Solar Permit in San Francisco, California
Permit required
Yes, a permit is required
Before installing or altering any solar energy system; a building permit is also needed on landmark or historic buildings and on new construction.
Issued bySan Francisco Department of Building Inspection (DBI)
By Mario Bailey, verified against official sources
Quick answer
San Francisco requires an electrical permit to install or alter any solar energy system. A small residential rooftop system (up to 10 kW AC on a single-family or duplex dwelling) on a building that is not a landmark, contributory historic resource or National or State Register listed or eligible building is exempt from the BUILDING permit, but not from the electrical permit; landmark and historic buildings need a building permit and Planning review. Solar hot water systems need a plumbing permit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your California Contractors State License Board (CSLB) license active, and under which business name? Verify it on www.cslb.ca.gov.
California's owner-builder rule (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5) sets what you may do on your own home without hiring anyone. Read the statute.
When a permit is usually needed
Before installing or altering any solar energy system; a building permit is also needed on landmark or historic buildings and on new construction.
What a solar permit costs in San Francisco
How San Francisco compares in California
No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Alameda County | Permit required | ...less than 35 Kva per system (when no plan review is required) $280.00 for... |
| Contra Costa County | Permit required | ...photovoltaic systems 15 kW or less: Building Permit/inspection $86.00 per... |
| Fresno County | Permit required | See schedule |
| Los Angeles | Permit required | ...per-component fees per the LADBS Electrical Permit Fee Schedule: $6 per... |
| Los Angeles County | Permit required | ...for small residential rooftop photovoltaic systems shall not exceed $500... |
| Orange County | Permit required | Solar Permits, Roof-Mounted (includes County Standard Plan): $428 for FY... |
| San Franciscothis page | Permit required | ...Installations: "Solar Photovoltaic Systems" "10 KW rating or less"... |
How to apply in San Francisco
In San Francisco, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.
What most solar permit applications include:
- Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
- For San Francisco, the plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
- Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
- For San Francisco, the site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
- For San Francisco, the one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
- Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
- Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).
General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. San Francisco Department of Building Inspection (DBI) sets the exact checklist for San Francisco.
Where to apply in San Francisco:
San Francisco Department of Building Inspection (DBI)
- Permit Center, 49 South Van Ness Avenue, San Francisco, CA 94103
- Phone: (628) 652-3200
- Email: dbicustomerservice@sfgov.org
Solar Permit in San Francisco compared with nearby California localities
| Locality | Permit needed? | Threshold | What each California schedule says | Verified |
|---|---|---|---|---|
| San Francisco | Permit required | Any size | ...Installations: "Solar Photovoltaic Systems" "10 KW rating or less"... | |
| Alameda County | Permit required | Any size | ...energy system less than 35 Kva per system (when no plan review is required) $280.00... | |
| Contra Costa County | Permit required | Any size | ...mount," photovoltaic systems 15 kW or less: Building Permit/inspection $86.00 per... | |
| Fresno County | Permit required | Any size | See schedule | |
| Los Angeles | Permit required | Any size | ...with itemized per-component fees per the LADBS Electrical Permit Fee Schedule: $6... |
Inspections and closing out your permit
In San Francisco, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
- In San Francisco: where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
- In San Francisco: the inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
- In San Francisco: pV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
- In San Francisco: bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
- In San Francisco: at the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
- In San Francisco: utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the San Francisco permit portal or by phone at (628) 652-3200.
Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Solar Permit checklist for San Francisco
- Confirm the requirement. Yes, a permit is required. Usually needed: Before installing or altering any solar energy system; a building permit is also needed on landmark or historic buildings and on new construction.
- Budget the fee. Table 1A-E Electrical Permit Issuance and Inspection ("July 2026", fees for permits issued on and after July 12, 2026), Category 5 Miscellaneous Installations: "Solar Photovoltaic Systems" "10 KW rating or less" $320; "Each additional 10 KW (up to 2 inspections)" $259. Official fee schedule.
- Apply. In San Francisco, a rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit. Start at the San Francisco permit portal.
- Keep the office details handy. San Francisco Department of Building Inspection (DBI). Phone: (628) 652-3200. Address: Permit Center, 49 South Van Ness Avenue, San Francisco, CA 94103.
- Plan for inspections. In San Francisco, inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need a solar permit in San Francisco?
- San Francisco requires an electrical permit to install or alter any solar energy system. A small residential rooftop system (up to 10 kW AC on a single-family or duplex dwelling) on a building that is not a landmark, contributory historic resource or National or State Register listed or eligible building is exempt from the BUILDING permit, but not from the electrical permit; landmark and historic buildings need a building permit and Planning review. Solar hot water systems need a plumbing permit. Always confirm with the San Francisco Department of Building Inspection (DBI) before starting.
- How much does a solar permit cost in San Francisco?
- Table 1A-E Electrical Permit Issuance and Inspection ("July 2026", fees for permits issued on and after July 12, 2026), Category 5 Miscellaneous Installations: "Solar Photovoltaic Systems" "10 KW rating or less" $320; "Each additional 10 KW (up to 2 inspections)" $259. See the official fee schedule for current amounts.
- How long does a solar permit take in San Francisco?
- Code: a permit for a system of 4 kilowatts or less is issued over the counter if the application meets all requirements; eligible R-3 systems can get an instant electrical permit through SolarAPP+. Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for a solar permit in San Francisco?
- You can apply through the San Francisco permit portal or contact the San Francisco Department of Building Inspection (DBI) directly. The links are listed on this page.
- Can a homeowner pull a solar permit themselves in San Francisco?
- Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how San Francisco applies this before you apply.
From the Library
What else needs a permit in San Francisco
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | Permit required | Any size | ...(Table 1A-C, "CATEGORY 1P" includes "a single kitchen or bathroom remodel", $290)... |
| Deck Permit | It depends | height of the deck walking surface above grade | ...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to... |
| Electrical Permit | Permit required | Any size | ...up to 10,000 sq. ft.": "Up to 10 outlets and/or devices (1 inspection)"... |
| EV Charger Permit | It depends | Before installing, altering or modifying any part of the electrical system for an EV... | ...1 residential wiring applies ("Up to 10 outlets and/or devices (1 inspection)"... |
| Fence Permit | It depends | fences in a side or rear yard; the figure is 3 feet for a fence in the front yard | ...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to... |
| HVAC Permit | Permit required | Any size | ...gas appliance (furnace, hydronic heat, heat pump)" "(maximum two inspections)"... |
| Plumbing Permit | Permit required | Any size | ...or a single kitchen or bathroom remodel" "(maximum two inspections)"... |
| Pool Permit | It depends | prefabricated pools with walls entirely above grade, accessory to a one- or two-family dwelling (Group R-3) | ...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to... |
| Roof Replacement Permit | It depends | area reroofed in any 12-month period, with no roof sheathing installed, repaired or removed | DBI's reroofing page: "$514 and up for single-family homes and duplexes." and "$714 and... |
| Shed Permit | It depends | one-story detached storage shed or playhouse; a 10-foot height limit also applies | ...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to... |
| Water Heater Permit | Permit required | Any size | the residential single-unit plumbing category is "CATEGORY 1P" at $290 and "CATEGORY... |
Solar Permit in other California localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not San Francisco documents; the office above sets the local rules.
How this solar permit page for San Francisco was verified. 2 official sources: sf.gov, codelibrary.amlegal.com; fee schedule: official document. Last checked by Mario Bailey, not confirmed with San Francisco Department of Building Inspection (DBI). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page