PermitNotebook / Permit processing times / Pierce County
How long does it take to get a building permit in Pierce County, Washington?
Median, November 2025 to October 2026: 24 days for new homes.
These are permits Pierce County issues for its unincorporated areas. Tacoma and the other cities inside the county run their own permit offices and are not included.
Days to permit, by type
| Permit type, as Pierce County's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Plumbing Residential plumbing permits. | Same day | Same day | Same day | 99.9% | 1,093 | 25 of 25 |
| Roof replacement "Construction Residential" permits whose description names a reroof and no other work. | 6 days | 4 to 15 days | Too few | 0% | 74 | 25 of 25 |
| Solar panels "Construction Residential" permits whose description names solar and no other work. | 8 days | 5 to 19 days | Too few | 0% | 56 | 49 of 50 |
| New home "Construction Residential" new structures of building type "House/plex", except those whose description names an accessory dwelling unit (counted as ADUs), a cabana, a cabin, or a garage that is not part of a house. By the county's own label: Builder base plan, 771 at 14 days; Other new house, 425 at 98 days. | 24 days | 12 to 70 days | 171 days | 0% | 1,196 | 25 of 25 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the county's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Addition or remodel | 716 | 50 | 47 | 3 | 0 |
| Deck | 59 | 25 | 8 | 17 | 0 |
| ADU | 75 | 25 | 21 | 4 | 0 |
| Demolition | 112 | 50 | 46 | 3 | 1 |
| Commercial alteration | 116 | 25 | 15 | 10 | 0 |
Not separable: electrical permits.
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Plumbing | Same day (298) | Same day(273) | Same day(273) |
| New home | 27 days (225) | 48 days(227) | 21 days(347) |
New home permits by month
Review paths and the county's published rules
Quoted from Pierce County Planning and Public Works's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Platted Lot Program. "Permits will be approved and issued within 7-10 business days once fees are paid."
Faster routes
- Plumbing and mechanical permits. "Permits to install or replace residential plumbing and mechanical fixtures are issued immediately after payment. Apply online."
Before you apply
- Start Smart: Pre-Application Services. "Applications that are complete and well prepared at submittal reduce the need for follow-up requests, help reviewers focus on substantive issues, and support a more predictable review timeline."
- Predesigned Project Guides.For a deck, detached carport or similar detached structure, applicants can use the county's predesigned plans instead of hiring an engineer or architect. "Save money and time on your deck, detached carport or similar detached structure project with our Predesigned Project Guides. This feature allows you to choose from predesigned plans with no engineer or architect required."
- Level 1 Pre-Application Screening. "Most Pre-Application Services are optional. However, a Level 1 Pre-Application Screening is required for certain projects, including those with critical area indicators, special site restrictions, or properties served by on-site septic systems or private wells."
After you apply
- Step Three: Pay fees. "Once your fees are paid, you will receive a determination that your application is complete and ready for technical review. The application will be cancelled if fees are not paid within 5 days."
- Extending Applications and Permits: application expiration. "Application review can take over 180 days through the normal process of review. To allow time for a completed review, a 180-day extension is built into the initial expiration date allowing 360 days for approval of the application."
- Inspection Scheduling. "Inspections can be scheduled for the next workday if requested before midnight, however current workload will determine the actual date of inspection."
How the fee is set
- Project valuation (Residential Construction Application). "Building permit fees for most new construction will be determined using quantities from the data table below and current Building Valuation Data tables. Fees for remodels and elements not captured in the BVD tables will be based on valuation provided."
Your next step
Planning a new home? Last year three in four were issued within 70 days of application, nine in ten within 171 days.
Sources
- Permits - Pierce County: application date "submittaldate", issue date "issueddate".
Pierce County Planning and Public Works. License: Pierce County Open Data. Unincorporated Pierce County permits with a submittal date and an issue date. Electrical permits in Washington are issued by the state Department of Labor and Industries, so there is no electrical figure.
Used: 6,150 of 24,322. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem