California / San Francisco

Electrical Permit in San Francisco, California

Permit required

Yes, a permit is required

Before installing new wiring or altering, extending or adding to an existing electrical installation.

Confirmed on official page Verified

Issued bySan Francisco Department of Building Inspection (DBI)

By Mario Bailey, verified against official sources

Quick answer

San Francisco requires an electrical permit from DBI before installing new wiring or making alterations, extensions or additions to existing electrical installations. The San Francisco Electrical Code 89.121 exempts only narrow like-for-like work: replacing broken luminaires of 50 pounds or less, domestic appliances, fuses, switches and receptacles of 20 amperes or less and same-rating breakers up to 100 amperes (never the main service disconnect) where no wiring changes, plus data cable in R-3 homes. Only owners of stand-alone single-family dwellings may pull a permit to do their own electrical work, after seeing an inspector at the Permit Center.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before installing new wiring or altering, extending or adding to an existing electrical installation.

What an electrical permit costs in San Francisco

Line item
electrical permitBy formulaTable 1A-E Electrical Permit Issuance and Inspection ("July 2026", fees for permits issued on and after July 12, 2026), Category 1 "General Wiring: Residential Buildings up to 10,000 sq. ft.": "Up to 10 outlets and/or devices (1 inspection)" $305; "11 to 20 outlets and/or devices (up to 2 inspections)" $450; "Up to 40 outlets and/or devices, includes up to 200 Amp service upgrade (up to 3 inspections)" $580; "More than 40 outlets and/or devices (up to 4 inspections)" $740.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How San Francisco compares in California

No California jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Alameda CountyPermit required...permit scope, 'Electrical Permit 20% of Building Permit Fees, $140.00...
Contra Costa CountyPermit requiredLand Development Fee Schedule S-002 C.6, "Electrical Permit (Other) $75.00...
Fresno CountyPermit requiredSection 2511 Electrical Code Fees, FY 2026-27: Issuing permits $42.77 each
Los AngelesPermit required...per the LADBS Electrical Permit Fee Schedule (rev 12/2016): minimum $55...
Los Angeles CountyPermit required...of Los Angeles Code, Ord No. 2013-0049), effective July 1, 2026: $41.35...
Orange CountyPermit requiredElectrical Permit Application Flat Fee, 1 to 75 fixtures: $340 for FY 2024-25...
San Franciscothis pagePermit required...to 10,000 sq. ft.": "Up to 10 outlets and/or devices (1 inspection)"...

How to apply in San Francisco

In San Francisco, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For San Francisco, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For San Francisco, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. San Francisco Department of Building Inspection (DBI) sets the exact checklist for San Francisco.

Where to apply in San Francisco:

San Francisco Department of Building Inspection (DBI)

Electrical Permit in San Francisco compared with nearby California localities

LocalityPermit needed?ThresholdWhat each California schedule saysVerified
San FranciscoPermit requiredAny size...up to 10,000 sq. ft.": "Up to 10 outlets and/or devices (1 inspection)"...
Alameda CountyPermit requiredAny size...of a building permit scope, 'Electrical Permit 20% of Building Permit Fees, $140.00...
Contra Costa CountyPermit requiredAny sizeLand Development Fee Schedule S-002 C.6, "Electrical Permit (Other) $75.00 minimum."...
Fresno CountyPermit requiredAny sizeSection 2511 Electrical Code Fees, FY 2026-27: Issuing permits $42.77 each
Los AngelesPermit requiredAny size...item per the LADBS Electrical Permit Fee Schedule (rev 12/2016): minimum $55 for...

Inspections and closing out your permit

In San Francisco, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In San Francisco: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In San Francisco: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In San Francisco: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In San Francisco: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In San Francisco: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In San Francisco: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In San Francisco: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the San Francisco permit portal or by phone at (628) 652-3200.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need an electrical permit in San Francisco?
San Francisco requires an electrical permit from DBI before installing new wiring or making alterations, extensions or additions to existing electrical installations. The San Francisco Electrical Code 89.121 exempts only narrow like-for-like work: replacing broken luminaires of 50 pounds or less, domestic appliances, fuses, switches and receptacles of 20 amperes or less and same-rating breakers up to 100 amperes (never the main service disconnect) where no wiring changes, plus data cable in R-3 homes. Only owners of stand-alone single-family dwellings may pull a permit to do their own electrical work, after seeing an inspector at the Permit Center. Always confirm with the San Francisco Department of Building Inspection (DBI) before starting.
How much does an electrical permit cost in San Francisco?
Table 1A-E Electrical Permit Issuance and Inspection ("July 2026", fees for permits issued on and after July 12, 2026), Category 1 "General Wiring: Residential Buildings up to 10,000 sq. ft.": "Up to 10 outlets and/or devices (1 inspection)" $305; "11 to 20 outlets and/or devices (up to 2 inspections)" $450; "Up to 40 outlets and/or devices, includes up to 200 Amp service upgrade (up to 3 inspections)" $580; "More than 40 outlets and/or devices (up to 4 inspections)" $740. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in San Francisco?
You can apply through the San Francisco permit portal or contact the San Francisco Department of Building Inspection (DBI) directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in San Francisco?
Under California law (Business & Professions Code 7044(a)-(b); Business & Professions Code 7031.5): California exempts an owner from contractor licensing under section 7044 when they personally perform all the work on their own property, or any work they do not perform themselves is done by their own employees paid only wages, and none of the improvements are intended or offered for sale. It also exempts an owner who directly contracts with licensed contractors for each trade, as long as no more than four of the single-family residential structures involved are intended or offered for sale in a calendar year; this route does not apply if the owner instead contracts with a general contractor for the construction. A homeowner may also improve their own principal residence without a license, as long as the work is done before any sale, they have actually resided there for the 12 months before completion, and they have not used this exemption on more than two structures more than once in any three-year period. Selling a self-built structure within one year of completion creates a rebuttable presumption that it was built for sale, which defeats the exemption, and selling five or more structures within a year makes that presumption conclusive. Separately, every city or county that requires a permit must also require the applicant to file a signed statement giving their contractor license number or the basis of their claimed exemption; a false or missing statement carries a civil penalty of up to $500. Confirm how San Francisco applies this before you apply.

From the Library

What else needs a permit in San Francisco

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitPermit requiredAny size...(Table 1A-C, "CATEGORY 1P" includes "a single kitchen or bathroom remodel", $290)...
Deck PermitIt dependsheight of the deck walking surface above grade...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to...
EV Charger PermitIt dependsBefore installing, altering or modifying any part of the electrical system for an EV......1 residential wiring applies ("Up to 10 outlets and/or devices (1 inspection)"...
Fence PermitIt dependsfences in a side or rear yard; the figure is 3 feet for a fence in the front yard...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to...
HVAC PermitPermit requiredAny size...gas appliance (furnace, hydronic heat, heat pump)" "(maximum two inspections)"...
Plumbing PermitPermit requiredAny size...or a single kitchen or bathroom remodel" "(maximum two inspections)"...
Pool PermitIt dependsprefabricated pools with walls entirely above grade, accessory to a one- or two-family dwelling (Group R-3)...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to...
Roof Replacement PermitIt dependsarea reroofed in any 12-month period, with no roof sheathing installed, repaired or removedDBI's reroofing page: "$514 and up for single-family homes and duplexes." and "$714 and...
Shed PermitIt dependsone-story detached storage shed or playhouse; a 10-foot height limit also applies...Fee is the Plan Review Fee plus the Permit Issuance Fee." For a valuation of $1 to...
Solar PermitPermit requiredAny size...Installations: "Solar Photovoltaic Systems" "10 KW rating or less"...
Water Heater PermitPermit requiredAny sizethe residential single-unit plumbing category is "CATEGORY 1P" at $290 and "CATEGORY...

Electrical Permit in other California localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not San Francisco documents; the office above sets the local rules.

How this electrical permit page for San Francisco was verified. 2 official sources: sf.gov, sf.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with San Francisco Department of Building Inspection (DBI). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across California localities

Electrical permit rules nationwide

Permit required
Get quotes