PermitNotebook / Permit processing times / San Diego County
How long does it take to get a building permit in San Diego County, California?
Median, November 2025 to October 2026: 173 days for additions and remodels; 408 days for new homes.
These are permits the County of San Diego issues for its unincorporated areas. The City of San Diego and the other incorporated cities run their own permit offices and are not included.
Days to permit, by type
| Permit type, as San Diego County's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Plumbing Accessory plumbing scope codes on residential records (plumbing only, water heater replacement, gas line repairs). By the county's own label: 8010 - ACC - Plumbing Only, 508 at 0 days; 8015 - ACC - (Online) Plumbing - HRA Water Heater R&R, 402 at 0 days; 8016 - ACC - (Online) Plumbing - HRA Gas Line Repairs, 37 at 0 days. | Same day | Same day | Same day | 97.9% | 950 | 25 of 25 |
| Solar panels Scope codes 8001 to 8003, residential photovoltaic systems. By the county's own label: 8002 - REN - Solar Photovoltaic Roof Mount Residential - Online, 2,466 at 1 day; 8003 - REN - Solar Photovoltaic Ground Mount Residential, 106 at 0 days; 8001 - REN - Solar Photovoltaic Roof Mount Residential - In Person, 37 at 0 days. | 1 day | 0 to 2 days | 4 days | 46.7% | 2,609 | 25 of 25 |
| Addition or remodel Scope codes 4340, "Addition/Alter To SFD/Duplex", and 3312, "Major Remodel" (a 4340 that also adds an attached ADU stays here, because the record does not say so). | 173 days | 82 to 301 days | 460 days | 7.3% | 178 | 25 of 25 |
| ADU Scope codes 1015 and 1016, accessory and junior accessory dwelling units. | 216 days | 125 to 353 days | 544 days | 0% | 278 | 25 of 25 |
| New home Scope code 1010, "New Primary Residential Structure" (manufactured homes and apartment buildings excluded). | 408 days | 274 to 603 days | 866 days | 0% | 135 | 48 of 50 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the county's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Electrical | 1,218 | 25 | 20 | 5 | 0 |
| Commercial alteration | 74 | 25 | 20 | 5 | 0 |
Under 50 permits in the year: demolitions (22).
Not separable: decks, roof replacements.
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Plumbing | Same day (272) | Same day(233) | Same day(256) |
| Solar panels | 1 day (608) | 1 day(991) | Same day(683) |
| Addition or remodel | 144 days (36) | 144 days(68) | 196 days(47) |
| ADU | 180 days (54) | 273 days(78) | 242 days(89) |
Addition or remodel permits by month
Review paths and the county's published rules
The County records whether each building permit was created online; many small permits (solar, panel upgrades, water heaters) can be applied for and issued online.
| How it was filed | Median | 3 in 4 within | Permits |
|---|---|---|---|
| Applied online | Same day | 1 day | 2,908 |
| Applied in person or through plan check | 2 days | 227 days | 1,264 |
Each path carries different kinds of projects, so part of each gap is the work itself.
Quoted from County of San Diego Planning & Development Services's own pages, read 16 Nov 2026; each name links to the page quoted.
Faster routes
- Instant Permit (online residential building permits).Through the county's online services, applicants can apply for a minor residential permit or get an Instant Permit; listed online types include window replacement, roof-mounted solar PV, energy storage, EV chargers, water heater replacement and gas line repair. "Apply for a minor residential permit or get an Instant Permit Online"
- Self-Certification Program. "The Self-Certification Program eliminates plan review by allowing a registered professional to take responsibility for and certify a project's compliance with building codes, standards, and ordinances. Depending on the scope of the project, permits can be issued within one to five business days."
- Expedited Plan Check Request (PDS 617).An owner or agent in unincorporated San Diego County can request expedited plan check for added hourly fees: $225 for the engineer's review and $182 for a planner's review if needed. "I request expedited processing of these plans through the plan check process. I am aware of and agree to additional fees, being $225.00 an hour for the engineer’s review and $182.00 an hour for planner’s review (if required)."
- Green Building Incentive Program. "Eligible participants can get faster plan checks and pay lower building permit fees."
Before you apply
- Conditions of Approval. "We recommend you review your Conditions of Approval early. Some items (for example, Fire District Approval, Flood Control, Septic Review, Driveway Review, etc.) may take longer."
After you apply
- Scope changes between review cycles.Changing a county project's scope can change its Conditions of Approval, so PDS asks to hear about scope changes between review cycles. "If you change your permit’s scope, we may need to change your Conditions of Approval. To avoid delays in getting your permit, tell us about any scope changes in between review cycles."
- Building Permit Expiration and Renewal (progress inspections). "Once the work has started and the first required inspection has been passed, the permittee must show that the work is progressing by passing a valid inspection at least every 180 days (six months)."
- Automated inspection hotline. "To schedule an inspection on an open, unexpired permit, you can call the automated inspection hotline at 800-351-2551 (or 858-694-8971). You must have your full twelve-digit permit number and the number for the inspection type you wish to schedule."
Your next step
Planning an addition or remodel? Last year three in four were issued within 301 days of application, nine in ten within 460 days.
Sources
- Building Permits: application date "open_date", issue date "issued_date".
County of San Diego Planning & Development Services. License: County of San Diego open data. Unincorporated San Diego County building permits with an open date and an issue date.
Used: 11,756 of 22,645. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem