Permit required

Yes, a permit is required

For all new wiring and service work

From an official source Verified

Issued byLoudoun County Department of Building and Development

By Mario Bailey, verified against official sources

Quick answer

An electrical permit is required in Loudoun County for new wiring, outlets, circuits, lighting, and panel upgrades. Contractors must hold a master electrical license and a valid Loudoun County business license. Permit applications are submitted through the LandMARC online portal. The county also requires plan review for some residential fuel gas permits as of October 2025.

Who is pulling this permit?

Hire it out

Sponsored

Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.

Compare electrician quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

For all new wiring and service work

What an electrical permit costs in Loudoun County

Line item
electrical permitBy formulaBase fee for adding, replacing or relocating fixtures, receptacles or circuits in a 1 or 2 family dwelling is $70; service equipment upgrades are $70 for 0-400 amps or $100 above 400 amps, per the July 2022 fee schedule.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How Loudoun County compares in Virginia

No Virginia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlington CountyPermit requiredFees per FY27 ISD fee schedule
Chesterfield CountyPermit required$171 for a new single-family dwelling
Fairfax CountyPermit requiredResidential addition or alteration electrical work starts at the $141.75 base...
Fauquier CountyIt dependsA single-trade electrical permit is $84.15 including the technology fee at the...
Henrico CountyPermit requiredExisting-dwelling trade permit fee applies: $100 for the first $5,000 of labor...
Loudoun Countythis pagePermit requiredBase fee for adding, replacing or relocating fixtures, receptacles or circuits...
Orange CountyPermit requiredBilled under the residential Trades category at $0.15 per square foot with a...

How to apply in Loudoun County

In Loudoun County, in most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • For Loudoun County, the written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • For Loudoun County, the application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Loudoun County Department of Building and Development sets the exact checklist for Loudoun County.

Where to apply in Loudoun County:

Loudoun County Department of Building and Development

  • 1 Harrison Street SE, Leesburg, VA 20175
  • Phone: (703) 777-0220

Electrical Permit in Loudoun County compared with nearby Virginia localities

LocalityPermit needed?ThresholdWhat each Virginia schedule saysVerified
Loudoun CountyPermit requiredNot specifiedBase fee for adding, replacing or relocating fixtures, receptacles or circuits in a 1 or...
Arlington CountyPermit requiredLike for like replacement of switches, receptacles, lighting fixtures and similar elements of the same type, size and location is exempt unless located in plenums or penetrating fire rated or smoke protected construction.Fees per FY27 ISD fee schedule
Chesterfield CountyPermit requiredNot specified$171 for a new single-family dwelling
Culpeper CountyIt dependsNot specifiedNot published
Fairfax CountyPermit requiredNot specifiedResidential addition or alteration electrical work starts at the $141.75 base fee for...

Inspections and closing out your permit

In Loudoun County, electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. In Loudoun County: a rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. In Loudoun County: the framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. In Loudoun County: ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. In Loudoun County: arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. In Loudoun County: panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. In Loudoun County: the service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. In Loudoun County: a final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Loudoun County permit portal or by phone at (703) 777-0220.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Loudoun County

In 2024, Loudoun County authorized permits for 3,314 new residential housing units (1,496 single-family, 1,818 in multi-family buildings), valued at $458M, up from 1,782 the year before. That works out to about 7.5 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 443,380.

About Loudoun County

Loudoun County has about 144,804 housing units. The median home is valued at $701,000, against a median household income of $178,707. About 78% of homes are owner-occupied, and the typical home was built around 2002.

Source: U.S. Census Bureau, American Community Survey 2023 5-year.

Frequently asked questions

Do you need an electrical permit in Loudoun County?
An electrical permit is required in Loudoun County for new wiring, outlets, circuits, lighting, and panel upgrades. Contractors must hold a master electrical license and a valid Loudoun County business license. Permit applications are submitted through the LandMARC online portal. The county also requires plan review for some residential fuel gas permits as of October 2025. Always confirm with the Loudoun County Department of Building and Development before starting.
How much does an electrical permit cost in Loudoun County?
Base fee for adding, replacing or relocating fixtures, receptacles or circuits in a 1 or 2 family dwelling is $70; service equipment upgrades are $70 for 0-400 amps or $100 above 400 amps, per the July 2022 fee schedule. See the official fee schedule for current amounts.
Where do you apply for an electrical permit in Loudoun County?
You can apply through the Loudoun County permit portal or contact the Loudoun County Department of Building and Development directly. The links are listed on this page.
Can a homeowner pull an electrical permit themselves in Loudoun County?
Under Virginia law (Va. Code 54.1-1101(A); 13VAC5-63-80 (USBC Sections 108.3, 108.4)): Yes. Va. Code 54.1-1101(A) exempts any person who performs or supervises construction, removal, repair, or improvement of no more than one primary residence owned by them and for their own use during any 24-month period. The exemption covers the whole licensing chapter, including tradesman licensing for electrical, plumbing, and HVAC, so it reaches trade work on the owner's own primary residence. Under the USBC the permit applicant may be the owner or the owner's agent, and an applicant may file a written statement that they are not subject to licensure instead of proof of license. Limits: one primary residence per 24 months, for the owner's own use; rental and investment property work is not covered. Confirm how Loudoun County applies this before you apply.

From the Library

What else needs a permit in Loudoun County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsNot specifiedBilled as a residential alteration: building permit fee is 1% of construction cost plus...
Deck PermitPermit requiredNot specifiedA county-typical (pre-approved design) deck under 1,000 sq ft outside an incorporated...
EV Charger PermitPermit requiredNot specifiedNo EV-specific fee line
Fence PermitNo permit neededNot specifiedTypical residential fences are exempt from the Zoning Permit requirement so no fee applies
HVAC PermitPermit requiredNot specifiedBase Mechanical Permit fee for adding, replacing or relocating central heating or air...
Patio PermitIt dependson-grade concrete or paver patios need no building permit; a permit is required for covered patios, patio covers, or slabs designed to support a future structureNot published
Plumbing PermitPermit requiredNot specifiedBase fee for adding, replacing or relocating plumbing equipment in a 1 or 2 family...
Pool PermitPermit requiredNot specifiedFlat $260 covers both the county building and zoning permit fees for a residential pool...
Roof Replacement PermitIt dependspermit required if replacing more than 256 sq ft of roof decking or making structural changes or changing roofing materialsNo dedicated fee line
Shed PermitIt dependsunder 256 sq ft requires zoning permit only; 256 sq ft or larger requires a building permit in addition to zoning permitZoning-only permit is $165
Solar PermitPermit requiredNot specifiedBuilding permit fee is $230 and electrical permit fee is $70 for rooftop systems
Water Heater PermitIt dependsNot specifiedNo dedicated line

Electrical Permit in other Virginia localities

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Loudoun County documents; the office above sets the local rules.

How this electrical permit page for Loudoun County was verified. 2 official sources: loudoun.gov, loudoun.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Loudoun County Department of Building and Development. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Electrical Permit requirements across Virginia localities

Electrical permit rules nationwide

Look up an existing Loudoun County permit record

Permit required
Get quotes