PermitNotebook / Permit processing times / San Diego County

How long does it take to get a building permit in San Diego County, California?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 173 days for additions and remodels; 408 days for new homes.

These are permits the County of San Diego issues for its unincorporated areas. The City of San Diego and the other incorporated cities run their own permit offices and are not included.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as San Diego County's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Plumbing Accessory plumbing scope codes on residential records (plumbing only, water heater replacement, gas line repairs). By the county's own label: 8010 - ACC - Plumbing Only, 508 at 0 days; 8015 - ACC - (Online) Plumbing - HRA Water Heater R&R, 402 at 0 days; 8016 - ACC - (Online) Plumbing - HRA Gas Line Repairs, 37 at 0 days. Same day Same day Same day 97.9% 950 25 of 25
Solar panels Scope codes 8001 to 8003, residential photovoltaic systems. By the county's own label: 8002 - REN - Solar Photovoltaic Roof Mount Residential - Online, 2,466 at 1 day; 8003 - REN - Solar Photovoltaic Ground Mount Residential, 106 at 0 days; 8001 - REN - Solar Photovoltaic Roof Mount Residential - In Person, 37 at 0 days. 1 day 0 to 2 days 4 days 46.7% 2,609 25 of 25
Addition or remodel Scope codes 4340, "Addition/Alter To SFD/Duplex", and 3312, "Major Remodel" (a 4340 that also adds an attached ADU stays here, because the record does not say so). 173 days 82 to 301 days 460 days 7.3% 178 25 of 25
ADU Scope codes 1015 and 1016, accessory and junior accessory dwelling units. 216 days 125 to 353 days 544 days 0% 278 25 of 25
New home Scope code 1010, "New Primary Residential Structure" (manufactured homes and apartment buildings excluded). 408 days 274 to 603 days 866 days 0% 135 48 of 50

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the county's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Electrical 1,218 25 20 5 0
Commercial alteration 74 25 20 5 0

Under 50 permits in the year: demolitions (22).

Not separable: decks, roof replacements.

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Plumbing Same day (272) Same day(233) Same day(256)
Solar panels 1 day (608) 1 day(991) Same day(683)
Addition or remodel 144 days (36) 144 days(68) 196 days(47)
ADU 180 days (54) 273 days(78) 242 days(89)

Addition or remodel permits by month

additions and remodels issued each month in San Diego County (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 10 permits, median 131 days December 2024: 14 permits, median 211 days January 2025: 16 permits, median 162 days February 2025: 16 permits, median 202 days March 2025: 14 permits, median 210 days April 2025: 18 permits, median 237 days May 2025: 13 permits, median 190 days June 2025: 19 permits, median 199 days July 2025: 14 permits, median 177 days August 2025: 17 permits, median 163 days September 2025: 29 permits, median 143 days October 2025: 22 permits, median 116 days November 2025: 14 permits, median 154 days December 2025: 13 permits, median 237 days January 2026: 16 permits, median 204 days February 2026: 15 permits, median 175 days March 2026: 15 permits, median 161 days April 2026: 17 permits, median 266 days May 2026: 20 permits, median 166 days June 2026: 17 permits, median 138 days July 2026: 15 permits, median 141 days August 2026: 12 permits, median 148 days September 2026: 10 permits, median 139 days October 2026: 14 permits, median 167 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (29 at most). Dots: median days.

Review paths and the county's published rules

The County records whether each building permit was created online; many small permits (solar, panel upgrades, water heaters) can be applied for and issued online.

How it was filed in San Diego County, permits issued November 2025 to October 2026
How it was filed Median 3 in 4 within Permits
Applied online Same day 1 day 2,908
Applied in person or through plan check 2 days 227 days 1,264

Each path carries different kinds of projects, so part of each gap is the work itself.

Quoted from County of San Diego Planning & Development Services's own pages, read 16 Nov 2026; each name links to the page quoted.

Faster routes

Before you apply

After you apply

Your next step

Planning an addition or remodel? Last year three in four were issued within 301 days of application, nine in ten within 460 days.

Sources

County of San Diego Planning & Development Services. License: County of San Diego open data. Unincorporated San Diego County building permits with an open date and an issue date.

Used: 11,756 of 22,645. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem