Pool Permit in Tacoma, Washington
By Mario Bailey Last checked 2026-06-18 · 2 official sources
Verified against official sources From an official sourceIt depends
Quick answer
In Tacoma prefabricated above-ground swimming pools that are less than 24 inches deep and no greater than 5,000 gallons are exempt from a building permit. All in-ground pools and larger above-ground pools require a building permit from Planning and Development Services. Pool fencing and safety barriers are required regardless of permit status.
Typical threshold: prefabricated above-ground pools less than 24 inches deep and not greater than 5000 gallons are exempt; all other pools require a building permit.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Tacoma, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
Before installing any pool except small exempt above-ground prefabricated units in Tacoma
What your pool permit must meet in Washington
Washington's 2021 Residential Code (WAC 51-51, effective statewide March 15, 2024) requires backyard swimming pools, spas, and hot tubs at single-family and duplex homes to be designed and built to the 2021 International Swimming Pool and Spa Code, incorporated by direct statewide reference rather than left to local option.
- The design and construction of swimming pools, spas, and other aquatic recreation facilities must comply with the 2021 International Swimming Pool and Spa Code whenever the facility falls into one of three defined residential categories (WAC 51-51-0327).
- That mandatory ISPSC standard covers pools for the sole use of a single-family dwelling's residents and guests, the sole use of a resident-owned duplex, or a facility used exclusively for medical physical therapy under a licensed practitioner's supervision (WAC 51-51-0327).
- Any other water recreation facility outside those residential categories is regulated under separate Washington Department of Health rules, not the Residential Code (WAC 246-260; WAC 51-50-3109).
Based on 2021 International Swimming Pool and Spa Code (ISPSC), incorporated by WAC 51-51-0327 into the 2021 Washington State Residential Code. Read the code. Local amendments can be stricter; confirm the current requirement with your office before you build.
What pool permit costs in Tacoma
Pools 24 inches deep or more need a permit priced from $55 for the first $500 of valuation plus $32 per $100 over $500, per the PDS Fee Schedule effective 1/1/2025.
How Tacoma compares in Washington
| Jurisdiction | Permit needed? | Threshold |
|---|---|---|
| Bellevue | It depends | swimming pools over 24 inches deep require a permit with plan review; above-ground pools 24 inches or less may be exempt |
| Clark County | It depends | A permit is required for any structure intended for swimming or recreational bathing that contains water over 24 inches deep, including in-ground, aboveground and on-ground pools, hot tubs and spas. |
| King County | It depends | prefabricated above-ground pools less than 24 inches deep and not exceeding 5000 gallons are exempt; all other pools require a building permit in unincorporated King County |
| Pierce County | It depends | Prefabricated swimming pools accessory to a single family residence (Group R-3 occupancy) are exempt if less than 24 inches deep, with no separate gallon volume cap; in-ground pools and pools 24 inches deep or deeper require a building permit. Self-contained spas and hot tubs installed entirely above ground and not connected to the potable water system or a septic or sewer drain are separately exempt regardless of depth. |
| Snohomish County | It depends | prefabricated swimming pools regulated under the IRC (one- and two-family dwellings) exempt if less than 24 inches deep, with no gallon-volume cap; in-ground pools or pools 24 inches deep or more require a building permit |
| Tacomathis page | It depends | prefabricated above-ground pools less than 24 inches deep and not greater than 5000 gallons are exempt; all other pools require a building permit |
| Thurston County | It depends | Pools are exempt only if prefabricated, entirely above ground, less than 24 inches deep, and under 5,000 gallons capacity. |
Closest pool permit thresholds outside Washington
Jurisdictions we cover whose limit sits nearest Tacoma's 24 inches.
- Lee County, Florida, All in-ground pool construction or renovation requires a permit; an above-ground pool requires a permit when its water depth is 24 inches or more.
- Palm Beach County, Florida, Portable or manufactured pools and spas less than 24 inches deep need no permit; all in-ground pools, larger above-ground pools, and spas require a Building Permit (Type 3(E) for 1 and 2 unit dwellings) plus applicable electrical, plumbing, and pool-barrier sub-permits, and must satisfy Florida's residential pool safety-feature requirements under F.S. 515.27 before final inspection.
- Polk County, Florida, In-ground pools and spas always require a permit; above-ground pools and spas require one only when more than 24 inches deep.
- Virginia Beach, Virginia, Permits are required for pools, hot tubs, and spas holding 24 inches or more of water; state code exempts only pools with a surface area of 150 square feet or less that are under 24 inches deep.
How to apply in Tacoma
A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect.
What most pool permit applications include:
- Pool and spa design and construction fall under the residential code chapter that folds in the swimming pool and spa code, and permit review checks plans against that chapter (IRC R326).
- The site plan must show pool equipment such as pumps, filters, and heaters set back at least 36 inches from the outside of the required barrier (ISPSC 305.2.9).
- For an in-ground pool, engineered structural plans covering the shell and reinforcing steel, with the responsible structural engineer's license information, are a standard part of the submittal (per official pool submittal checklists).
- A barrier plan identifying the fence, pool structure, or dwelling wall that will enclose the pool must be submitted and must comply with the code's barrier chapter (ISPSC 305).
- Electrical plans must show the pool's equipotential bonding design, since the shell, perimeter surfaces, and metal fittings within 5 feet of the water must all tie into a common bonding grid (NEC 680.26).
- The electrical plan must also show a disconnecting means for the pool equipment that is readily accessible and within sight of the equipment (NEC 680.13).
General submittal guidance from 2021 IRC R326 (adopting the ISPSC), ISPSC 2021 Section 305, and NEC 2020 Article 680. Source. City of Tacoma Planning and Development Services sets the exact checklist for Tacoma.
Where to apply in Tacoma:
City of Tacoma Planning and Development Services
- 747 Market Street Third Floor, Tacoma, WA 98402
- Phone: (253) 591-5030
- Email: Permits@tacoma.gov
Inspections and closing out your permit
Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
- Before gunite or shotcrete is sprayed, the inspector checks the rebar against the engineered plans and confirms the equipotential bonding wire is stubbed out and tied into the steel, since it will be buried in concrete afterward (NEC 680.26).
- A bonding inspection separately confirms coping, decking, ladders, handrail cups, and any other metal within 5 feet of the water are tied to the bonding grid, and it must pass before coping is installed (NEC 680.26).
- A temporary barrier at least 4 feet high must enclose the site from the moment excavation starts until the permanent barrier is finished, and inspectors check for it throughout construction (ISPSC 305.1.1).
- A pre-plaster inspection confirms the circulation equipment's electrical work is installed and all bonding is complete before the pool's interior finish goes on (NEC 680.26).
- At final inspection the permanent barrier is checked against the code's requirements and the equipment and cover-mechanism bonding must be complete before the pool can be filled and used (ISPSC 305, NEC 680.26).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Tacoma permit portal or by phone at (253) 591-5030.
Inspection sequence from NEC 2020 Article 680.26 (equipotential bonding) and ISPSC 2021 Section 305 (barriers). Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Pool Permit checklist for Tacoma
- Confirm the requirement. Sometimes, depending on the project. Typical threshold: prefabricated above-ground pools less than 24 inches deep and not greater than 5000 gallons are exempt; all other pools require a building permit. Usually needed: Before installing any pool except small exempt above-ground prefabricated units in Tacoma.
- Budget the fee. Pools 24 inches deep or more need a permit priced from $55 for the first $500 of valuation plus $32 per $100 over $500, per the PDS Fee Schedule effective 1/1/2025. Official fee schedule.
- Apply. A residential pool permit application covers both construction and safety: a scaled site plan, structural plans for the pool, a barrier plan showing how the pool will be enclosed, and an electrical plan covering bonding and the equipment disconnect. Start at the Tacoma permit portal.
- Keep the office details handy. City of Tacoma Planning and Development Services. Phone: (253) 591-5030. Address: 747 Market Street Third Floor, Tacoma, WA 98402.
