PermitNotebook / Permit processing times / Detroit
How long does it take to get a building permit in Detroit?
Median, November 2025 to October 2026: 49 days for new homes.
Days to permit, by type
| Permit type, as Detroit's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Roof replacement One and two family permits whose description names a reroof and no other work. | 5 days | 0 to 11 days | 27 days | 25.2% | 218 | 25 of 25 |
| Solar panels One and two family permits whose description names solar and no other work. | 32 days | 14 to 63 days | Too few | 0% | 68 | 25 of 25 |
| New home Permits of type "New" on a one or two family use; one whose description names only an ADU counts as an ADU. | 49 days | 36 to 88 days | Too few | 0% | 68 | 25 of 25 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Commercial alteration | 589 | 25 | 13 | 12 | 0 |
- Addition or remodel, not shown: the share issued the day they were applied for went from 13% a year earlier to 61% now, a change in how the city records the application date.
Under 50 permits in the year: decks (12), ADUs (1).
Not separable: electrical permits, plumbing permits, demolitions.
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Roof replacement | 5 days (52) | 10 days(67) | 4 days(53) |
Roof replacement permits by month
Review paths and the city's published rules
Quoted from Detroit Buildings, Safety Engineering and Environmental Department (BSEED)'s own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Residential Building Permit, estimated time to issue.In the residential building permit section, BSEED tells applicants who submit online or at the DRC office to expect the permit about 5 days after applying. "After submitting your application, you can expect to get your permit in about 5 days."
Before you apply
- Pre-Plan Consultation. "If you have Building Code or Trade Code related questions, you can request a Pre-Plan Consultation meeting to answer questions prior to your submission"
- Online project requirements tool.Before applying, applicants can use the city's online tool to check for any special requirements their project may need. "The City of Detroit has an online tool designed to help you know if there are any special requirements that you might need for your project."
Your next step
Planning a new home? Last year three in four were issued within 88 days of application.
Sources
- Building Permits: application date "submitted_date", issue date "issued_date".
Detroit Buildings, Safety Engineering and Environmental Department (BSEED). License: City of Detroit Open Data. Building permits with a submitted date and an issue date; revision permits excluded.
- BSEED publishes building permits only, so there are no electrical or plumbing figures for Detroit.
Used: 10,311 of 12,660. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem