PermitNotebook / Permit processing times / Baton Rouge
How long does it take to get a building permit in Baton Rouge?
Median, November 2025 to October 2026: 16 days for new homes.
Days to permit, by type
| Permit type, as Baton Rouge's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Electrical "Electrical Permit (R)" records. | Same day | 0 to 1 day | 3 days | 68.1% | 626 | 49 of 50 |
| Plumbing "Plumbing Permit (R)" records. | Same day | 0 to 1 day | Too few | 59.1% | 66 | 25 of 25 |
| New home "New Building Permit (R)" records. | 16 days | 9 to 33 days | 103 days | 0% | 516 | 25 of 25 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Addition or remodel | 394 | 25 | 22 | 1 | 2 |
| Roof replacement | 1,653 | 25 | 22 | 0 | 3 |
| Demolition | 124 | 25 | 13 | 1 | 11 |
| Commercial alteration | 294 | 50 | 37 | 6 | 7 |
Under 50 permits in the year: decks (1), ADUs (2), solar installations (9).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Electrical | Same day (183) | Same day(159) | Same day(130) |
| New home | 16 days (111) | 15 days(108) | 16 days(176) |
New home permits by month
Review paths and the city's published rules
Quoted from City of Baton Rouge and Parish of East Baton Rouge, Department of Development's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Standard plan review time (How long will it take to get a permit?). "Residential plan reviews will be completed within seven (7) business days after receipt of all required information necessary in order to complete an initial review. Residential resubmittals will be reviewed within three (3) business days after receipt."
- Plan review is one step (How long will it take to get a permit?).A finished plan review is not the same as an issued permit in East Baton Rouge Parish; issuance can take longer depending on the permit's other requirements. "Plan review is only one of the many steps in the permitting and review process. It may take additional time for a permit to be issued, based on the specific permit requirements."
Faster routes
- Expedited Plan Review Service. "Expedited RESIDENTIAL plan reviews will be completed within three (3) business days after receipt of all required information, and resubmittals reviewed within two (2) business days after receipt."
Before you apply
- Roof Permits & Installations (reroof photographs).A Baton Rouge reroof permit requires the contractor's geotagged photos of the roofing work, combined into one PDF and uploaded in MGO Connect. "Contractors must provide geotagged photographs documenting roof installation work. Please create one pdf with all photos. The pictures will also be uploaded to the MGOCONNECT.ORG website."
After you apply
- Inspection scheduling lead time (Permits and Inspections FAQ). "How far in advance do I need to schedule an inspection? Inspections can be scheduled for the next business day."
- After hours inspections.Baton Rouge offers inspections outside normal hours only when an inspector is free, for an extra $150. "Can I schedule an after hours inspection? Yes. However, after hours inspections are subject to inspector availability and require an additional $150 fee."
How the fee is set
- Builders Package.On new residential permits in East Baton Rouge Parish, the applicant can defer part of the fees until the plans are approved. "The Builders Package option allows the Applicant to defer a pre-dermined portion of the fees, to be paid after plans are approved. The option is only available for Residential: NEW permit types."
- Expedited Review Costs (residential).The expedited residential plan review costs a $60 base plus 10 cents for every square foot under roof. "Residential: $60 + $0.10 per total square foot under roof"
Your next step
Planning a new home? Last year three in four were issued within 33 days of application, nine in ten within 103 days.
Sources
- EBR Building Permits: application date "creationdate", issue date "issueddate".
City of Baton Rouge and Parish of East Baton Rouge, Department of Development. License: Public Domain. East Baton Rouge Parish building permits with a creation date and an issue date.
Used: 6,165 of 15,977. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem