PermitNotebook / Permit processing times / Chicago
How long does it take to get a building permit in Chicago?
Median, November 2025 to October 2026: 1 day for electrical permits; 1 day for roof replacements; 3 days for plumbing permits.
Days to permit, by type
| Permit type, as Chicago's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Electrical Express Permit Program "Electrical Work" permits, homes and businesses together (the portal does not separate them). | 1 day | 0 to 6 days | 17 days | 46.5% | 5,613 | 25 of 25 |
| Roof replacement Express Permit Program "Reroofing" permits. | 1 day | 0 to 4 days | 12 days | 47.6% | 1,305 | 25 of 25 |
| Plumbing Express Permit Program "Plumbing Work" permits, homes and businesses together. | 3 days | 1 to 8 days | 18 days | 18.1% | 673 | 25 of 25 |
| Solar panels Express Permit Program "Small-Scale Solar PV System" permits. | 9 days | 6 to 15 days | 26 days | 2% | 1,802 | 25 of 25 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| New home | 133 | 25 | 10 | 15 | 0 |
| Addition or remodel | 2,383 | 25 | 19 | 6 | 0 |
| ADU | 73 | 25 | 22 | 3 | 0 |
| Commercial alteration | 1,199 | 25 | 22 | 3 | 0 |
- Demolition, not shown: the share issued the day they were applied for went from 97% a year earlier to 2% now, a change in how the city records the application date.
Under 50 permits in the year: decks (45).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Electrical | 1 day (1,488) | 1 day(1,676) | 1 day(1,348) |
| Roof replacement | 1 day (489) | Same day(373) | 1 day(273) |
| Plumbing | 4 days (179) | 4 days(182) | 3 days(182) |
| Solar panels | 8 days (641) | 5 days(559) | 7 days(294) |
Roof replacement permits by month
Review paths and the city's published rules
Quoted from Chicago Department of Buildings's own pages, read 16 Nov 2026; each name links to the page quoted.
Faster routes
- Express Permit Program. "The Express Permit Program includes a fully web-enabled customer platform allowing users to apply for building permits for most types of building repairs and administrative changes to issued permits, as well as a limited range of small improvement projects."
- Self-Certified Permit Application Program (Self-Cert). "After zoning is approved, self-certified permit applications are typically issued a permit within 10 business days if all contractor licenses are valid and there are no building violations or stop work orders on the property."
Your next step
Planning a roof replacement? Last year three in four were issued within 4 days of application, nine in ten within 12 days.
Sources
- Building Permits: application date "application_start_date", issue date "issue_date".
Chicago Department of Buildings. License: City of Chicago Data Portal Terms of Use. Permits with an application start date and an issue date. The portal excludes permits voided or revoked after issuance. "Reinstate revoked permit" records are not counted.
- Chicago's Express Permit Program covers small jobs (reroofing, electrical, plumbing, solar, porches) and most of them issue within days; anything with plans goes through Standard Plan Review or Self Certification.
Used: 27,778 of 64,316. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem