PermitNotebook / Permit processing times / New Orleans
How long does it take to get a building permit in New Orleans?
Median, November 2025 to October 2026: 2 days for plumbing permits; 8 days for roof replacements; 13 days for electrical permits.
Days to permit, by type
| Permit type, as New Orleans' records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Plumbing Residential permits of type PLMB. | 2 days | 1 to 6 days | 19 days | 11% | 1,999 | 49 of 50 |
| Roof replacement Residential permits of type ROOF (Residential Re-Roofing). | 8 days | 5 to 15 days | 35 days | 2.1% | 1,169 | 25 of 25 |
| Electrical Residential electrical permits of type SERV (service, circuit, feeder) and ERPR (repair, replacement, addition), except those whose description names solar, an inverter or a battery system, or the wiring of a new house, duplex or building, which are timed with their own permits. By the city's own label: Electrical Service / Circuit / Feeder, 2,319 at 12 days; Electrical Repair / Replacement / Addition, 97 at 109 days. | 13 days | 5 to 32 days | 83 days | 4% | 2,416 | 50 of 50 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| New home | 343 | 25 | 22 | 3 | 0 |
| Addition or remodel | 1,171 | 50 | 45 | 4 | 1 |
| Demolition | 130 | 50 | 47 | 3 | 0 |
| Commercial alteration | 644 | 25 | 16 | 9 | 0 |
- Solar panels, not shown: only 7 were issued in the latest 3 months against 108 a year earlier, a break in how the city records them.
Under 50 permits in the year: decks (9), ADUs (1).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Plumbing | 2 days (533) | 3 days(498) | 3 days(544) |
| Roof replacement | 10 days (321) | 7 days(225) | 7 days(303) |
Electrical: no then-and-now row, because the share of "Electrical Service / Circuit / Feeder" permits moved from 80% a year earlier to 97% now, so the comparison would measure the mix, not the wait.
Electrical permits: a median of 20 days for permits issued November 2025 to April 2026, then 9 days for those issued May 2026 to October 2026. The records do not say why, so the 12-month figure blends both periods.
Roof replacement permits by month
Review paths and the city's published rules
Quoted from City of New Orleans Department of Safety and Permits's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Renovation (Non-Structural) Permit duration. "A building permit will only be issued after the plan review process is completed and compliance with all applicable regulations is verified. Duration: Residential projects, 2-5 business days; Commercial projects, 20-30 business days."
Faster routes
- SolarAPP+ (Solar Permitting).New rooftop solar permits filed through OneStop need an approved plan review from the automated SolarAPP+ platform. "Beginning March 1, 2025, new PV system solar permits through OneStop will require approved plan reviews through the SolarAPP+ platform."
Before you apply
- Standards for Complete Permit Applications. "If the application is missing any information or required documentation the application will be rejected and informed to resubmit with required documents."
- Signed contract (Standards for Complete Permit Applications).A New Orleans permit application needs a signed contract that describes all the work and splits the cost between materials and labor. "Submit a signed and dated contract. The contract must include signatures, printed names and titles. The contract must include the full description of all work being done and an itemized cost between materials and labor."
After you apply
- Schedule your Inspections. "Inspections can only be requested once a permit status is "Issued". Contractors can schedule inspections by emailing the following information to inspections@nola.gov:"
- When Do Building Permits Expire?. "Building permits expire 6 months after the date of issuance, unless you have had inspections before that time."
How the fee is set
- Building Permit Fee.A New Orleans building permit costs a $60 base plus $5 for every $1,000 of work value. "$60 plus $5 per $1,000 of work to be performed"
Your next step
Planning a roof replacement? Last year three in four were issued within 15 days of application, nine in ten within 35 days.
Sources
- Permits - BLDS: application date "applieddate", issue date "issuedate".
City of New Orleans Department of Safety and Permits. License: Creative Commons 1.0 Universal (Public Domain Dedication). The city's BLDS-format permit file, with an applied date and an issue date, sorted by the city's own permit type codes. Historic district approvals, change-of-address and painting permits, which the file also lists under building permits, are not counted.
Used: 16,241 of 47,990. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem