Solar Permit in Pima County, Arizona

By Mario Bailey Last checked 2026-07-06 · 2 official sources

Verified against official sources Confirmed on official page

Permit required

Quick answer

A building permit is required for residential photovoltaic systems in unincorporated Pima County; the county's "Do I Need a Permit?" list confirms "Photovoltaic systems or generators" require a permit. Eligible rooftop installations on a main dwelling can use the SolarAPP automated same-day review process via GoSolarApp.org, provided the parcel is in unincorporated Pima County, the system is on a permitted residential structure, the system is not ballasted, and the property is not in an environmentally sensitive area, hillside development zone, or flood hazard area (owner-owned systems in flood hazard areas require traditional plan review instead). A $94 permitting fee is charged once the permit is issued, in addition to any SolarAPP processing fee. Arizona A.R.S. Section 11-323 sets statewide processing standards for county solar permits (standardized submittal content, limits on requiring a PE stamp, and permission to use an automated permitting platform such as SolarAPP+) that underlie this process, but the permit requirement itself is established by Pima County.

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?
  • Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help

Tell us where your project stands. Free to ask; no obligation.

Where we have a vetted local pro who handles permits in Pima County, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

When a permit is usually needed

Before installing any residential rooftop photovoltaic solar system in unincorporated Pima County

What solar permit costs in Pima County

Residential photovoltaic installation is treated as minor electrical work, flat fee $27, per the Development Services Fee Schedule effective 2026-07-01.

Official fee schedule

How Pima County compares in Arizona

No Arizona jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.

JurisdictionPermit needed?Typical fee
ChandlerPermit requiredFlat $150 fee for a residential solar photovoltaic system permit and a separa...
GilbertIt dependsNo Town permit fee when the licensed-contractor exemption applies;
Maricopa CountyPermit requiredRoof-mounted residential solar is printed at $300 ($150 inspection plus $140...
MesaPermit requiredMost residential rooftop solar under 10,000 sq ft installed by a licensed Ari...
PeoriaPermit requiredResidential Solar Photovoltaic Permit is 184 dollars for a 40 amp circuit or...
PhoenixPermit requiredResidential solar photovoltaic permits use fixed-fee options from $780 with p...
Pima Countythis pagePermit requiredResidential photovoltaic installation is treated as minor electrical work, fl...

How to apply in Pima County

A rooftop solar PV permit application is a combined structural and electrical plan set: a site plan and roof framing details proving the array's mounting can carry its added loads, plus a one line electrical diagram covering listed modules and inverters, disconnects, and the rapid shutdown design. Utility interconnection is a separate approval that runs in parallel with the permit.

What most solar permit applications include:

  • Both a building permit and a separate electrical permit are required, since the array must be designed and installed to the residential code's solar provisions and to the National Electrical Code (IRC R324.3).
  • The plan set identifies listed equipment: PV modules listed to UL 1703 (or both UL 61730-1 and UL 61730-2), and inverters listed to UL 1741, with grid-tied inverters listed for utility interaction (IRC R324.3.1).
  • Structural drawings show that the roof framing is designed to structurally support the array and withstand the gravity loads it adds (IRC R324.4.1).
  • The site plan lays out roof access pathways at least 36 inches wide, plus a ridge setback sized to how much of the roof the array covers, so firefighters retain pathways and ventilation access (IRC R324.6.1, IRC R324.6.2).
  • The one line electrical diagram shows the rapid shutdown method and the location of its single initiation device, since one control point must bring all system conductors down to safe levels (NEC 690.12, NEC 690.56(C)).
  • Interconnecting the array to the utility grid at a defined point of connection is a separate application process from the local building or electrical permit and must be approved before the system can operate (NEC 705.12).
  • Some permitting offices route applications through SolarAPP+, an automated review platform that checks the plan set against code requirements and issues eligible permits instantly (DOE SolarAPP+).

General submittal guidance from IRC 2021 R324 (Solar Energy Systems) and NEC 2020 Article 690 (Solar Photovoltaic Systems) and Article 705 (Interconnected Power Production Sources). Source. Pima County Development Services Department sets the exact checklist for Pima County.

Where to apply in Pima County:

Pima County Development Services Department

  • 201 N. Stone Ave., Tucson, AZ 85701
  • Phone: 520-724-9000

Inspections and closing out your permit

Inspectors verify the installed array against the approved plans, and some agencies run a rough check of roof attachments and penetrations while they are still exposed before the wiring and roofing close them in. The final inspection confirms rapid shutdown, disconnects, grounding, and required labels are installed correctly, and the system cannot be energized until the utility separately approves interconnection.

  1. Where an agency runs a rough or pre-inspection, it checks the array's roof penetrations while they are still exposed, confirming they are flashed and sealed (IRC R324.4.3).
  2. The inspector confirms whether rapid shutdown is required, how it is accomplished, and that it is properly identified (NEC 690.12, NEC 690.56(C)).
  3. PV disconnecting means must be permanently marked and installed where they are readily accessible, which the inspector confirms in the field (NEC 690.13).
  4. Bonding and grounding of the array, including every exposed non current carrying metal part and the grounding electrode system, is checked before sign off (NEC 690.43, NEC 690.47).
  5. At the service equipment, the inspector looks for the required rapid shutdown placard, a labeled diagram showing the initiation device's location in the specified colors and letter sizes (NEC 690.56(C)).
  6. Utility interconnection is inspected and approved separately from the local building department's sign off, and the system cannot be energized until both approvals are in hand (NEC 705.12).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Pima County permit portal or by phone at 520-724-9000.

