Permit required

Quick answer

An electrical permit is required in Henrico County for new wiring, service changes, and the initial installation or replacement of electrical fixtures and equipment such as lighting fixtures, hard-wired smoke alarms, and electric water heaters, dryers, or stoves, per the county's own Permit Center guidance. Exemptions are narrow, covering items such as wiring under 50 volts and like-for-like replacement of general-use switches, standard receptacles, light fixtures, and ceiling fans.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Henrico County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

For new wiring, service changes, and installation or replacement of electrical fixtures and equipment

What electrical permit costs in Henrico County

Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; a new-dwelling trade permit is a $100 flat fee plus $2 state levy ($102 total), per Henrico's residential trade permit fee schedule.

Official fee schedule

How Henrico County compares in Virginia

No Virginia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlington CountyPermit requiredFees per FY27 ISD fee schedule;
Chesterfield CountyPermit required$171 for a new single-family dwelling;
Fairfax CountyPermit requiredResidential addition or alteration electrical work starts at the $141.75 base...
Fauquier CountyIt dependsA single-trade electrical permit is $84.15 including the technology fee at th...
Henrico Countythis pagePermit requiredExisting-dwelling trade permit fee applies: $100 for the first $5,000 of labo...
Loudoun CountyPermit requiredBase fee for adding, replacing or relocating fixtures, receptacles or circuit...
Orange CountyPermit requiredBilled under the residential Trades category at $0.15 per square foot with a...

How to apply in Henrico County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Henrico County Department of Building Construction and Inspections sets the exact checklist for Henrico County.

Where to apply in Henrico County:

Henrico County Department of Building Construction and Inspections

  • 4301 East Parham Road, Henrico, VA 23228
  • Phone: (804) 501-4360

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Henrico County permit portal or by phone at (804) 501-4360.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a electrical permit in Henrico County?
An electrical permit is required in Henrico County for new wiring, service changes, and the initial installation or replacement of electrical fixtures and equipment such as lighting fixtures, hard-wired smoke alarms, and electric water heaters, dryers, or stoves, per the county's own Permit Center guidance. Exemptions are narrow, covering items such as wiring under 50 volts and like-for-like replacement of general-use switches, standard receptacles, light fixtures, and ceiling fans. Always confirm with the Henrico County Department of Building Construction and Inspections before starting.
How much does a electrical permit cost in Henrico County?
Existing-dwelling trade permit fee applies: $100 for the first $5,000 of labor and materials cost, plus $6 per additional $1,000 or fraction thereof, plus a 2% state levy; a new-dwelling trade permit is a $100 flat fee plus $2 state levy ($102 total), per Henrico's residential trade permit fee schedule. See the official fee schedule for current amounts.
Where do you apply for a electrical permit in Henrico County?
You can apply through the Henrico County permit portal or contact the Henrico County Department of Building Construction and Inspections directly. The links are listed on this page.
Can a homeowner pull a electrical permit themselves in Henrico County?
Under Virginia law (Va. Code 54.1-1101(A); 13VAC5-63-80 (USBC Sections 108.3, 108.4)): Yes. Va. Code 54.1-1101(A) exempts any person who performs or supervises construction, removal, repair, or improvement of no more than one primary residence owned by them and for their own use during any 24-month period. The exemption covers the whole licensing chapter, including tradesman licensing for electrical, plumbing, and HVAC, so it reaches trade work on the owner's own primary residence. Under the USBC the permit applicant may be the owner or the owner's agent, and an applicant may file a written statement that they are not subject to licensure instead of proof of license. Limits: one primary residence per 24 months, for the owner's own use; rental and investment property work is not covered. Confirm how Henrico County applies this before you apply.

From the Library

What else needs a permit in Henrico County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedFalls under the existing-dwelling building permit formula of $100 for the first $5,000...
Deck PermitPermit requiredNot specifiedExisting-dwelling addition or alteration permit fee applies: $100 for the first $5,000...
EV Charger PermitPermit requiredNot specifiedNo EV-specific fee;
Fence PermitIt dependsfences 7 feet or less in height that do not serve as a swimming pool barrier are exempt; taller fences and any fence serving as a pool barrier require a building permitFences up to 7 feet that are not a pool barrier need no permit;
HVAC PermitPermit requiredNot specifiedExisting-dwelling trade permit fee applies: $100 for the first $5,000 of labor and mate...
Patio PermitIt dependson-grade concrete or paver patios are exempt; a permit is required for a patio cover, roofed patio structure, or an addition built over or attached to the patioNo permit fee;
Plumbing PermitPermit requiredNot specifiedExisting-dwelling trade permit fee applies: $100 for the first $5,000 of labor and mate...
Pool PermitIt dependspools, hot tubs, or spas with a surface area greater than 150 sq ft, more than 5,000 gallons, or 24 inches or more deep require a building permit; smaller and shallower pools are exemptExisting-dwelling addition or alteration permit fee applies to swimming pools requiring...
Roof Replacement PermitIt dependslike-for-like replacement of roof covering on one- and two-family homes is exempt in areas with nominal design wind speed of 100 mph or less; a permit is required when more than 256 sq ft of roof sheathing (decking) is repaired or replaced and may be required in historic districts or flood hazard areasRoof covering replacement is exempt in unlimited amounts so typical reroofing needs no...
Shed PermitIt dependssheds and playhouses over 256 sq ft or more than one story require a building permit; 256 sq ft or less and only one story is exemptSheds of 256 sq ft or less and one story need no permit;
Solar PermitPermit requiredNot specifiedResidential solar needs only an electrical permit with no separate building permit per...
Water Heater PermitIt dependsNot specifiedElectric, gas and oil water heaters need a mechanical permit for new or replacement ins...

Electrical Permit in other Virginia localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Henrico County Department of Building Construction and Inspections. Rules change; confirm before you build. How we verify.