- Plan for inspections. Pool inspections track the concrete pour: the steel and bonding grid are checked before gunite or shotcrete goes in, bonding is checked again before decking is poured, and the permanent barrier and remaining electrical work are checked at final before the pool can be filled and used.
Compiled from the official sources on this page. Last checked 2026-06-18.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Tacoma
In 2024, Tacoma authorized permits for 402 new residential housing units (137 single-family, 265 in multi-family buildings), valued at $99M, down from692 the year before. That works out to about 1.8 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 219,945.
About Tacoma
Tacoma has about 96,151 housing units. The median home is valued at $454,600, against a median household income of $83,857. About 56% of homes are owner-occupied, and the typical home was built around 1967.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a pool permit in Tacoma?
- In Tacoma prefabricated above-ground swimming pools that are less than 24 inches deep and no greater than 5,000 gallons are exempt from a building permit. All in-ground pools and larger above-ground pools require a building permit from Planning and Development Services. Pool fencing and safety barriers are required regardless of permit status. Prefabricated above-ground pools less than 24 inches deep and not greater than 5000 gallons are exempt; all other pools require a building permit. Always confirm with the office before starting.
- How much does a pool permit cost in Tacoma?
- Pools 24 inches deep or more need a permit priced from $55 for the first $500 of valuation plus $32 per $100 over $500, per the PDS Fee Schedule effective 1/1/2025. See the official fee schedule for current amounts.
- Where do you apply for a pool permit in Tacoma?
- You can apply through the Tacoma permit portal or contact the City of Tacoma Planning and Development Services directly. The links are listed on this page.
From the Library
What else needs a permit in Tacoma
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | freestanding decks not exceeding 200 sq ft and not more than 30 inches above grade are exempt; decks over 200 sq ft, over 30 inches above grade, or attached to the dwelling require a permit | Decks bill as an addition at 2.81 percent of ICC building valuation, with uncovered woo... |
| Electrical Permit | Permit required | Not specified | No Planning and Development Services fee; |
| Fence Permit | It depends | fences 7 feet or under in height do not require a building permit; fences over 7 feet require a permit | Only fences over 7 feet or masonry walls over 4 feet need a building permit, priced fro... |
| HVAC Permit | Permit required | Not specified | Standalone HVAC and mechanical permits run 2.81 percent of construction value with a $1... |
| Patio Permit | It depends | at-grade flatwork such as sidewalks and driveways is exempt from a building permit, though separate site-development permits can apply; covered patios require a building permit | Patio covers bill as an addition at 2.81 percent of ICC building valuation, per the PDS... |
| Plumbing Permit | Permit required | Not specified | Standalone plumbing permits run 2.81 percent of construction value with a $180 minimum... |
| Roof Replacement Permit | It depends | removing and replacing existing roof coverings with the same type does not require a permit; adding a layer or changing roofing materials requires a permit and pre-roof inspection | Reroofs outside the tear-off exemption bill as a remodel at 2.81 percent of ICC buildin... |
| Shed Permit | It depends | one-story detached accessory structures with a floor area of 200 square feet or less do not require a building permit; structures over 200 square feet require a permit | Sheds 200 square feet or larger need a permit priced from $55 for the first $500 of val... |
| Solar Permit | Permit required | Not specified | Solar panel installation bills as a remodel at 2.81 percent of ICC building valuation w... |
Pool Permit in other Washington localities
Official sources
- https://www.tacomapermits.org/tip-sheet-index/what-requires-a-permit
- https://tacoma.gov/government/departments/planning-and-development-services/permits-and-development-services/
- https://www.bountifulutah.gov/file/ee478521-f791-4cee-a755-2d923ff70257
- https://app.leg.wa.gov/wac/default.aspx?cite=51-51-0327
Verified by a person against the sources above on 2026-06-18, not confirmed with City of Tacoma Planning and Development Services. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-18Report an error on this page
Compare Pool Permit requirements across Washington localities
Washington rule changes
- Bellevue, WA sets a flat $290 re-roof permit fee (Ordinance 6879)
Ord. 6879 · 2026-07-25