Permit processing times by permit type
The same project can take days in one city and months in the next. Each table ranks the places we measure by the median wait from application to permit for permits issued November 2025 to October 2026, fastest first.
Reading these tables fairly
Read these rankings as a starting point, not a verdict. Cities file the same work in different ways: one issues a reroof online in minutes, another routes it through plan review; one counts every interior job as an alteration, another sends small ones through an express program counted elsewhere. Each place's page lists exactly which of its records count as each type, and some types cover all buildings where a city does not separate homes from businesses. A city compared with itself over time is the fairest reading. Methodology.
New home
A new single-family home, duplex or townhouse (a new dwelling, not an ADU).
Lowest median: Baton Rouge (16 days). Highest: San Diego County (408 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 2 got faster and 1 was about the same.
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Baton Rouge, Louisiana | 16 days | 9 to 33 days | 103 days | 516 |
| Pierce County, Washington | 24 days | 12 to 70 days | 171 days | 1,196 |
| Nashville, Tennessee | 36 days | 21 to 71 days | 180 days | 2,485 |
| Detroit, Michigan | 49 days | 36 to 88 days | Too few | 68 |
| Austin, Texas | 52 days | 26 to 115 days | 263 days | 2,227 |
| San Diego County, California | 408 days | 274 to 603 days | 866 days | 135 |
Addition or remodel
A residential addition, alteration, remodel or repair filed as a building permit.
Lowest median: Nashville (14 days). Highest: San Diego County (173 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 2 got faster and 1 was about the same.
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Nashville, Tennessee | 14 days | 5 to 35 days | 71 days | 1,486 |
| San Diego, California | 74 days | 21 to 209 days | 343 days | 2,226 |
| San Diego County, California | 173 days | 82 to 301 days | 460 days | 178 |
ADU
An accessory dwelling unit, attached, detached or converted, including junior ADUs.
Lowest median: Nashville (44 days). Highest: San Diego (274 days).
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Nashville, Tennessee | 44 days | 21 to 85 days | 172 days | 178 |
| San Diego County, California | 216 days | 125 to 353 days | 544 days | 278 |
| San Diego, California | 274 days | 162 to 459 days | 709 days | 1,376 |
Roof replacement
A reroof or roof replacement (not a roof deck and not solar).
Lowest median: Chicago (1 day). Highest: New Orleans (8 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 1 got faster, 1 got slower and 1 was about the same.
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Chicago, Illinois | 1 day | 0 to 4 days | 12 days | 1,305 |
| Austin, Texas | 3 days | 0 to 7 days | Too few | 99 |
| Detroit, Michigan | 5 days | 0 to 11 days | 27 days | 218 |
| Pierce County, Washington | 6 days | 4 to 15 days | Too few | 74 |
| New Orleans, Louisiana | 8 days | 5 to 15 days | 35 days | 1,169 |
Solar panels
A rooftop or ground photovoltaic system, whether filed as a building or an electrical permit.
Lowest median: San Diego County (1 day). Highest: Detroit (32 days).
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| San Diego County, California | 1 day | 0 to 2 days | 4 days | 2,609 |
| Pierce County, Washington | 8 days | 5 to 19 days | Too few | 56 |
| Chicago, Illinois | 9 days | 6 to 15 days | 26 days | 1,802 |
| Detroit, Michigan | 32 days | 14 to 63 days | Too few | 68 |
Electrical
An electrical trade permit (service, wiring, panel, EV charger), excluding solar.
Lowest median: Nashville, Baton Rouge (same day). Highest: New Orleans (13 days). Against the same months a year earlier, all 3 places with enough permits in both windows were about the same.
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Nashville, Tennessee | Same day | Same day | 1 day | 7,772 |
| Baton Rouge, Louisiana | Same day | 0 to 1 day | 3 days | 626 |
| Chicago, Illinois | 1 day | 0 to 6 days | 17 days | 5,613 |
| Austin, Texas | 6 days | 3 to 17 days | 90 days | 7,836 |
| New Orleans, Louisiana | 13 days | 5 to 32 days | 83 days | 2,416 |
Plumbing
A plumbing trade permit (fixtures, water heater, gas or sewer line).
Lowest median: San Diego, Baton Rouge and 2 others (same day). Highest: Chicago (3 days). Against the same months a year earlier, all 5 places with enough permits in both windows were about the same.
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| San Diego, California | Same day | Same day | 1 day | 2,699 |
| Baton Rouge, Louisiana | Same day | 0 to 1 day | Too few | 66 |
| Pierce County, Washington | Same day | Same day | Same day | 1,093 |
| San Diego County, California | Same day | Same day | Same day | 950 |
| New Orleans, Louisiana | 2 days | 1 to 6 days | 19 days | 1,999 |
| Chicago, Illinois | 3 days | 1 to 8 days | 18 days | 673 |
Demolition
A demolition or wrecking permit for a whole structure. Cities differ on demolitions of garages and other accessory buildings; each city's rule says whether they are counted.
Lowest median: Nashville (13 days). Highest: San Diego (266 days).
| Place | Median | Middle half | 9 in 10 within | Permits |
|---|---|---|---|---|
| Nashville, Tennessee | 13 days | 6 to 30 days | 66 days | 616 |
| Austin, Texas | 21 days | 13 to 51 days | 140 days | 711 |
| San Diego, California | 266 days | 183 to 432 days | 610 days | 116 |