Virginia / Arlington County

Electrical Permit in Arlington County, Virginia

By Mario Bailey Last checked 2026-07-19 · 3 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

An Electrical Permit is required in Arlington County for adding, removing or relocating fixtures, appliances or wiring for any electrical work. Replacement of these elements with the same type, size and location does not require a permit unless they sit in plenums or penetrate fire rated or smoke protected construction. Applications are submitted online through Permit Arlington, and some projects such as solar panels need a building permit issued first. Further exemptions appear in Section 108.2 of the building code.

Typical threshold: Like for like replacement of switches, receptacles, lighting fixtures and similar elements of the same type, size and location is exempt unless located in plenums or penetrating fire rated or smoke protected construction.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Arlington County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Adding, removing or relocating wiring, fixtures or appliances

What electrical permit costs in Arlington County

Fees per FY27 ISD fee schedule; paid online through Permit Arlington (eCheck free, cards 2.35 percent fee).

Official fee schedule

How Arlington County compares in Virginia

No Virginia jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
Arlington Countythis pagePermit requiredFees per FY27 ISD fee schedule;
Chesterfield CountyPermit required$171 for a new single-family dwelling;
Fairfax CountyPermit requiredResidential addition or alteration electrical work starts at the $141.75 base...
Fauquier CountyIt dependsA single-trade electrical permit is $84.15 including the technology fee at th...
Henrico CountyPermit requiredExisting-dwelling trade permit fee applies: $100 for the first $5,000 of labo...
Loudoun CountyPermit requiredBase fee for adding, replacing or relocating fixtures, receptacles or circuit...
Orange CountyPermit requiredBilled under the residential Trades category at $0.15 per square foot with a...

How to apply in Arlington County

In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.

What most electrical permit applications include:

  • Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
  • The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
  • The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
  • Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
  • Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).

General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Department of Community Planning, Housing and Development, Inspection Services Division sets the exact checklist for Arlington County.

Where to apply in Arlington County:

Department of Community Planning, Housing and Development, Inspection Services Division

Inspections and closing out your permit

Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.

  1. A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
  2. The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
  3. Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
  4. Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
  5. Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
  6. The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
  7. A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Arlington County permit portal or by phone at 703-228-3800.

Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a electrical permit in Arlington County?
An Electrical Permit is required in Arlington County for adding, removing or relocating fixtures, appliances or wiring for any electrical work. Replacement of these elements with the same type, size and location does not require a permit unless they sit in plenums or penetrate fire rated or smoke protected construction. Applications are submitted online through Permit Arlington, and some projects such as solar panels need a building permit issued first. Further exemptions appear in Section 108.2 of the building code. Always confirm with the Department of Community Planning, Housing and Development, Inspection Services Division before starting.
How much does a electrical permit cost in Arlington County?
Fees per FY27 ISD fee schedule; paid online through Permit Arlington (eCheck free, cards 2.35 percent fee). See the official fee schedule for current amounts.
How long does a electrical permit take in Arlington County?
Completeness check within 2 business days; residential review up to 2 business days. Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a electrical permit in Arlington County?
You can apply through the Arlington County permit portal or contact the Department of Community Planning, Housing and Development, Inspection Services Division directly. The links are listed on this page.
Can a homeowner pull a electrical permit themselves in Arlington County?
Under Virginia law (Va. Code 54.1-1101(A); 13VAC5-63-80 (USBC Sections 108.3, 108.4)): Yes. Va. Code 54.1-1101(A) exempts any person who performs or supervises construction, removal, repair, or improvement of no more than one primary residence owned by them and for their own use during any 24-month period. The exemption covers the whole licensing chapter, including tradesman licensing for electrical, plumbing, and HVAC, so it reaches trade work on the owner's own primary residence. Under the USBC the permit applicant may be the owner or the owner's agent, and an applicant may file a written statement that they are not subject to licensure instead of proof of license. Limits: one primary residence per 24 months, for the owner's own use; rental and investment property work is not covered. Confirm how Arlington County applies this before you apply.

From the Library

What else needs a permit in Arlington County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitPermit requiredNo size exemption is published for decks; new decks and deck modifications are treated as additions requiring a Residential Building Permit.Fees per FY27 ISD fee schedule;
Fence PermitPermit requiredArlington requires a fence permit for any new or replacement fence not part of a larger permitted project; the state building code exempts fences from a building permit unless they serve as a swimming pool barrier or are required for pedestrian safety.Fees per FY27 Planning and Zoning fee schedule;
HVAC PermitPermit requiredReplacement of mechanical equipment of the same type, size and location is exempt unless the equipment is fueled by gas, in which case a Plumbing/Gas Permit is required; outdoor equipment locations still need zoning approval.Fees per FY27 ISD fee schedule;
Patio PermitIt dependsArlington lists no patio building permit type; a Land Disturbing Activity/Stormwater permit is required when total land disturbance equals or exceeds 2,500 square feet.LDA/SWM fees per FY27 DES fee schedule;
Plumbing PermitPermit requiredReplacement of fixtures, appliances or piping of the same type, size and location on equipment not fueled by gas is exempt; work on gas fueled equipment always requires a permit and inspections.Fees per FY27 ISD fee schedule plus DES drainage fixture unit fees where applicable;
Pool PermitIt dependsUnder USBC 108.2 a swimming pool is exempt only when its surface area is not greater than 150 square feet and it is less than 24 inches deep; otherwise building and trade permits are required.Fees per FY27 ISD fee schedule;
Roof Replacement PermitIt dependsReplacing roof covering alone or with less than 256 square feet of roof decking replaced needs no permit; replacing more than 256 square feet of decking requires a building permit, and decking originally required to be fire retardant treated always requires a permit.Fees per FY27 ISD fee schedule;
Shed PermitIt dependsOne story detached tool and storage sheds, playhouses and similar structures are exempt from a building permit when the building area does not exceed 256 square feet.Fees per FY27 ISD fee schedule;
Solar PermitPermit requiredResidential solar electric systems require both an electrical permit and a building permit; no size exemption is published.Fees per FY27 ISD fee schedule;

Electrical Permit in other Virginia localities

Official sources

Verified by a person against the sources above on 2026-07-19, not confirmed with Department of Community Planning, Housing and Development, Inspection Services Division. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-19Report an error on this page