PermitNotebook / Permit processing times

How long building permits take, city by city

By Mario Bailey Last checked · 11 official sources

We count the days between application and permit in the open permit records of 9 cities and counties: 207,694 permits issued November 2024 to October 2026 that fall into ten common project types and carry both dates, refreshed each month. Each place's page says exactly which of its records count.

What the records show

Median days to permit, last 12 months

Permits issued November 2025 to October 2026. "Too few" means under 50 permits of that type in the year; "Withheld" means one of two things: the records cannot time that type honestly (most lack an application date, or the city changed how it records them), or a reading of a random sample of its records, each against its own description of the work or its page on the city's permit portal, did not give 95% confidence that at least 85% of them are that work (25 of 25 read, or 48 of 50); each city page says which. A dash means we cannot separate that type in the place's records.

Median days from application to permit by place and permit type, permits issued November 2025 to October 2026
Place New homeAddition or remodelDeckADURoof replacementSolar panelsElectrical
Austin, Texas 52 daysWithheldWithheldToo few3 daysWithheld6 days
Baton Rouge, Louisiana 16 daysWithheldToo fewToo fewWithheldToo fewSame day
Chicago, Illinois WithheldWithheldToo fewWithheld1 day9 days1 day
Detroit, Michigan 49 daysWithheldToo fewToo few5 days32 days-
Nashville, Tennessee 36 days14 daysWithheld44 daysWithheldToo fewSame day
New Orleans, Louisiana WithheldWithheldToo fewToo few8 daysWithheld13 days
Pierce County, Washington 24 daysWithheldWithheldWithheld6 days8 days-
San Diego, California Withheld74 daysToo few274 daysToo fewWithheldWithheld
San Diego County, California 408 days173 days-216 days-1 dayWithheld

Go deeper

Places we read but do not publish yet

These publish permit records with both dates, but this month's records do not meet our bar for a page (at least 3 permit types, each with 50 or more permits in 12 months and each passing a reading of a random sample of its records, which needs 25 of 25 or 48 of 50 to be that work; and data less than 45 days old):