PermitNotebook / Permit processing times / Nashville
How long does it take to get a building permit in Nashville?
Median, November 2025 to October 2026: 14 days for additions and remodels; 36 days for new homes.
Days to permit, by type
| Permit type, as Nashville's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Electrical "Full Electrical Permit" trade permits (service releases and reconnects excluded), homes and businesses together. | Same day | Same day | 1 day | 88.5% | 7,772 | 25 of 25 |
| Demolition "Demolition Permit - Residential" permits. | 13 days | 6 to 30 days | 66 days | 1.5% | 616 | 25 of 25 |
| Addition or remodel "Building Residential - Addition" and "Rehab" permits on a single family residence (decks, ADUs and roofs have their own Metro subtypes and are not read from descriptions). By the city's own label: Building Residential - Addition: Single Family Residence, 757 at 24 days; Building Residential - Rehab: Single Family Residence, 729 at 7 days. | 14 days | 5 to 35 days | 71 days | 5.9% | 1,486 | 48 of 50 |
| New home "Building Residential - New" permits for a single family residence or a townhome. By the city's own label: Building Residential - New: Single Family Residence, 1,736 at 34 days; Building Residential - New: Multifamily, Townhome, 749 at 42 days. | 36 days | 21 to 71 days | 180 days | 0% | 2,485 | 49 of 50 |
| ADU Residential permits with Metro's subtype "Detached Accessory Dwelling Unit": new-building permits, and addition or rehab permits that create the unit (a garage conversion, a unit over a garage). Amendments, changes of contractor, and renovations or enlargements of a unit that already exists are left out, because they re-issue or alter a permit already granted. | 44 days | 21 to 85 days | 172 days | 0% | 178 | 48 of 50 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Deck | 334 | 25 | 18 | 6 | 1 |
| Roof replacement | 80 | 25 | 22 | 2 | 1 |
| Plumbing | 7,947 | 50 | 46 | 0 | 4 |
| Commercial alteration | 1,386 | 25 | 21 | 4 | 0 |
Under 50 permits in the year: solar installations (34).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Electrical | Same day (1,875) | Same day(1,975) | Same day(2,089) |
| Demolition | 13 days (167) | 9 days(151) | 9 days(148) |
| Addition or remodel | 13 days (428) | 17 days(375) | 15 days(364) |
| ADU | 43 days (62) | Too few | 47 days(52) |
New home: no then-and-now row, because the share of "Building Residential - New: Multifamily, Townhome" permits moved from 12% a year earlier to 38% now, so the comparison would measure the mix, not the wait.
New home permits by month
Review paths and the city's published rules
Quoted from Metro Nashville Codes Administration's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Review Process Timeline (Electrical Photovoltaic permits).Metro Codes aims to review a complete residential solar permit application within 30 days of submission. "Best efforts are made to review completed residential permit applications within 30 days of submission."
Faster routes
- ePermits (online application for registered contractors). "To apply for a Residential or Commercial permit, submit your permitting documents to the Zoning Help Desk or Registered contractors can apply for residential building permits by visiting ePermits."
Before you apply
- Residential site plan.Metro Codes says an accurate, complete site plan is very important for speeding up both the permit application and the inspections. "An accurate and complete site plan is extremely important in expediting the permit application and inspection process."
- Permit application checklist steps. "Do not seek to determine what reviews and approvals are required on your own. If you fail to complete the steps identified in your permit application your process will be delayed."
- Construction plans for single-family homes. "We do not normally require construction plans for single family construction at time of application. (Plans are reviewed for homes containing more than 5,000 square feet or more than 3 stories in height)."
- Deck permit site plan (Add a Deck or Patio to a Residence). "Site Plan showing the proposed location of the deck with distances to property lines, existing structures and easements labeled."
After you apply
- Requesting an Inspection by phone. "To schedule an inspection by phone, have your Metro permit number ready for each job before calling our offices to request an inspection. Please call between 7:30 a.m. and 4:00 p.m. Monday through Friday."
How the fee is set
- Building permit fee basis.Nashville prices a new home's building permit from valuation figures, but prices remodels on the actual value of the work, with trade permits charged separately. "Fees for building permits involving new residential structures are charged based on the valuation figures. Fees for residential remodeling and all commercial work are based on the actual value of the improvements. Separate fees are charged for trade permits: plumbing, electrical, and gas/mechanical."
- Permit Fees (Electrical Photovoltaic permits). "Electrical Photovoltaic permits start at $75.00, and may increase marginally depending upon the fixture and equipment type specific to your plan."
Your next step
Planning an addition or remodel? Last year three in four were issued within 35 days of application, nine in ten within 71 days.
Sources
- Building Permits Issued: application date "Date_Entered", issue date "Date_Issued".
- Trade Permits: application date "Date_Entered", issue date "Date_Issued".
Metro Nashville Codes Administration. License: Nashville Open Data terms. Building permits issued and trade permits, with an entered date and an issue date. Permit amendments and changes of contractor are not counted in any type.
Used: 45,520 of 88,477. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem