How long does it take to get a building permit in Pierce County, Washington?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 24 days for new homes.

These are permits Pierce County issues for its unincorporated areas. Tacoma and the other cities inside the county run their own permit offices and are not included.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Pierce County's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Plumbing Residential plumbing permits. Same day Same day Same day 99.9% 1,093 25 of 25
Roof replacement "Construction Residential" permits whose description names a reroof and no other work. 6 days 4 to 15 days Too few 0% 74 25 of 25
Solar panels "Construction Residential" permits whose description names solar and no other work. 8 days 5 to 19 days Too few 0% 56 49 of 50
New home "Construction Residential" new structures of building type "House/plex", except those whose description names an accessory dwelling unit (counted as ADUs), a cabana, a cabin, or a garage that is not part of a house. By the county's own label: Builder base plan, 771 at 14 days; Other new house, 425 at 98 days. 24 days 12 to 70 days 171 days 0% 1,196 25 of 25

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the county's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Addition or remodel 716 50 47 3 0
Deck 59 25 8 17 0
ADU 75 25 21 4 0
Demolition 112 50 46 3 1
Commercial alteration 116 25 15 10 0

Not separable: electrical permits.

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Plumbing Same day (298) Same day(273) Same day(273)
New home 27 days (225) 48 days(227) 21 days(347)

New home permits by month

new homes issued each month in Pierce County (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 6 permits December 2024: 9 permits January 2025: 41 permits, median 20 days February 2025: 76 permits, median 33 days March 2025: 131 permits, median 33 days April 2025: 111 permits, median 33 days May 2025: 92 permits, median 34 days June 2025: 58 permits, median 35 days July 2025: 129 permits, median 21 days August 2025: 90 permits, median 59 days September 2025: 55 permits, median 69 days October 2025: 82 permits, median 24 days November 2025: 76 permits, median 22 days December 2025: 76 permits, median 45 days January 2026: 105 permits, median 30 days February 2026: 101 permits, median 16 days March 2026: 118 permits, median 27 days April 2026: 128 permits, median 23 days May 2026: 143 permits, median 17 days June 2026: 136 permits, median 22 days July 2026: 88 permits, median 30 days August 2026: 94 permits, median 21 days September 2026: 79 permits, median 27 days October 2026: 52 permits, median 53 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (143 at most). Dots: median days.

Review paths and the county's published rules

Quoted from Pierce County Planning and Public Works's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

How the fee is set

Your next step

Planning a new home? Last year three in four were issued within 70 days of application, nine in ten within 171 days.

Sources

Pierce County Planning and Public Works. License: Pierce County Open Data. Unincorporated Pierce County permits with a submittal date and an issue date. Electrical permits in Washington are issued by the state Department of Labor and Industries, so there is no electrical figure.

Used: 6,150 of 24,322. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem