-27: Issuing each permit $42.77
Patio PermitPermit requiredAny sizeNo flat patio permit fee is published
Plumbing PermitPermit requiredAny sizeSee schedule
Pool PermitIt dependsPrefabricated pools accessory to a Group R-3 occupancy are exempt from a building permit only when they are less than 24 inches deep, hold not more than 5,000 gallons, and are installed entirely above groundSee schedule
Roof Replacement PermitPermit requiredAny sizeSingle family residential: $201.47 per structure for FY 2026-27
Shed PermitIt dependsOne-story detached accessory structures used as tool and storage sheds, playhouses and similar uses are exempt from a building permit when the floor area is not greater than 120 square feetIts Building and Safety FAQ says 'The cost for the permit will be $153.44'; the schedule has the rest
Solar PermitPermit requiredAny sizeSee schedule

Frequently asked questions

Do you need an electrical permit in Fresno County?
Yes, before installing, altering or reconnecting residential electrical wiring or service in unincorporated Fresno County. If you are unsure how that applies to your project, call the permit office at 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line) before you start.
How much does an electrical permit cost in Fresno County?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the permit office at 559-600-4570 (plan check and permit information); 559-600-4560 (building inspection); 559-600-4131 (24 hour inspection request line).
Where do you apply for an electrical permit in Fresno County?
You can apply through the Fresno County permit portal or contact the Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Fresno County?
Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how Fresno County applies this before you apply.

From the Library

Electrical Permit in other California localities

Everything above, sourced

How this electrical permit page for Fresno County was verified. 2 official sources: fresnocountyca.gov, fresnocountyca.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Department of Public Works and Planning, Development Services and Capital Projects Division, Building and Safety. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project