PermitNotebook / Permit processing times / San Diego
How long does it take to get a building permit in San Diego?
Median, November 2025 to October 2026: 74 days for additions and remodels.
Days to permit, by type
| Permit type, as San Diego's records define it | Median | Middle half (25th to 75th percentile) | 9 in 10 within | Same day | Permits | Records read (are this work) |
|---|---|---|---|---|---|---|
| Plumbing Plumbing approvals on 1 or 2 family homes, and no-plan residential approvals whose scope names plumbing. | Same day | Same day | 1 day | 87.8% | 2,699 | 25 of 25 |
| Addition or remodel Approvals coded "Add/Alt 1 or 2 Fam, No Chg DU", unless the scope names only solar, a deck or a reroof. | 74 days | 21 to 209 days | 343 days | 7% | 2,226 | 49 of 49 |
| Demolition Demolition approvals for one and two family houses. | 266 days | 183 to 432 days | 610 days | 0% | 116 | 49 of 50 |
| ADU Approvals coded "Add/Alt Companion Unit/Acc Apt", San Diego's code for an ADU. | 274 days | 162 to 459 days | 709 days | 0% | 1,376 | 25 of 25 |
Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.
| Permit type | Permits | Records read | Are this work | Other work | Could not be checked |
|---|---|---|---|---|---|
| New home | 237 | 25 | 22 | 3 | 0 |
| Solar panels | 4,726 | 25 | 21 | 4 | 0 |
| Electrical | 2,418 | 50 | 46 | 4 | 0 |
| Commercial alteration | 1,199 | 25 | 19 | 6 | 0 |
Under 50 permits in the year: decks (39), roof replacements (21).
Then and now
| Permit type | August to October 2026 | August to October 2025 | February to April 2026 |
|---|---|---|---|
| Plumbing | Same day (713) | Same day(595) | Same day(675) |
| Addition or remodel | 64 days (583) | 90 days(550) | 83 days(578) |
| ADU | 258 days (322) | 266 days(367) | 274 days(375) |
Addition or remodel permits by month
Review paths and the city's published rules
Quoted from City of San Diego Development Services Department's own pages, read 16 Nov 2026; each name links to the page quoted.
Published review times
- First Reviews (Permit Processing Timeline).San Diego's first-review clock starts only when the project is deemed complete, which happens once the project set-up fees are paid. "First Reviews represent the average number of days it takes to initially review a project after it has been deemed complete. Projects are deemed complete once the project set-up fees have been paid."
Faster routes
- Rapid Review. "Rapid Review, formerly known as Over-the-Counter review, is determined at the time of submittal based on the proposed scope of the project. Eligible projects are those that are minor in scope."
- Express Plan Check.Most projects and review disciplines can buy a faster Express Plan Check for an added fee, and that fee covers up to two rechecks. "Express Plan Check is available for most projects and disciplines for additional fees. The Express Plan Check fee includes up to two rechecks."
- Simple Permits. "Licensed contractors will receive the permit as soon as they complete and submit the application and pay the invoice. Homeowners will receive their Simple Permit normally within two business days after the completed Owner-Builder Verification Form DS-3042 is submitted."
- Residential Rooftop-Mounted Solar PV Permit.Home rooftop solar in San Diego that follows the IB-301 template and meets the listed limits gets a self-issued permit with no plan review. "For single-family, duplex, or townhouse roof installations designed per the template in Information Bulletin (IB) 301, the permit will be self-issued with no plan review, provided the following conditions are met:"
Before you apply
- Single Discipline Preliminary Review. "A single-discipline review takes 20 business days from the time the application is deemed complete, and the fees are paid."
After you apply
- Cycle issues and resubmittals (What happens after I submit my permit application?).In San Diego, corrections can be uploaded only after every review discipline finishes its cycle, even if one reviewer is done early. "Even if one reviewer finishes early, you will not be able to upload responses or corrected plans until all review disciplines have completed their cycle."
- Standard Inspections scheduling. "Standard inspections must be scheduled at least one day in advance."
How the fee is set
- Express Plan Check fee. "Express is available for most disciplines upon payment of an Express Plan Check administrative fee plus 1.5 times the regular plan check fee."
Your next step
Planning an addition or remodel? Last year three in four were issued within 209 days of application, nine in ten within 343 days.
Sources
- Development Permits, set 2 (closed projects): application date "APPROVAL_CREATE_DATE", issue date "APPROVAL_ISSUE_DATE".
- Development Permits, set 2 (active projects): application date "APPROVAL_CREATE_DATE", issue date "APPROVAL_ISSUE_DATE".
City of San Diego Development Services Department. License: City of San Diego open data portal terms. Approvals in the city's Development Permits (set 2) files, active and closed, with a create date and an issue date. "Final Only" approvals, which re-issue an expired approval so its work can be finaled, are not counted in any type.
Used: 30,831 of 112,013. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem