PermitNotebook / Permit processing times / New Orleans

How long does it take to get a building permit in New Orleans?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 2 days for plumbing permits; 8 days for roof replacements; 13 days for electrical permits.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as New Orleans' records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Plumbing Residential permits of type PLMB. 2 days 1 to 6 days 19 days 11% 1,999 49 of 50
Roof replacement Residential permits of type ROOF (Residential Re-Roofing). 8 days 5 to 15 days 35 days 2.1% 1,169 25 of 25
Electrical Residential electrical permits of type SERV (service, circuit, feeder) and ERPR (repair, replacement, addition), except those whose description names solar, an inverter or a battery system, or the wiring of a new house, duplex or building, which are timed with their own permits. By the city's own label: Electrical Service / Circuit / Feeder, 2,319 at 12 days; Electrical Repair / Replacement / Addition, 97 at 109 days. 13 days 5 to 32 days 83 days 4% 2,416 50 of 50

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
New home 343 25 22 3 0
Addition or remodel 1,171 50 45 4 1
Demolition 130 50 47 3 0
Commercial alteration 644 25 16 9 0

Under 50 permits in the year: decks (9), ADUs (1).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Plumbing 2 days (533) 3 days(498) 3 days(544)
Roof replacement 10 days (321) 7 days(225) 7 days(303)

Electrical: no then-and-now row, because the share of "Electrical Service / Circuit / Feeder" permits moved from 80% a year earlier to 97% now, so the comparison would measure the mix, not the wait.

Electrical permits: a median of 20 days for permits issued November 2025 to April 2026, then 9 days for those issued May 2026 to October 2026. The records do not say why, so the 12-month figure blends both periods.

Roof replacement permits by month

roof replacements issued each month in New Orleans (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 0 permits December 2024: 0 permits January 2025: 0 permits February 2025: 0 permits March 2025: 0 permits April 2025: 0 permits May 2025: 32 permits, median 4 days June 2025: 77 permits, median 7 days July 2025: 65 permits, median 6 days August 2025: 53 permits, median 7 days September 2025: 71 permits, median 6 days October 2025: 101 permits, median 8 days November 2025: 77 permits, median 5 days December 2025: 47 permits, median 10 days January 2026: 91 permits, median 6 days February 2026: 69 permits, median 6 days March 2026: 99 permits, median 6 days April 2026: 135 permits, median 7 days May 2026: 134 permits, median 8 days June 2026: 92 permits, median 9 days July 2026: 104 permits, median 9 days August 2026: 98 permits, median 7 days September 2026: 124 permits, median 10 days October 2026: 99 permits, median 14 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (135 at most). Dots: median days.

Review paths and the city's published rules

Quoted from City of New Orleans Department of Safety and Permits's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

How the fee is set

Your next step

Planning a roof replacement? Last year three in four were issued within 15 days of application, nine in ten within 35 days.

Sources

City of New Orleans Department of Safety and Permits. License: Creative Commons 1.0 Universal (Public Domain Dedication). The city's BLDS-format permit file, with an applied date and an issue date, sorted by the city's own permit type codes. Historic district approvals, change-of-address and painting permits, which the file also lists under building permits, are not counted.

Used: 16,241 of 47,990. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem