PermitNotebook / Permit processing times / By permit type

Permit processing times by permit type

By Mario Bailey Last checked

The same project can take days in one city and months in the next. Each table ranks the places we measure by the median wait from application to permit for permits issued November 2025 to October 2026, fastest first.

Reading these tables fairly

Read these rankings as a starting point, not a verdict. Cities file the same work in different ways: one issues a reroof online in minutes, another routes it through plan review; one counts every interior job as an alteration, another sends small ones through an express program counted elsewhere. Each place's page lists exactly which of its records count as each type, and some types cover all buildings where a city does not separate homes from businesses. A city compared with itself over time is the fairest reading. Methodology.

New home

A new single-family home, duplex or townhouse (a new dwelling, not an ADU).

Lowest median: Baton Rouge (16 days). Highest: San Diego County (408 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 2 got faster and 1 was about the same.

New home: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Baton Rouge, Louisiana 16 days 9 to 33 days 103 days 516
Pierce County, Washington 24 days 12 to 70 days 171 days 1,196
Nashville, Tennessee 36 days 21 to 71 days 180 days 2,485
Detroit, Michigan 49 days 36 to 88 days Too few 68
Austin, Texas 52 days 26 to 115 days 263 days 2,227
San Diego County, California 408 days 274 to 603 days 866 days 135

Addition or remodel

A residential addition, alteration, remodel or repair filed as a building permit.

Lowest median: Nashville (14 days). Highest: San Diego County (173 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 2 got faster and 1 was about the same.

Addition or remodel: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Nashville, Tennessee 14 days 5 to 35 days 71 days 1,486
San Diego, California 74 days 21 to 209 days 343 days 2,226
San Diego County, California 173 days 82 to 301 days 460 days 178

ADU

An accessory dwelling unit, attached, detached or converted, including junior ADUs.

Lowest median: Nashville (44 days). Highest: San Diego (274 days).

ADU: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Nashville, Tennessee 44 days 21 to 85 days 172 days 178
San Diego County, California 216 days 125 to 353 days 544 days 278
San Diego, California 274 days 162 to 459 days 709 days 1,376

Roof replacement

A reroof or roof replacement (not a roof deck and not solar).

Lowest median: Chicago (1 day). Highest: New Orleans (8 days). Against the same months a year earlier, of the 3 places with enough permits in both windows, 1 got faster, 1 got slower and 1 was about the same.

Roof replacement: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Chicago, Illinois 1 day 0 to 4 days 12 days 1,305
Austin, Texas 3 days 0 to 7 days Too few 99
Detroit, Michigan 5 days 0 to 11 days 27 days 218
Pierce County, Washington 6 days 4 to 15 days Too few 74
New Orleans, Louisiana 8 days 5 to 15 days 35 days 1,169

Solar panels

A rooftop or ground photovoltaic system, whether filed as a building or an electrical permit.

Lowest median: San Diego County (1 day). Highest: Detroit (32 days).

Solar panels: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
San Diego County, California 1 day 0 to 2 days 4 days 2,609
Pierce County, Washington 8 days 5 to 19 days Too few 56
Chicago, Illinois 9 days 6 to 15 days 26 days 1,802
Detroit, Michigan 32 days 14 to 63 days Too few 68

Electrical

An electrical trade permit (service, wiring, panel, EV charger), excluding solar.

Lowest median: Nashville, Baton Rouge (same day). Highest: New Orleans (13 days). Against the same months a year earlier, all 3 places with enough permits in both windows were about the same.

Electrical: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Nashville, Tennessee Same day Same day 1 day 7,772
Baton Rouge, Louisiana Same day 0 to 1 day 3 days 626
Chicago, Illinois 1 day 0 to 6 days 17 days 5,613
Austin, Texas 6 days 3 to 17 days 90 days 7,836
New Orleans, Louisiana 13 days 5 to 32 days 83 days 2,416

Plumbing

A plumbing trade permit (fixtures, water heater, gas or sewer line).

Lowest median: San Diego, Baton Rouge and 2 others (same day). Highest: Chicago (3 days). Against the same months a year earlier, all 5 places with enough permits in both windows were about the same.

Plumbing: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
San Diego, California Same day Same day 1 day 2,699
Baton Rouge, Louisiana Same day 0 to 1 day Too few 66
Pierce County, Washington Same day Same day Same day 1,093
San Diego County, California Same day Same day Same day 950
New Orleans, Louisiana 2 days 1 to 6 days 19 days 1,999
Chicago, Illinois 3 days 1 to 8 days 18 days 673

Demolition

A demolition or wrecking permit for a whole structure. Cities differ on demolitions of garages and other accessory buildings; each city's rule says whether they are counted.

Lowest median: Nashville (13 days). Highest: San Diego (266 days).

Demolition: median days from application to permit by place
Place Median Middle half 9 in 10 within Permits
Nashville, Tennessee 13 days 6 to 30 days 66 days 616
Austin, Texas 21 days 13 to 51 days 140 days 711
San Diego, California 266 days 183 to 432 days 610 days 116