PermitNotebook / Permit processing times / Detroit

How long does it take to get a building permit in Detroit?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 49 days for new homes.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Detroit's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Roof replacement One and two family permits whose description names a reroof and no other work. 5 days 0 to 11 days 27 days 25.2% 218 25 of 25
Solar panels One and two family permits whose description names solar and no other work. 32 days 14 to 63 days Too few 0% 68 25 of 25
New home Permits of type "New" on a one or two family use; one whose description names only an ADU counts as an ADU. 49 days 36 to 88 days Too few 0% 68 25 of 25

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Commercial alteration 589 25 13 12 0

Under 50 permits in the year: decks (12), ADUs (1).

Not separable: electrical permits, plumbing permits, demolitions.

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Roof replacement 5 days (52) 10 days(67) 4 days(53)

Roof replacement permits by month

roof replacements issued each month in Detroit (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 15 permits, median 18 days December 2024: 10 permits, median 22 days January 2025: 5 permits February 2025: 16 permits, median 8 days March 2025: 4 permits April 2025: 0 permits May 2025: 5 permits June 2025: 11 permits, median 15 days July 2025: 2 permits August 2025: 20 permits, median 16 days September 2025: 12 permits, median 15 days October 2025: 35 permits, median 7 days November 2025: 39 permits, median 3 days December 2025: 18 permits, median 7 days January 2026: 17 permits, median 4 days February 2026: 17 permits, median 2 days March 2026: 17 permits, median 5 days April 2026: 19 permits, median 7 days May 2026: 14 permits, median 2 days June 2026: 9 permits July 2026: 16 permits, median 4 days August 2026: 18 permits, median 3 days September 2026: 18 permits, median 3 days October 2026: 16 permits, median 8 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (39 at most). Dots: median days.

Review paths and the city's published rules

Quoted from Detroit Buildings, Safety Engineering and Environmental Department (BSEED)'s own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Before you apply

Your next step

Planning a new home? Last year three in four were issued within 88 days of application.

Sources

Detroit Buildings, Safety Engineering and Environmental Department (BSEED). License: City of Detroit Open Data. Building permits with a submitted date and an issue date; revision permits excluded.

Used: 10,311 of 12,660. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem