PermitNotebook / Permit processing times / Nashville

How long does it take to get a building permit in Nashville?

By Mario Bailey Last checked · 2 official sources

Median, November 2025 to October 2026: 14 days for additions and remodels; 36 days for new homes.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Nashville's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Electrical "Full Electrical Permit" trade permits (service releases and reconnects excluded), homes and businesses together. Same day Same day 1 day 88.5% 7,772 25 of 25
Demolition "Demolition Permit - Residential" permits. 13 days 6 to 30 days 66 days 1.5% 616 25 of 25
Addition or remodel "Building Residential - Addition" and "Rehab" permits on a single family residence (decks, ADUs and roofs have their own Metro subtypes and are not read from descriptions). By the city's own label: Building Residential - Addition: Single Family Residence, 757 at 24 days; Building Residential - Rehab: Single Family Residence, 729 at 7 days. 14 days 5 to 35 days 71 days 5.9% 1,486 48 of 50
New home "Building Residential - New" permits for a single family residence or a townhome. By the city's own label: Building Residential - New: Single Family Residence, 1,736 at 34 days; Building Residential - New: Multifamily, Townhome, 749 at 42 days. 36 days 21 to 71 days 180 days 0% 2,485 49 of 50
ADU Residential permits with Metro's subtype "Detached Accessory Dwelling Unit": new-building permits, and addition or rehab permits that create the unit (a garage conversion, a unit over a garage). Amendments, changes of contractor, and renovations or enlargements of a unit that already exists are left out, because they re-issue or alter a permit already granted. 44 days 21 to 85 days 172 days 0% 178 48 of 50

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Deck 334 25 18 6 1
Roof replacement 80 25 22 2 1
Plumbing 7,947 50 46 0 4
Commercial alteration 1,386 25 21 4 0

Under 50 permits in the year: solar installations (34).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Electrical Same day (1,875) Same day(1,975) Same day(2,089)
Demolition 13 days (167) 9 days(151) 9 days(148)
Addition or remodel 13 days (428) 17 days(375) 15 days(364)
ADU 43 days (62) Too few 47 days(52)

New home: no then-and-now row, because the share of "Building Residential - New: Multifamily, Townhome" permits moved from 12% a year earlier to 38% now, so the comparison would measure the mix, not the wait.

New home permits by month

new homes issued each month in Nashville (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 197 permits, median 40 days December 2024: 188 permits, median 26 days January 2025: 268 permits, median 36 days February 2025: 193 permits, median 26 days March 2025: 226 permits, median 37 days April 2025: 205 permits, median 37 days May 2025: 210 permits, median 23 days June 2025: 310 permits, median 36 days July 2025: 196 permits, median 38 days August 2025: 191 permits, median 38 days September 2025: 229 permits, median 41 days October 2025: 228 permits, median 22 days November 2025: 162 permits, median 33 days December 2025: 213 permits, median 31 days January 2026: 146 permits, median 48 days February 2026: 154 permits, median 39 days March 2026: 227 permits, median 35 days April 2026: 246 permits, median 57 days May 2026: 207 permits, median 33 days June 2026: 217 permits, median 34 days July 2026: 228 permits, median 43 days August 2026: 225 permits, median 33 days September 2026: 272 permits, median 32 days October 2026: 188 permits, median 29 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (310 at most). Dots: median days.

Review paths and the city's published rules

Quoted from Metro Nashville Codes Administration's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

How the fee is set

Your next step

Planning an addition or remodel? Last year three in four were issued within 35 days of application, nine in ten within 71 days.

Sources

Metro Nashville Codes Administration. License: Nashville Open Data terms. Building permits issued and trade permits, with an entered date and an issue date. Permit amendments and changes of contractor are not counted in any type.

Used: 45,520 of 88,477. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem