PermitNotebook / Permit processing times / San Diego

How long does it take to get a building permit in San Diego?

By Mario Bailey Last checked · 2 official sources

Median, November 2025 to October 2026: 74 days for additions and remodels.

Days to permit, by type

Days to permit by type, November 2025 to October 2026
Permit type, as San Diego's records define it Median Middle half (25th to 75th percentile) 9 in 10 within Same day Permits Records read (are this work)
Plumbing Plumbing approvals on 1 or 2 family homes, and no-plan residential approvals whose scope names plumbing. Same day Same day 1 day 87.8% 2,699 25 of 25
Addition or remodel Approvals coded "Add/Alt 1 or 2 Fam, No Chg DU", unless the scope names only solar, a deck or a reroof. 74 days 21 to 209 days 343 days 7% 2,226 49 of 49
Demolition Demolition approvals for one and two family houses. 266 days 183 to 432 days 610 days 0% 116 49 of 50
ADU Approvals coded "Add/Alt Companion Unit/Acc Apt", San Diego's code for an ADU. 274 days 162 to 459 days 709 days 0% 1,376 25 of 25

Records read: a random sample of each type's permits from the 12 months, each read against its own description of the work or its page on the city's permit portal (read 17 Nov 2026). A type is shown only when the count gives 95% confidence that at least 85% of its permits are the work named (25 of 25, or 48 of 50); how the check works.

Not shown: the reading of a random sample of their records has not reached the bar
Permit type Permits Records read Are this work Other work Could not be checked
New home 237 25 22 3 0
Solar panels 4,726 25 21 4 0
Electrical 2,418 50 46 4 0
Commercial alteration 1,199 25 19 6 0

Under 50 permits in the year: decks (39), roof replacements (21).

Then and now

Median days, three-month windows
Permit type August to October 2026 August to October 2025 February to April 2026
Plumbing Same day (713) Same day(595) Same day(675)
Addition or remodel 64 days (583) 90 days(550) 83 days(578)
ADU 258 days (322) 266 days(367) 274 days(375)

Addition or remodel permits by month

additions and remodels issued each month in San Diego (bars) and their median days to permit (dots), November 2024 to October 2026 November 2024: 149 permits, median 86 days December 2024: 137 permits, median 56 days January 2025: 162 permits, median 68 days February 2025: 150 permits, median 65 days March 2025: 183 permits, median 74 days April 2025: 211 permits, median 91 days May 2025: 160 permits, median 82 days June 2025: 168 permits, median 68 days July 2025: 178 permits, median 83 days August 2025: 171 permits, median 71 days September 2025: 148 permits, median 106 days October 2025: 231 permits, median 92 days November 2025: 129 permits, median 76 days December 2025: 139 permits, median 76 days January 2026: 188 permits, median 106 days February 2026: 165 permits, median 112 days March 2026: 206 permits, median 63 days April 2026: 207 permits, median 66 days May 2026: 188 permits, median 60 days June 2026: 174 permits, median 98 days July 2026: 247 permits, median 61 days August 2026: 195 permits, median 60 days September 2026: 216 permits, median 65 days October 2026: 172 permits, median 59 days Nov 2024May 2025Nov 2025May 2026
Bars: permits (247 at most). Dots: median days.

Review paths and the city's published rules

Quoted from City of San Diego Development Services Department's own pages, read 16 Nov 2026; each name links to the page quoted.

Published review times

Faster routes

Before you apply

After you apply

How the fee is set

Your next step

Planning an addition or remodel? Last year three in four were issued within 209 days of application, nine in ten within 343 days.

Sources

City of San Diego Development Services Department. License: City of San Diego open data portal terms. Approvals in the city's Development Permits (set 2) files, active and closed, with a create date and an issue date. "Final Only" approvals, which re-issue an expired approval so its work can be finaled, are not counted in any type.

Used: 30,831 of 112,013. Pending and withdrawn applications are not counted. Newest: . Methodology · Explorer · CSV · Report a problem