PermitNotebook / Permit processing times / Chicago

How long does it take to get a building permit in Chicago?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 1 day for electrical permits; 1 day for roof replacements; 3 days for plumbing permits.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Chicago's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Electrical Express Permit Program "Electrical Work" permits, homes and businesses together (the portal does not separate them). 1 day 0 to 6 days 17 days 46.5% 5,613 25 of 25
Roof replacement Express Permit Program "Reroofing" permits. 1 day 0 to 4 days 12 days 47.6% 1,305 25 of 25
Plumbing Express Permit Program "Plumbing Work" permits, homes and businesses together. 3 days 1 to 8 days 18 days 18.1% 673 25 of 25
Solar panels Express Permit Program "Small-Scale Solar PV System" permits. 9 days 6 to 15 days 26 days 2% 1,802 25 of 25

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
New home 133 25 10 15 0
Addition or remodel 2,383 25 19 6 0
ADU 73 25 22 3 0
Commercial alteration 1,199 25 22 3 0

Under 50 permits in the year: decks (45).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Electrical 1 day (1,488) 1 day(1,676) 1 day(1,348)
Roof replacement 1 day (489) Same day(373) 1 day(273)
Plumbing 4 days (179) 4 days(182) 3 days(182)
Solar panels 8 days (641) 5 days(559) 7 days(294)

Roof replacement permits by month

roof replacements issued each month in Chicago (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 58 permits, median 3 days December 2024: 35 permits, median 0 days January 2025: 34 permits, median 1 day February 2025: 25 permits, median 1 day March 2025: 74 permits, median 1 day April 2025: 115 permits, median 1 day May 2025: 106 permits, median 0 days June 2025: 98 permits, median 1 day July 2025: 112 permits, median 0 days August 2025: 114 permits, median 0 days September 2025: 120 permits, median 0 days October 2025: 139 permits, median 1 day November 2025: 84 permits, median 3 days December 2025: 35 permits, median 1 day January 2026: 32 permits, median 0 days February 2026: 69 permits, median 1 day March 2026: 78 permits, median 1 day April 2026: 126 permits, median 0 days May 2026: 136 permits, median 0 days June 2026: 137 permits, median 0 days July 2026: 119 permits, median 0 days August 2026: 175 permits, median 0 days September 2026: 157 permits, median 1 day October 2026: 157 permits, median 1 day Nov 2024May 2025Nov 2025May 2026
Bars: permits (175 at most). Dots: median days.

Review paths and the city's published rules

Quoted from Chicago Department of Buildings's own pages, read 16 Nov 2026; each name links to the page quoted.

Faster routes

Your next step

Planning a roof replacement? Last year three in four were issued within 4 days of application, nine in ten within 12 days.

Sources

Chicago Department of Buildings. License: City of Chicago Data Portal Terms of Use. Permits with an application start date and an issue date. The portal excludes permits voided or revoked after issuance. "Reinstate revoked permit" records are not counted.

Used: 27,778 of 64,316. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem