How long does it take to get a building permit in Austin?

By Mario Bailey Last checked · 1 official source

Median, November 2025 to October 2026: 52 days for new homes.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as Austin's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Roof replacement Residential building permits of the same classes whose description names a reroof and no other work. 3 days 0 to 7 days Too few 26.3% 99 25 of 25
Electrical Residential electrical permits other than work class "New" sub-permits of new construction, excluding solar; Austin's "Homebuilder Loop" temporary-power permits for new homes are included. By the city's own label: Electrical Permit: Homebuilder Loop, 2,281 at 5 days; Electrical Permit: Repair, 1,853 at 5 days; Electrical Permit: Upgrade, 1,624 at 5 days; Electrical Permit: Addition and Remodel, 1,004 at 119 days; Electrical Permit: Auxiliary Power, 633 at 14 days. 6 days 3 to 17 days 90 days 2% 7,836 25 of 25
Demolition Residential building permits of the demolition classes, R- 645 to R- 649; R- 649 is the demolition of garages and other accessory buildings, counted here and shown as its own kind. By the city's own label: R- 645 Demolition One Family Homes, 453 at 21 days; R- 649 Demolition All Other Bldgs Res, 236 at 21 days. 21 days 13 to 51 days 140 days 0% 711 25 of 25
New home Residential building permits of class "R- 101 Single Family Houses" or "R- 103 Two Family Bldgs" with work class "New". By the city's own label: R- 101 Single Family Houses, 2,065 at 49 days; R- 103 Two Family Bldgs, 162 at 117 days. 52 days 26 to 115 days 263 days 0% 2,227 48 of 50

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
Addition or remodel 3,792 50 47 3 0
Deck 133 25 6 19 0
Solar panels 556 25 21 4 0
Plumbing 8,535 50 45 4 1
Commercial alteration 2,890 25 14 10 1

Under 50 permits in the year: ADUs (8).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Demolition 22 days (175) 21 days(169) 15 days(182)
New home 42 days (537) 85 days(394) 47 days(572)

Electrical: no then-and-now row, because the share of "Electrical Permit: Auxiliary Power" permits moved from 1% a year earlier to 23% now, so the comparison would measure the mix, not the wait.

New home permits by month

new homes issued each month in Austin (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 162 permits, median 49 days December 2024: 151 permits, median 43 days January 2025: 138 permits, median 40 days February 2025: 179 permits, median 61 days March 2025: 356 permits, median 28 days April 2025: 312 permits, median 28 days May 2025: 212 permits, median 52 days June 2025: 223 permits, median 54 days July 2025: 241 permits, median 52 days August 2025: 129 permits, median 64 days September 2025: 127 permits, median 79 days October 2025: 138 permits, median 100 days November 2025: 120 permits, median 79 days December 2025: 157 permits, median 89 days January 2026: 168 permits, median 92 days February 2026: 154 permits, median 69 days March 2026: 213 permits, median 44 days April 2026: 205 permits, median 34 days May 2026: 206 permits, median 42 days June 2026: 239 permits, median 49 days July 2026: 228 permits, median 56 days August 2026: 177 permits, median 40 days September 2026: 166 permits, median 38 days October 2026: 194 permits, median 56 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (356 at most). Dots: median days.

Review paths and the city's published rules

Quoted from City of Austin Development Services Department's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

Your next step

Planning a new home? Last year three in four were issued within 115 days of application, nine in ten within 263 days.