Residential electrical permits in Seattle are issued by SDCI not by Washington State L&I. A permit is required for adding or moving circuits and for service panel changes. Many electrical permits are issued the same day through the Seattle Services Portal. Three inspections are typically required: cover, service, and final.
Who is pulling this permit?
Apply yourself
Hire it out
Before you sign, ask the contractor:
- Who pulls the permit, you or me, and is the permit fee included in the bid?
- Which inspections will this job need, and who meets the inspector on site?
- Is your contractor license active in this locality, and under which business name?
Want a pro to handle this permit? Request free help
Tell us where your project stands. Free to ask; no obligation.
Where we have a vetted local pro who handles permits in Seattle, we connect you; otherwise we reply with the exact steps and office links for your situation. PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
When a permit is usually needed
For all residential electrical work including new circuits and panel upgrades in Seattle
What electrical permit costs in Seattle
Itemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online self-issued permit plus a $55.48 administrative fee per permit, new or altered service up to 125 amps $146, 150 to 200 amps $292, branch circuit or feeder up to 200 amps $146, all plus a 5% technology fee, per the 2026 Fee Subtitle.
How Seattle compares in Washington
No Washington jurisdiction we have verified sets a size threshold for this permit, so what actually differs between them is the fee.
| Jurisdiction | Permit needed? | Typical fee |
|---|---|---|
| Bellevue | Permit required | Electrical permit fee by valuation per Table 6 of Ordinance 6879, $79 inspect... |
| Clark County | Permit required | No county fee; |
| King County | Permit required | Set by state L&I, not King County, under WAC 296-46B-906 (effective 7/1/2026)... |
| Pierce County | Permit required | No county fee; |
| Seattlethis page | Permit required | Itemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online s... |
| Snohomish County | Permit required | No county fee; |
| Tacoma | Permit required | No Planning and Development Services fee; |
How to apply in Seattle
In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished.
What most electrical permit applications include:
- Before any electrical work begins, the owner or an authorized agent must first apply to the building official and obtain the required permit (IRC R105.1).
- The written application must identify and describe the electrical work covered by the permit and describe the property, such as by street address, well enough to locate the job (IRC R105.3).
- The application must be accompanied by construction documents (plans) and any other information the permit office requires, and must be signed by the applicant or an authorized agent (IRC R105.3).
- Certain minor or like-for-like electrical jobs, such as replacing a branch-circuit breaker of the required capacity in the same location, are commonly exempt from needing a separate permit (IRC R105.2).
- Once issued, the building permit or a copy of it must be kept at the job site until the project is complete (IRC R105.7).
General submittal guidance from International Residential Code (IRC), Section R105, Permits (2015 and 2021 editions, as locally adopted). Source. Seattle Department of Construction and Inspections sets the exact checklist for Seattle.
Where to apply in Seattle:
Seattle Department of Construction and Inspections
- 700 5th Ave Suite 2000, Seattle, WA 98104
- Phone: (206) 684-8600
Inspections and closing out your permit
Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
- A rough-in inspection of the electrical wiring is required before it is covered or concealed by insulation, drywall, or other finish material, and before fixtures or appliances are set (IRC R109.1.2).
- The framing inspection cannot proceed until the plumbing, mechanical, and electrical rough-in inspections have all been approved (IRC R109.1.4).
- Ground-fault circuit-interrupter (GFCI) protection is checked at receptacles in bathrooms, kitchens, garages, basements, crawl spaces, outdoors, and other damp or wet locations (NEC 210.8(A)).
- Arc-fault circuit-interrupter (AFCI) protection is verified on branch circuits serving bedrooms, living areas, and most other habitable rooms (NEC 210.12(A)).
- Panelboards must carry a circuit directory that legibly and specifically identifies the purpose of each circuit, not a vague label (NEC 408.4).
- The service disconnect must be installed in a readily accessible location, either outside the structure or just inside the point where the service conductors enter (NEC 230.70).
- A final inspection is made only after all permitted electrical work is complete, and the wiring cannot be used or the space occupied until it passes (IRC R109.1.6).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Seattle permit portal or by phone at (206) 684-8600.
Inspection sequence from International Residential Code (IRC), Section R109, Required Inspections, and NFPA 70 National Electrical Code (NEC), 2020 and 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your Electrical Permit checklist for Seattle
- Confirm the requirement. Yes, a permit is required. Usually needed: For all residential electrical work including new circuits and panel upgrades in Seattle.
