PermitNotebook / Permit processing times / Austin
How long does it take to get a building permit in Austin?
Median, November 2025 to October 2026: 52 days for new homes.
Days to permit, by type
| Permit type, as Austin's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Roof replacement Residential building permits of the same classes whose description names a reroof and no other work. | 3 days | 0 to 7 days | Too few | 26.3% | 99 | 25 of 25 |
| Electrical Residential electrical permits other than work class "New" sub-permits of new construction, excluding solar; Austin's "Homebuilder Loop" temporary-power permits for new homes are included. By the city's own label: Electrical Permit: Homebuilder Loop, 2,281 at 5 days; Electrical Permit: Repair, 1,853 at 5 days; Electrical Permit: Upgrade, 1,624 at 5 days; Electrical Permit: Addition and Remodel, 1,004 at 119 days; Electrical Permit: Auxiliary Power, 633 at 14 days. | 6 days | 3 to 17 days | 90 days | 2% | 7,836 | 25 of 25 |
| Demolition Residential building permits of the demolition classes, R- 645 to R- 649; R- 649 is the demolition of garages and other accessory buildings, counted here and shown as its own kind. By the city's own label: R- 645 Demolition One Family Homes, 453 at 21 days; R- 649 Demolition All Other Bldgs Res, 236 at 21 days. | 21 days | 13 to 51 days | 140 days | 0% | 711 | 25 of 25 |
| New home Residential building permits of class "R- 101 Single Family Houses" or "R- 103 Two Family Bldgs" with work class "New". By the city's own label: R- 101 Single Family Houses, 2,065 at 49 days; R- 103 Two Family Bldgs, 162 at 117 days. | 52 days | 26 to 115 days | 263 days | 0% | 2,227 | 48 of 50 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| Addition or remodel | 3,792 | 50 | 47 | 3 | 0 |
| Deck | 133 | 25 | 6 | 19 | 0 |
| Solar panels | 556 | 25 | 21 | 4 | 0 |
| Plumbing | 8,535 | 50 | 45 | 4 | 1 |
| Commercial alteration | 2,890 | 25 | 14 | 10 | 1 |
Under 50 permits in the year: ADUs (8).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Demolition | 22 days (175) | 21 days(169) | 15 days(182) |
| New home | 42 days (537) | 85 days(394) | 47 days(572) |
Electrical: no then-and-now row, because the share of "Electrical Permit: Auxiliary Power" permits moved from 1% a year earlier to 23% now, so the comparison would measure the mix, not the wait.
New home permits by month
Review paths and the city's published rules
Quoted from City of Austin Development Services Department's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- Small Project application (commercial). "As of July 15, 2026, the 7 Day checklist is no longer necessary when submitting the Commercial Building Application. The Small Project application is a short plan review option for projects that are simple in scope and can be reviewed within five business days."
- When residential review time starts (Permitting Process).Austin's residential review clock starts only once you pay the invoice. "Once you pay the invoice, we will distribute your project for review, and your review time will start."
Faster routes
- Residential Express Building Permits (Minor Repairs). "Residential Express Building Permits (Minor Repairs) are for specific, small projects for residential properties (single-family, duplex, or two-family houses and/or accessory buildings on one lot). The turnaround time to issue most Express Permits is one business day."
- Quick Turnaround (QT) Application. "As of July 15, 2026, the QT Checklist is no longer necessary when submitting the Commercial Building Application. The Quick Turnaround Application is a faster plan review option for simple projects. When a project qualifies, the plan review can be completed within one business day."
- Expedited Residential Plan Review eligibility.Most Austin home projects can use Expedited review, but projects that need a drainage review do not qualify. "Most residential projects are eligible through Expedited; however, projects requiring a drainage review (less than 10 ft. within a driveway) do not qualify."
Before you apply
- Preliminary Plan Review Meeting (PPR). "If an owner and/or the owner’s agents wish to meet with staff to discuss preliminary design and/or construction issues, request a Preliminary Plan Review Meeting (PPR) at any time before submitting a permit application to Residential Plan Review."
- Acknowledgment of Expired Permits. "If your property has expired permits, complete the Acknowledgment of Expired Permits and submit it with your application."
After you apply
- Formal update submittal.Austin refuses partial or informal correction submittals, and any comment left unresolved brings another rejection and may add fees. "Partial or informal updates will not be accepted for review. Any unresolved comments will result in a rejection and may generate additional fees."
- Inspection timing after scheduling (Building Inspections). "Inspections are usually performed 24 hours after scheduling, but an inspector’s workload can delay a scheduled inspection until the next business day or 48 hours after scheduling."
Your next step
Planning a new home? Last year three in four were issued within 115 days of application, nine in ten within 263 days.
Sources
- Issued Construction Permits: application date "applieddate", issue date "issue_date".
City of Austin Development Services Department. License: Public Domain (City of Austin Open Data Terms of Use). Issued permits with an applied date.
- Austin files second dwelling units on a lot as R- 101 house permits. Those whose description says ADU are counted as ADUs; garage apartments and other second units described another way stay in new homes (about 1% to 3% of them by their wording).
Used: 52,942 of 112,480. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem