PermitNotebook / Permit processing times / Baton Rouge

How long does it take to get a building permit in Baton Rouge?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 16 days for new homes.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Baton Rouge's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Electrical "Electrical Permit (R)" records. Same day 0 to 1 day 3 days 68.1% 626 49 of 50
Plumbing "Plumbing Permit (R)" records. Same day 0 to 1 day Too few 59.1% 66 25 of 25
New home "New Building Permit (R)" records. 16 days 9 to 33 days 103 days 0% 516 25 of 25

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Addition or remodel 394 25 22 1 2
Roof replacement 1,653 25 22 0 3
Demolition 124 25 13 1 11
Commercial alteration 294 50 37 6 7

Under 50 permits in the year: decks (1), ADUs (2), solar installations (9).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Electrical Same day (183) Same day(159) Same day(130)
New home 16 days (111) 15 days(108) 16 days(176)

New home permits by month

new homes issued each month in Baton Rouge (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 29 permits, median 15 days December 2024: 47 permits, median 18 days January 2025: 34 permits, median 21 days February 2025: 32 permits, median 20 days March 2025: 26 permits, median 9 days April 2025: 69 permits, median 49 days May 2025: 27 permits, median 17 days June 2025: 28 permits, median 16 days July 2025: 42 permits, median 21 days August 2025: 28 permits, median 19 days September 2025: 31 permits, median 12 days October 2025: 49 permits, median 12 days November 2025: 25 permits, median 16 days December 2025: 44 permits, median 22 days January 2026: 35 permits, median 30 days February 2026: 66 permits, median 25 days March 2026: 49 permits, median 16 days April 2026: 61 permits, median 12 days May 2026: 39 permits, median 12 days June 2026: 50 permits, median 11 days July 2026: 36 permits, median 17 days August 2026: 35 permits, median 15 days September 2026: 30 permits, median 16 days October 2026: 46 permits, median 20 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (69 at most). Dots: median days.

Review paths and the city's published rules

Quoted from City of Baton Rouge and Parish of East Baton Rouge, Department of Development's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

How the fee is set

Your next step

Planning a new home? Last year three in four were issued within 33 days of application, nine in ten within 103 days.

Sources

City of Baton Rouge and Parish of East Baton Rouge, Department of Development. License: Public Domain. East Baton Rouge Parish building permits with a creation date and an issue date.

Used: 6,165 of 15,977. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem