PermitNotebook / Permit processing times
How long building permits take, city by city
We count the days between application and permit in the open permit records of 9 cities and counties: 207,694 permits issued November 2024 to October 2026 that fall into ten common project types and carry both dates, refreshed each month. Each place's page says exactly which of its records count.
What the records show
- New home: medians ran from 16 days in Baton Rouge to 408 days in San Diego County, across 6 places with enough permits to measure. Cities define and file this work differently; see each page.
Median days to permit, last 12 months
Permits issued November 2025 to October 2026. "Too few" means under 50 permits of that type in the year; "Withheld" means one of two things: the records cannot time that type honestly (most lack an application date, or the city changed how it records them), or a reading of a random sample of its records, each against its own description of the work or its page on the city's permit portal, did not give 95% confidence that at least 85% of them are that work (25 of 25 read, or 48 of 50); each city page says which. A dash means we cannot separate that type in the place's records.
| Place | New home | Addition or remodel | Deck | ADU | Roof replacement | Solar panels | Electrical |
|---|---|---|---|---|---|---|---|
| Austin, Texas | 52 days | Withheld | Withheld | Too few | 3 days | Withheld | 6 days |
| Baton Rouge, Louisiana | 16 days | Withheld | Too few | Too few | Withheld | Too few | Same day |
| Chicago, Illinois | Withheld | Withheld | Too few | Withheld | 1 day | 9 days | 1 day |
| Detroit, Michigan | 49 days | Withheld | Too few | Too few | 5 days | 32 days | - |
| Nashville, Tennessee | 36 days | 14 days | Withheld | 44 days | Withheld | Too few | Same day |
| New Orleans, Louisiana | Withheld | Withheld | Too few | Too few | 8 days | Withheld | 13 days |
| Pierce County, Washington | 24 days | Withheld | Withheld | Withheld | 6 days | 8 days | - |
| San Diego, California | Withheld | 74 days | Too few | 274 days | Too few | Withheld | Withheld |
| San Diego County, California | 408 days | 173 days | - | 216 days | - | 1 day | Withheld |
Go deeper
Places we read but do not publish yet
These publish permit records with both dates, but this month's records do not meet our bar for a page (at least 3 permit types, each with 50 or more permits in 12 months and each passing a reading of a random sample of its records, which needs 25 of 25 or 48 of 50 to be that work; and data less than 45 days old):
- New York City, New York: 7 permit types have 50+ issued permits in the last 12 months, but only 1 of them has passed the reading of a random sample of records (needs 3).
- Los Angeles, California: 4 permit types have 50+ issued permits in the last 12 months, but none of them has passed the reading of a random sample of records (needs 3).
- Phoenix, Arizona: 1 permit type has 50+ issued permits in the last 12 months, but no random sample of its records has been read yet (needs 3); only 24 timed permits in the latest 3 months against 1,028 a year earlier, so the feed looks incomplete.
- San Antonio, Texas: 10 permit types have 50+ issued permits in the last 12 months, but only 2 of them have passed the reading of a random sample of records (needs 3).
- San Francisco, California: 4 permit types have 50+ issued permits in the last 12 months, but none of them has passed the reading of a random sample of records (needs 3).
- Seattle, Washington: 5 permit types have 50+ issued permits in the last 12 months, but only 1 of them has passed the reading of a random sample of records (needs 3).
- Denver, Colorado: 2 permit types have 50+ issued permits in the last 12 months, but no random sample of their records has been read yet (needs 3).
- Tucson, Arizona: 6 permit types have 50+ issued permits in the last 12 months, but only 2 of them have passed the reading of a random sample of records (needs 3).
- Raleigh, North Carolina: 5 permit types have 50+ issued permits in the last 12 months, but only 1 of them has passed the reading of a random sample of records (needs 3).
- Portland, Oregon: 1 permit type has 50+ issued permits in the last 12 months, but no random sample of its records has been read yet (needs 3); newest issued permit is 47 days old (limit 45).
- Milwaukee, Wisconsin: 1 permit type has 50+ issued permits in the last 12 months, but no random sample of its records has been read yet (needs 3); newest issued permit is 155 days old (limit 45); no timed permits in the latest 3 months against 433 a year earlier, so the feed looks incomplete.
- Cincinnati, Ohio: 5 permit types have 50+ issued permits in the last 12 months, but only 2 of them have passed the reading of a random sample of records (needs 3).
- Mesa, Arizona: 5 permit types have 50+ issued permits in the last 12 months, but only 1 of them has passed the reading of a random sample of records (needs 3).
- Montgomery County, Maryland: 8 permit types have 50+ issued permits in the last 12 months, but only 1 of them has passed the reading of a random sample of records (needs 3).