California / Sacramento

Electrical Permit in Sacramento, California

By Mario Bailey Last checked 2026-06-18 · 2 official sources

Verified against official sources Based on building code

Permit required

Quick answer

An electrical permit is required in Sacramento for new circuits, panel upgrades, service work, and EV charger installation. Applications are submitted online through the Accela permit portal. A licensed electrician is typically required for permitted electrical work. Contact the Building Division for applicability of homeowner exemptions.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Sacramento, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For all new wiring circuits panel upgrades and electrical service work

What electrical permit costs in Sacramento

Flat $105 permit fee for one-trade minor electrical work such as a panel change-out, rewire or new circuit, plus a 10% technology surcharge, per CDD-0245 (rev 07-12-2026).

Official fee schedule

How Sacramento compares in California

No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Los AngelesPermit requiredItemized per installed item per the LADBS Electrical Permit Fee Schedule (rev...
Sacramentothis pagePermit requiredFlat $105 permit fee for one-trade minor electrical work such as a panel chan...
San DiegoPermit requiredBilled per circuit or panel under IB-103 Table 2 effective May 2026: circuits...
San JosePermit requiredGreater of $315 per hour of required inspection time or an itemized fixture-b...

How to apply in Sacramento

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. City of Sacramento Community Development Department Building Division sets the exact checklist for Sacramento.

Where to apply in Sacramento:

City of Sacramento Community Development Department Building Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Sacramento permit portal or by phone at 916-808-5318.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Sacramento

In 2024, Sacramento authorized permits for 2,043 new residential housing units (708 single-family, 1,335 in multi-family buildings), valued at $487M, down from2,517 the year before. That works out to about 4 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 512,838.

About Sacramento

Sacramento has about 210,621 housing units. The median home is valued at $484,600, against a median household income of $83,753. About 51% of homes are owner-occupied, and the typical home was built around 1976.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need a electrical permit in Sacramento?
An electrical permit is required in Sacramento for new circuits, panel upgrades, service work, and EV charger installation. Applications are submitted online through the Accela permit portal. A licensed electrician is typically required for permitted electrical work. Contact the Building Division for applicability of homeowner exemptions. Always confirm with the City of Sacramento Community Development Department Building Division before starting.
How much does a electrical permit cost in Sacramento?
Flat $105 permit fee for one-trade minor electrical work such as a panel change-out, rewire or new circuit, plus a 10% technology surcharge, per CDD-0245 (rev 07-12-2026). See the official fee schedule for current amounts.
Where do you apply for a electrical permit in Sacramento?
You can apply through the Sacramento permit portal or contact the City of Sacramento Community Development Department Building Division directly. The links are listed on this page.

From the Library

What else needs a permit in Sacramento

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsuncovered deck 30 inches or more above grade requires a building permitValuation-based building permit per CDD-0245 (rev 07-12-2026), printed minimum $75 perm...
Fence PermitIt dependsfence over 7 feet in height requires a building permitValuation-based building permit per CDD-0245 (rev 07-12-2026), printed minimum $75 perm...
HVAC PermitPermit requiredNot specifiedFlat $175 permit fee for HVAC change-outs and new installations plus a 10% technology s...
Patio PermitIt dependscovered patios and patio covers require a building permit; at-grade sidewalks and driveways are exempt, as are unattached decks up to 200 sq ft and no more than 30 inches above gradePatio covers are valued at $34.50 per square foot per CDD-0245's construction valuation...
Plumbing PermitPermit requiredNot specifiedFlat $105 permit fee for one-trade minor plumbing work such as sewer repair, re-plumbin...
Pool PermitPermit requiredNot specifiedValuation-based building permit per CDD-0245 (rev 07-12-2026) using contract value or I...
Roof Replacement PermitIt dependsroof replacement involving structural framing or sheathing changes requires a permit; replacing only the roof covering may be exemptFlat $175 permit fee for re-roofs plus a 10% technology surcharge, per CDD-0245 (rev 07...
Shed PermitIt dependsdetached storage shed under 120 sq ft without electrical or plumbing does not require a permitValuation-based building permit per CDD-0245 (rev 07-12-2026), $75 minimum permit plus...
Solar PermitPermit requiredNot specifiedValuation-based building permit per CDD-0245 (rev 07-12-2026) using contract or equipme...

Electrical Permit in other California localities

Official sources

Verified by a person against the sources above on 2026-06-18, not confirmed with City of Sacramento Community Development Department Building Division. Rules change; confirm before you build. How we verify.

Last checked: 2026-06-18Report an error on this page