- Budget the fee. Itemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online self-issued permit plus a $55.48 administrative fee per permit, new or altered service up to 125 amps $146, 150 to 200 amps $292, branch circuit or feeder up to 200 amps $146, all plus a 5% technology fee, per the 2026 Fee Subtitle. Official fee schedule.
- Apply. In most US jurisdictions, the property owner or a licensed electrician applies for an electrical permit before work starts, describing the scope of work and the property and typically attaching plans. Some minor, like-for-like electrical repairs are commonly exempt, and once issued the permit is kept on site until the job is finished. Start at the Seattle permit portal.
- Keep the office details handy. Seattle Department of Construction and Inspections. Phone: (206) 684-8600. Address: 700 5th Ave Suite 2000, Seattle, WA 98104.
- Plan for inspections. Electrical work under a permit is inspected at least twice: a rough-in inspection of the wiring before it is covered by drywall or insulation, and a final inspection once all devices, panels, and labeling are complete. Inspectors also check specific safety items along the way, such as GFCI and AFCI protection, panel circuit directories, and the service disconnect location.
Compiled from the official sources on this page. Last checked 2026-06-18.
The checklist stays on this page either way. We may send occasional verified rule-change notes for your area; unsubscribe anytime. See our privacy policy.
Permitting activity in Seattle
In 2024, Seattle authorized permits for 5,895 new residential housing units (405 single-family, 5,490 in multi-family buildings), valued at $1.2B, up from5,299 the year before. That works out to about 7.7 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2024 annual data · population 769,714.
About Seattle
Seattle has about 382,933 housing units. The median home is valued at $912,100, against a median household income of $121,984. About 44% of homes are owner-occupied, and the typical home was built around 1974.
Source: U.S. Census Bureau, American Community Survey 2023 5-year.
Frequently asked questions
- Do you need a electrical permit in Seattle?
- Residential electrical permits in Seattle are issued by SDCI not by Washington State L&I. A permit is required for adding or moving circuits and for service panel changes. Many electrical permits are issued the same day through the Seattle Services Portal. Three inspections are typically required: cover, service, and final. Always confirm with the Seattle Department of Construction and Inspections before starting.
- How much does a electrical permit cost in Seattle?
- Itemized per Fee Subtitle Table D-15: minimum $105.12 for a standard online self-issued permit plus a $55.48 administrative fee per permit, new or altered service up to 125 amps $146, 150 to 200 amps $292, branch circuit or feeder up to 200 amps $146, all plus a 5% technology fee, per the 2026 Fee Subtitle. See the official fee schedule for current amounts.
- Where do you apply for a electrical permit in Seattle?
- You can apply through the Seattle permit portal or contact the Seattle Department of Construction and Inspections directly. The links are listed on this page.
From the Library
What else needs a permit in Seattle
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Deck Permit | It depends | decks more than 18 inches above grade require a permit; decks 18 inches or less above grade and not over a basement do not require a permit | Priced as a subject-to-field-inspection or addition/alteration construction permit by p... |
| Fence Permit | It depends | fences under 8 feet with no masonry or concrete elements exceeding 6 feet do not require a permit | Fences 8 feet or less with no masonry or concrete elements over 6 feet need no permit p... |
| HVAC Permit | Permit required | Not specified | Ducted HVAC systems are priced by project valuation with a $292 minimum; |
| Patio Permit | No permit needed | Not specified | No standalone patio permit; |
| Plumbing Permit | Permit required | Not specified | No SDCI fee; |
| Pool Permit | Permit required | Not specified | An unenclosed pool accessory to a single-family or duplex home is a flat fee of four ti... |
| Roof Replacement Permit | No permit needed | Not specified | One and two family homes need no permit for a straight reroof that does not change the... |
| Shed Permit | It depends | one-story detached storage sheds with a roof footprint of 120 square feet or less on a slab foundation and not in an environmentally critical area do not require a permit | Sheds of 120 square feet or less that are single story, unattached, and storage-only ne... |
| Solar Permit | Permit required | Not specified | Solar PV is permitted through the electrical permit: systems below 12kW are a flat $438... |
Electrical Permit in other Washington localities
Official sources
Verified by a person against the sources above on 2026-06-18, not confirmed with Seattle Department of Construction and Inspections. Rules change; confirm before you build. How we verify.
Last checked: 2026-06-18Report an error on this page
Compare Electrical Permit requirements across Washington localities
Washington rule changes
- Bellevue, WA sets a flat $290 re-roof permit fee (Ordinance 6879)
Ord. 6879 · 2026-07-25