Inspection sequence from NEC 2020 Article 690 (690.12 rapid shutdown, 690.13 disconnects, 690.43/690.47 grounding, 690.56 labeling) and IRC 2021 R324.4.3 (roof penetrations). Source. An open permit left un-inspected can surface later in a title search or home sale.

Frequently asked questions

Do you need a solar permit in Pima County?
A building permit is required for residential photovoltaic systems in unincorporated Pima County; the county's "Do I Need a Permit?" list confirms "Photovoltaic systems or generators" require a permit. Eligible rooftop installations on a main dwelling can use the SolarAPP automated same-day review process via GoSolarApp.org, provided the parcel is in unincorporated Pima County, the system is on a permitted residential structure, the system is not ballasted, and the property is not in an environmentally sensitive area, hillside development zone, or flood hazard area (owner-owned systems in flood hazard areas require traditional plan review instead). A $94 permitting fee is charged once the permit is issued, in addition to any SolarAPP processing fee. Arizona A.R.S. Section 11-323 sets statewide processing standards for county solar permits (standardized submittal content, limits on requiring a PE stamp, and permission to use an automated permitting platform such as SolarAPP+) that underlie this process, but the permit requirement itself is established by Pima County. Always confirm with the Pima County Development Services Department before starting.
How much does a solar permit cost in Pima County?
Residential photovoltaic installation is treated as minor electrical work, flat fee $27, per the Development Services Fee Schedule effective 2026-07-01. See the official fee schedule for current amounts.
Where do you apply for a solar permit in Pima County?
You can apply through the Pima County permit portal or contact the Pima County Development Services Department directly. The links are listed on this page.

From the Library

What else needs a permit in Pima County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Deck PermitIt dependsDecks and non-structural flat work not more than 30 inches above adjacent grade, not over any basement or story below, and not part of an accessible route do not require a permit; a deck greater than 30 inches above finished grade or floor level requires a permit.Assessed as a building permit: base fee $69 plus 1.096% of the ICC square foot construc...
Electrical PermitIt dependsNew electric outlet/fixture installations and photovoltaic systems or generators require a permit; wiring/devices operating under 25 volts and not exceeding 50 volt-amps, and like-for-like repair or replacement of switches, controls, overcurrent devices, fixed motors, transformers, or outlets/fixtures in the same location, do not.Flat fee tiered by scope: minor work such as a service upgrade, reconnect, or up to fiv...
Fence PermitIt dependsNon-retaining walls and fences no more than 7 feet in height do not require a permit; fences taller than 7 feet require a building permit.Fee is $0.25 per lineal foot plus the standard $69 base permit fee, per the Development...
HVAC PermitIt dependsNew or replacement central air conditioners/furnaces, mini-split systems, and modifying or replacing duct work require a permit; portable cooling, heating, or ventilation units, and replacing an existing evaporative cooler with a like unit, do not.Flat fee tiered by scope: minor work such as a residential air conditioner unit is $27,...
Patio PermitIt dependsAn open, ground-level patio slab counts as non-structural flat work not more than 30 inches above adjacent grade and does not require a permit; enclosing a porch or patio (adding walls, screens, or a roof enclosure) requires a permit.No patio-specific line;
Plumbing PermitIt dependsNew pipe work, propane tanks, septic systems, sewer connections, solar water heaters, water heater replacement, and new dishwashers require a permit; clearing stoppages or repairing leaks that do not involve replacing valves, pipes, or fixtures, fixture swaps (sinks, toilets, tubs), and grade-supported water tanks up to 5,000 gallons do not.Flat fee tiered by scope: minor work such as a water heater or a gas, water, or drain l...
Pool PermitIt dependsPre-fabricated residential pools installed entirely above ground require a building permit once they exceed 18 inches in depth and 5,000 gallons; any in-ground or custom-built residential pool or spa requires a building permit through Administrative Review regardless of size.Not published
Roof Replacement PermitIt dependsRe-roofing with like materials (tile, shingles, etc.) does not require a permit; structural roof work requires a permit.No fee for re-roofing with like materials since no permit is required per the county's...
Shed PermitIt dependsOne-story detached tool and storage sheds, playhouses, and similar non-habitable accessory structures are the category Pima County's own adopted code amendments refer to as "structures exempted from permits"; the standard exemption size carried in the adopted IRC for this category is 200 sq ft with no electrical, plumbing, or mechanical connections, though Pima's own published guidance pages do not restate that figure directly.No shed-specific line;

Solar Permit in other Arizona localities

Official sources

Verified by a person against the sources above on 2026-07-06, not confirmed with Pima County Development Services Department. Rules change; confirm before you build. How we verify.

Last checked: 2026-07-06Report an error on this page